Duncan (Feasibility Studies)
Duncan (Feasibility Studies)
UNIT
EACR 4197 (2 UNITS – 96HRS)
SUPERVISED BY:
QS. MICHAEL ACHIENG.
DR. LAWRENCE MBUGUA.
MR. EDWARD MBUGUA.
1
TABLE OF CONTENTS
4
LIST OF FIGURES
Fig 1. Map showing Kenya and the Capital City. Source: IEBC ……………………….….…...
…...10 Fig 2. Map showing Nairobi City County. Highlighting Sub-Counties. Source:
Constituency. Source: IEBC……....11 Fig 4. Satellite Image of TUK Ground, also showing access to
the site. Source: Google Map…….….11 Fig 5. Image showing Akiba Bellevue estate to the south of
TUK grounds ……….…………………12 Fig 6. Image showing CID Residence to the north of
the east of TUK grounds ……………...……...….13 Fig 8. Satellite Image showing 15.0m wide
access road to the site. Source: Google Map…………….13 Fig 9. Image showing 15.0m wide cabro
paved access road on the southern side to the site……......14 Fig 10. Image showing 15.0m wide
cabro paved access road on the western side to the site ......…….14 Fig 11. Image showing existing
showing drainage channel along access point on the western side to the site …….…...16 Fig 14.
Image showing street lights along access point on the western side to the site ...……….….…17 Fig
………......18 Fig 17. Image showing indigenous tree along the site 5
boundary
………………………………......…18 Fig 18. Image showing cynodon dactylon grass species and
…………………………………….….….21
Fig 22. Image showing Guard House at the main entry gate to the proposed site ………………....…
21 Fig 23. Image showing 2.2m high boundary wall on the western side of the site
…………………….22 Fig 24. Image showing 2.2m high boundary wall at the site
the site ………………………...…………………….23 Fig 27. Image showing main entry gate and
pedestrian gate at the site ………..…………………….24 Fig 28. Plate showing zoning regulations.
6
LIST OF ABBREVIATIONS AND ACRONYMS USED
CM Construction Manager
FIG Figure
REF Reference
PM Project Manager
P. I Profitability Index
QS Quantity Surveyor
7
ABSTRACT
The need for infrastructure and other amenities has for long remained insatiable. The growing
population is constantly requiring services such as schools, recreation facilities, rental
apartments, hotels among others. Most significantly, the needs will be adequately met through
development which shouldalso be carried out in a sustainable manner. Institutions can undertake
investment options to address the various societal needs, and at the same time, generate revenue
to meet its needs andrequirements.
Enhances the probability of success by addressing and mitigating factors early on that
could affect the project;
8
CHAPTER ONE
INTRODUCTION
Infrastructure refers to basic fundamental structures needed by a nation or entity for the
growing population that constantly require the services. They include services such as hotels,
rental apartment, hospitals, commercial car park, schools, recreation facilities, among many
others. These infrastructure services are critical to a nation or entity performance and
survival. Institutions can undertake investment options to address the various societal needs, and
at the same time, generate revenue to meet its needs andrequirements.
CLIENT’S BRIEF
The Technical University of Kenya has been having perennial financial problems. The
University has been receiving less capitation from the exchequer (Kenya government), which has
made the running of operations as well as paying the human resources a challenge. Therefore,
the university has been considering a variety of investment options, which can aid in enabling it
meet its financial obligations.
The Management at the University has been considering strategies to counter persistentfinancial
problems. Below options were suggested as investment options:
Rental Apartments.
Recreational Complex.
9
SITE DESCRIPTION
The Proposed site is located in the southern part of Nairobi County in South C, opposite KEBS
and adjacent to Toyota Kenya Academy. It is off Mombasa Road along Popo Road. The site is
approximately 7km from Nairobi CBD. The piece of land is nine (9) acres and approximately
200m long by 250m wide (50. 00SQ.M)
Fig 4. Satellite Image of TUK South C Ground, also showing access to the site. Source: Google
Map
11
SITE ANALYSIS
Akiba Bellevue estate is a controlled residential estate composed of 3 and 4 bedrooms town
houses located on the south of TUK grounds. Below is an image showing the view of the estate.
Fig 5. Image showing Akiba Bellevue estate to the south of TUK grounds.
B) CID Residence
Criminal Investigation Department (C.I.D) Training School of the Kenya is a national body in
charge of law enforcement in Kenya. It is subordinate to National Police Service which is headed
by Inspector General of Police. It is located to the North of TUK grounds. Below is the view of
CID residence.
Toyota Kenya Academy is a human resource development center with the aim of not only
supporting Toyota Staff but also implement human resource training for local communities. This
Center is in line with the Governments Vision 2030 Social Pillar aims to invest in the people of
Kenya in order to improve the quality of life through education and training. It is located to the
East of TUK grounds. Below is the view of the Toyota Kenya Academy.
Fig 7. Image showing Toyota Kenya Academy to the east of TUK grounds.
Infrastructure
The site is bordered by two roads. On the southern side is a 15.0m wide cabro paved service lane
linking both TUK grounds and Toyota Kenya Academy and on the west is also 15.0m wide
existing cabro paved access road to the proposed site.
Fig 8. Satellite Image showing highlighted 15.0m wide access road to the site. Source: Google
Map 13
Fig 9. Image showing 15.0m wide cabro paved access road on the southern side to the
site.
Fig 10. Image showing 15.0m wide cabro paved access road on the western side to the
site.
Recommendations
14
B) Electricity Powerline
The site is currently not served by electricity, but there is an existing electricity powerline
(Three-phase) from the Kenya power and lighting company.
Fig 11. Image showing existing Electricity Powerline from Kenya Power and Lighting Company.
Recommendations
Since there is an existing electricity powerline to the proposed recreational facility at the site.
Below will be the requirements to be availed by the client (TUK) for connection from Kenya
power and lighting company.
15
C) Drainage
I noted presence of drainage channels along the two main access points to the proposed site.
Fig 12. Image showing drainage channel along access point on the southern side to the
site.
Fig 13. Image showing drainage channel along access point on the western side to the site.
Recommendations
Widening the existing storm drainage channels during construction will be quite
necessary so as to prevent soil erosion and the collection of excess surface water.
D) Street Lights
I also noted presence of existing street lights, which are not in good working condition along the
15.0m wide main access on the western side of the site. Below is an image supporting above
statement.
16
Fig 14. Image showing street lights along access point on the western side to the site.
Recommendations
Solar-powered technology street lights along the two main 15.0m wide access roads and
along the paths within the proposed recreation facility will be adopted or be catered for
emergency of electricity supply systems in case of power rationing and blackouts.
Currently the site is relatively flat used partially as a sports utility area and with less vehicular
noise from both main access point, therefore less noise impact to the proposed site.
Recommendations
The site is characterized by black cotton soil, which shows large volume changes with respect to
variation of seasonal moisture content.
Recommendations
Since the soil is not structurally sound, it is recommended to excavate the top soil to
reach a stable ground before laying the foundation.
Bottom and sides of the excavations must be well treated with an approved insecticides
before foundation walls and ground slabs placements to prevent the insects approach the
building in future.
During landscaping there will be need to replace the top soil to achieve better result.
Vegetation
The site is characterized by short indigenous trees which grow naturally with no human
intervention. Other vegetation consists of scattered shrubs, and cynodon dactylon (Bermuda
grass) grass species.
Below are images supporting above vegetations types.
Recommendations
Vegetation can be used in the definition of space and in directing the vies towards the
entrances, e.g. Through creating avenues, circular outdoor spaces.
Planting other trees apart from the existing natural indigenous ones will enhance the
landscape and increases the aesthetic value of the site, as well as proving shading.
Climatic Analysis
A) Solar Radiation
The amount of solar radiation is on its peak between the month of January to the start of March,
which causes high temperatures and day time discomfort. Find below image representing
estimation of mean monthly solar radiation using sunshine hours for Nairobi city.
Fig 19. Image showing Radiation vs Month for Nairobi city. Source: Journal of Renewable and
Sustainable Energy 7, 053105 (2015); https//doi.org/10.1063/1.4930530
19
Recommendations
Window openings that will be affected by direct that will be affected by direct sunlight
will be treated with sun shading devices such as vertical and horizontal fins.
Installation of photovoltaic cells for solar energy harnessing. For interior use of energy
bulbs and street lights along main access entrance and along pedestrian and vehicular
paths.
B) Rainfall / Precipitation
Nairobi county receives just over 610 mm of rainfall a year occurring primarily in two rainfall
seasons. The long rains from March and May, which generally records around 310 mm, and the
short rains during November and December, where around 200 mm is recorded.
Fig 20. Image showing Average Temperature and Precipitation in Nairobi. Source: Climate–Data
2016
Recommendations
Rain water harvesting by providing rain water down pipe to channel rain water to
underground water storage tanks for water closet flushing and for use in external
landscaped areas.
Provide wide storm water drainages to prevent soil erosion and the collection of excess
surface water.
C) Temperature
In Nairobi, the average temperature of the coldest month (July) is of 20.6 °C (69.0 °F), that of
the warmest month (March) is of 25.6 °C (78.0 °F). Here are the average temperatures.
20
. Fig 21. Image showing Average Temperature in Nairobi. Source: Kenya Forecast
Recommendations
To minimize solid enclosure during design, therefore this will increase thermal comfort
to the users of the space.
D) Wind Direction
Prevailing winds throughout the year is characterized by 50 percent of the total wind flowing
from North East to South West.
Recommendations
The shape and orientation of the building to be in the direction of the prevailing wind
direction and openings placed to utilize those pressure difference.
Existing Facilities
A) Guard House
Presence of a guard house built purposely to shelter the security personnel safeguarding the
property. It is located at the main entry of a 15.0m wide access on the southern side of the site.
See below plate for the guard house.
Fig 22. Image showing Guard House at the main entry gate to the proposed 21
site.
Recommendations
To carefully demolish and store safely the materials, to be reused in the construction of a
modern security guard house with security equipment’s.
Presence of a 2.2m high boundary wall fence (built with dressed masonry wall) secured with a
razor wire above it on the western side and partly southern side of the site. Also noted barbed
wire fence on northern side of the site. See below plates.
Fig 23. Image showing 2.2m high boundary wall on the western side of the
site.
Fig 24. Image showing 2.2m high boundary wall and barbed wire on the southern side of the site.
Recommendations
Boundary walls will match the same finishes as the proposed recreational facility to
maintain aesthetic consistency.
22
C) Ablution Block.
Noted the presence of existing permanent ablution block with changing rooms for both genders,
which was constructed by TUK to be used by students undertaking variety of sport games.
Recommendations
It will be carefully demolished and some of the materials used during construction be
reused in the construction of the main project.
The water tank above will still retain its purpose for water storage.
The temporary residence structures at the site is currently occupied by the caretaker safeguarding
the property, who is an employee of TUK. See below plate showing the temporary structure.
They will be well repaired and painted to be temporary storage units for different
materials during construction of the main project.
The main entry gate is 6.0m wide and 1.5m wide pedestrian gate on the southern side of the
proposed site. They are both made of standard mild steel, fixed to 3No. 300mm by 300mm
reinforced concrete columns with hooks.
Fig 27. Image showing main entry gate and pedestrian gate at the site.
Recommendations
The main vehicular entry and size will be retained, but sliding gate proposed with Bol
overed security features installed.
To introduce both entry and exit points for pedestrians with metal detectors.
24
CURRENT LAND USE
Currently, the land is being utilized as a sports ground for the Technical University of Kenya. A
variety of games are undertaken by various teams within the school set up.
ZONING
According to the zoning regulation shown above, the site is located in zone 10, which allows for
the High-Density ResidentialDevelopment, Mixed Residential Development such as:
Flats.
Maisonettes.
Bungalows.
The power to control land use and development in Kenya is vested in the County Governments
and therefore the owner or the legal entity of any property, who intends to develop his/her land
for any purpose other than that earmarked in the approved Master Plan, will make an application,
along with relevant documents, to the respective County Governments’ Department of Physical
Planning for consideration through a registered physical planner.
PROCEDURE
The investor, through a registered physical planner will make application for thechange
of user through filling in PPA 1 form, which must be duly signed by the physical planner.
The planner and the investor will then publish public notices regarding the proposed
change of user in two daily newspapers, inviting objections from the public within a
period of not less than fourteen (14) days. A site notice will also be placed on the site
indicating intention to change its use within the same duration.
Planning brief/report for the site is prepared by the physical planner. The process of
preparing and implementing a planning brief/report provides a framework for collecting
information about a site, and investigating and evaluating different interests in it. The
brief will explain why the change of use is in line with the policy and why it will not have
any negative effects on the land and the neighboring properties. The process could take
from one day to 7days depending on the scale of the project.
The requisite fee will be paid to the respective County Governments and the receipt
annexed to the planning brief/report prepared by the physical planner.The brief will then
be submitted to the County Government's Department of Physical Planning for approval.
The County Government then receives submissions from the general public on any
opposition to the change of use. This process could take up to 14 working days. 26
The County Government will then review the Change of Use proposal/brief with the
public objections received if any and will pass a resolution, recording reasons, regarding
its consideration or non-consideration for the change. This process takes a minimum of
20 days and could extend depending on the requirements the County Government wants
fulfilled.
The authority shall, if it finds that the changes sought are relevant to planningprinciples
and are in public interest and are not in contravention to any other statute, give
permission for the same by issuing a PPA2 form.
REQUIREMENTS
In summary, below are the requirements for application for a change of user.
Two dully filled P.P.A 1 forms in triplicate submitted and signed by a registered physical
Planner
27
PROFESSIONAL AND STATUTORY FEES
Professional Fees.
PROFESSIONAL FEES
E.I.A Expert (Lead Expert) 1% of the total construction cost + 16% V.A.T
Physical Planner (Change of User) 1% of the total construction cost +16% V.A.T
Total 24%
28
Statutory Plans Submission Fees.
FINANCIAL APPRAISALS
The purpose of the financial appraisal is to determine whether the project is worthwhile,
comparing its costs with its expected benefits. It stands as a key element for deciding whether or
not to proceed with a construction project and any project in general. Also, it stands as a key
element for choosing between alternative construction projects. Financial appraisal addresses not
only the adequacy of funds, but also the financial viability of the project, estimating in the end if
and when the project returns a profit or not.
There are several financial appraisal methods that can be used to check the project viability
including the following;
Payback period
Market analysis
For this scenario, three appraisal methods are used to inform the client on the best choice
between the available proposed options. They include the: -
Payback Period
According to the Net Present Value method, investments should be made in projects with the
highest positive NPV.
Payback Period.
The payback period (PBP) is the amount of time that is expected before an investment will be
returned in the form of income. When comparing two or more investments, developers and
investors will typically compare the projects to see which one has the shorter PBP. Projects with
longer PBP are usually associated with higher risk and therefore, less attractive to the developers
30
and clients.
Fisher, Martin, Mosbaugh, & Mueller, (1991) puts the definition of payback period as the
number of years required for cumulative income from an investment to equal the amount initially
invested.
However, the payback period does not consider the time value of money and, therefore,
insufficient to use as an appraisal method on its own.
The formula can be expressed as follows;
The calculation process is quicker than and simple than any other appraisal techniques
31
Disadvantages of Payback Period Method
Once the internal rate of return is determined, it is typically compared to a company’s hurdle rate
or cost of capital. If the IRR is greater than or equal to the cost of capital, the company would
accept the project as a good investment. If the IRR is lower than the hurdle rate, then it would be
rejected.
Check the formula is presented as follows;
32
Advantages of Internal Rate of Return
Takes account of profits earned over the entire life of the project
Profitability Index.
Profitability index is the ratio of present value of cash inflows to present value of cash outflows.
It discounts cash inflows and cash outflow to obtain net present values. Cost of finance or
interest rate is used to discount inflows and outflows. It is also known as Benefit-Cost Ratio.
If P.I is greater than 1 you invest and if less than 1 do not invest.
It considers the risks which are involved with future cash flows.
It will take the time value of money into consideration in the calculation.
It will give you information about ranking projects while still rationing capital.
It provides you with information about how an investment changes the value of a firm.
33
Disadvantages of Profitability Index Method
Advantages of MIRR
MIRR overcomes 2 major drawbacks of IRR including the elimination of multiple IRRs
in case of investments with unusual timing of cash flows and secondly the re-investment
problem.
Disadvantages of MIRR
MIRR may lead to sub-optimal decision making when multiple investment options are
being considered.
MIRR can be hard to understand for people belonging from a non-financial background.
The theoretical basis for MIRR is also disputed among academics
34
Annualized Net Present Value.
An approach to evaluating unequal-lived projects that converts the net present value of unequal-
lived, mutually exclusive projects into an equivalent (in NPV terms) annual amount. The
calculation of the ANPV involves the following steps:
Calculation the NPV of the project using the given project life.
Division of the project’s NPV by the present value annuity factor over the project life.
This gives you the annual annuity value – the ANPV.
Comparison of the ANPVs of the projects. The project with the highest ANPV is
preferred.
The approximate method of approximation that will be used in this project is the floor area or the
superficial method.
35
METHODS OF APPROXIMATE APPROXIMATION.
Option 1: High-Cost Private Hospital
Case Study: Meridian Medical Hospital located in Buruburu – Nairobi County
According to Institute of Quantity Surveyors of Kenya (IQSK) High-Cost Private Hospital rates
are KShs 81,860 per SQ.M
1,038,066,660
ADD
TOTALS 1,373,050,771
= 6.3 years
Net Present Value
Discounting period 4 years and discounted rate 14%
YEAR CASH FLOW P.V FACTOR CASH FLOW P.V
TOTALS -148,524,750
404,319,000
ADD
TOTALS 595,036,272.30
TOTALS -510,236,800
Totals 2,661,962,000
ADD
TOTALS 3,518,315,175.4
TOTALS -553,994,000
1,092,120,000
ADD
TOTALS 1,454,376,204
5 230,050,000
TOTALS +405,169,093
44
INTERNAL RATE OF RETURN
Recreational Complex
DISCOUNTING PERIOD – 10 YEARS
DISCOUNTING RATE - 10%
0 -9601481134 -960148134
554979041
NPV 405169093
IRR 18%
45
GRAND SUMMARY
CONCLUSION
According to the study and financial appraisal a Recreational Complex has a payback of 5.2
years, which is short compared to other investment options. After 5.2 years TUK should be out
from the financial crisis it is in.
46
CHAPTER ONE
FEASIBILITY STUDY
Feasibility studies look into the practicability as well as viability of various investmentoptions,
which can be construction project, as an example. According to Fercher, (2006), a feasibility
study covers the aspects of necessity, practicability as well as the justifiability of an investment
option.
The following is a feasibility study report for a project to construct Recreational Complex at
TUK grounds in South C. The aim of the study was to:-
Enhances the probability of success by addressing and mitigating factors early on that
could affect the project;
METHODOLOGY
Information to support this study was obtained through an evaluation site visit method. Further
information was obtained qualitatively through in interviews with key relevant people including
the school vice chancellor, local people from the estate, local business persons and my
counterparts.
The data is further analyzed by textual description of the observations and the feasibility
implications indicated.
47
FEASIBILITY ANALYSIS
Soil conditions
Soil type at the site is black cotton soil. Construction of a good drainage system should be
factored into during the carrying out ofexternal works.
Topography
Drainage
The nearest tributary from the river is kilometers away from the project site and there is no
potential direct impact of the project on the river. However, the waste from construction and
chemicals from the building should not just be left laying aimlessly.
The area is surrounded by residential Buildings an indicator of a number of people living around.
This means that the project has to observe the regulations stipulated in the EMCA act concerning
the level of noise and the periods for working. 48
MARKET FEASIBILITY
Option 4: Proposed Recreational Complex
South C area is located in Nairobi County just approximately 7.2kilometers south of Nairobi
which is about an 18 minutes’ drive from the CBD. The estate is part of the Nairobi Metropolitan
Area.
South C is growing constantly with buildings coming up and people moving in to capitalize on
the property boom in the area. In the last five years, property prices in South C have steadily
been going up, and there is no sign of a slow down any time soon.
South C has experienced an upsurge in the development of bungalows and villas in gated
communities for outright sale to those seeking accommodation in well-established and secure
areas. The demand is mainly fueled by the rising middle class due to improved economy; also, a
cultural belief among Kenyans that makes sense to own property not only in the rural area where
one resides, but also in other towns where people spend most of their working lives and for
investment purposes. In addition to this, the South C vicinity borders the Wilson Airport and
furthermore, a few kilometers from the Jomo Kenyatta International Airport, which are avenues
of international arrivals. Therefore, recreation facility in South C will conveniently accommodate
the locals as well as foreign sports visitors coming into the country for training and other
purposes.
MARKETING STRATEGY
A marketing strategy refers to a business's overall game plan for reaching prospective consumers
and turning them into customers of the products or services the business provides. A marketing
strategy contains the company’s value proposition, key brand messaging, data on target customer
demographics, and other high-level elements.
Increased competition in every sector of the Kenyan economy has necessitated for intensified
marketing strategies. Recreational facilities for that matter, is doing well and therefore modern
facilities are required. The proposed development of recreational facility need come up with a
differentiated plan as well as a different strategy that will attract people from around the city,
country and the world at large.
49
Below describes the proposed marketing strategies;
Advertisement
Adverts can be sponsored to the local and international newspapers, as well as billboards. Most
significantly, the adverts are crucial to creating an impression of the services that the recreation
facility offers to the potential customers.
Legal Feasibility
Legal feasibility is the study to know if the proposed project conforms the legal and ethical
requirements. It is important that the project is following the requirements needed to start a
business or a project including business licenses, certificates, copyrights, business insurance, tax
number, health and safety measures, and many more.
Financial Feasibility
Financial feasibility focuses specifically on the financial aspects of the study. It assesses the
economic viability of a proposed venture by evaluating the startup costs, operating expenses,
cash flow and making a forecast of future performance. A cost benefit analysis is used to
evaluate the total anticipated cost of a project compared to the total expected benefit in order to
determine whether the proposed implementation is viable for a company or project team.
The preparation of a financial feasibility study has three parts:
Determining the startup costs.
51
Political Feasibility
A political feasibility study involves evaluating the status of the political climate that may affect
the viability of the project. Depending on the size of the project and its social and political
implications, the project may gain widespread support from the government or its opposition.
This means that there are unanticipated challenges that will come with this, on the other hand,
the government itself may be against the project because it differs with its political standing. This
makes political feasibility an important factor especially for large projects.
Managerial/Administrative Feasibility
Schedule Feasibility
The proposed timeline will be represented in a timeline in the form of a Gantt chart. The
representation will be in a position to factor in the critical path, which would indicate the critical
activities as far as the completion of the project is concerned.
52
Social-Economic Feasibility
Social and economic feasibility of a project serve to identify the extent to which a project is
socially and economically beneficial. In addition, it identifies the positive and negative
consequences of the project from a social as well as an economic perspective
Positive Impacts of the Project
Creation of Employment
During the project life cycle, employment will be created to both skilled, semiskilled as well as
unskilled labour. For instance, the pre-construction phase of the project will involve
professionals such as project managers and designers, who will gain meaningful employment.
The construction phase will offer employment to other parties such as masons, welders,
electricians, plumbers, among others. Similarly, the operational phase of the project will involve
the property managers, who will in turn create employment for parties such as cleaners, security
personnel, caretakers among others.
Environmental Feasibility
53
Negative effects that result from the construction stage
Airborne emissions The project area will be cordoned off KShs 100,000
to minimize dust migration to
nearby facilities by wind.
Speed controls by temporary speed
bumps on diversions where
necessary within the construction
site
Staff working in dust generating
activities e.g. site preparation,
excavation, concrete mixing, stone
dressing should be provided with
personal protective equipment the
use of PPE shall be enforced.
Avoiding open burning of solid
wastes;
Construction equipment will be
maintained in good operating
condition to reduce exhaust
emissions;
55
Haulage trucks must be covered or
the aggregates sprayed with water
before loading the haulage trucks;
All diesel fuel in use should be ultra-
low Sulphur diesel
56
investigations should involve the
collection of subsurface soil and
groundwater samples for laboratory
analysis;
Areas dedicated for hazardous
material storage shall provide spill
containment and facilitate clean up
through measures such as dedicated
spill response equipment.
Open stockpiles of construction
materials on site should be covered
with tarpaulin or similar fabric
during rainy season.
Measures should be taken to prevent
the washing away of construction
materials, soil, silt or debris into any
drainage system.
57
Negative environmental impacts during operation stage
Increased EffluentWaste Ensure that sewerage discharge pipes are KShs 100,000
and SurfaceRunoff
Generation not blocked or damaged since this can lead
to release of the effluent, resulting in land
and water contamination.
Ensure that no surface wastewater is
directed into the sewer system to avoid
overloading the sewerage system;
Monitor effluent quality regularly to
ensure that the stipulated discharge rules
and standards are not violated.
Harvest rainwater from roof for non-
portable uses e.g. cleaning and watering
plants.
58
REFERENCES
Fisher, J. D., Martin, R. S., Mosbaugh, P., & Mueller, P. (1991). The Language of Real
EstateAppraisal. La Crosse, WI: Dearborn Real Estate.
Dayananda, D., Irons, R., Harrison, S., Herbohn, J., & Rowland, P. (2002). Capital
Budgeting: Financial Appraisal of Investment Projects. Cambridge, England: Cambridge
UniversityPress.
CAP.525. http://kenyalaw.org
Hutchinson, K. (1993). Building Project Appraisal: Analysis of value and cost. London,
UnitedKingdom: Macmillan International Higher Education.
Corporate finance institute. (2019, January 17). Internal Rate of Return (IRR) - A Guide for
Financial Analysts
Practical Financial Management: A guide to budgets, balance sheets and business finance (7
Edition) London, UK; Kogan Page.
59