Project Scheduling
Project Scheduling
Learning Objectives
Understand the importance of project schedules and good project time management. Define activities as the basis for developing project schedules. Describe how project managers use network diagrams and dependencies to assist in activity sequencing. Understand the relationship between estimating resources and project schedules. Explain how various tools and techniques help project managers perform activity duration estimating.
2
Learning Objectives
Use a Gantt chart for planning and tracking schedule information, find the critical path for a project, and describe how critical chain scheduling and the Program Evaluation and Review Technique (PERT) affect schedule development.
Discuss how reality checks and people issues are involved in controlling and managing changes to the project schedule.
Describe how project management software can assist in project time management and review words of caution before using this software.
3
Activity Definition
An activity or task is an element of work normally found on the WBS that has an expected duration, a cost, and resource requirements. Project schedules grow out of the basic documents that initiate a project.
The project charter includes start and end dates and budget information. The scope statement and WBS help define what will be done.
Activity definition involves developing a more detailed WBS and supporting explanations to understand all the work to be done, so you can develop realistic cost and duration estimates.
7
Activity attributes provide more information about each activity, such as predecessors, successors, logical relationships, leads and lags, resource requirements, constraints, imposed dates, and assumptions related to the activity.
8
Milestones
A milestone is a significant event that normally has no duration. It often takes several activities and a lot of work to complete a milestone.
Milestones are useful tools for setting schedule goals and monitoring progress. Examples include completion and customer sign-off on key documents and completion of specific products.
9
10
Activity Sequencing
Involves reviewing activities and determining dependencies. A dependency or relationship relates to the sequencing of project activities or tasks. You must determine dependencies in order to use critical path analysis.
11
Network Diagrams
Network diagrams are the preferred technique for showing activity sequencing. A network diagram is a schematic display of the logical relationships among, or sequencing of, project activities. Two main formats are the arrow and precedence diagramming methods.
13
14
15
2.
3. 4.
17
18
19
21
Three-Point Estimates
Instead of providing activity estimates as a discrete number, such as four weeks, its often helpful to create a three-point estimate:
An estimate that includes an optimistic, most likely, and pessimistic estimate, such as three weeks for the optimistic, four weeks for the most likely, and five weeks for the pessimistic estimate.
Three-point estimates are needed for PERT estimates and Monte Carlo simulations.
22
Schedule Development
Uses results of the other time management processes to determine the start and end dates of the project. Ultimate goal is to create a realistic project schedule that provides a basis for monitoring project progress for the time dimension of the project. Important tools and techniques include Gantt charts, Critical Path Method (CPM) or Critical Path Analysis, Critical Chain Scheduling, and PERT (Program Evaluation and Review Technique) analysis.
23
Gantt Charts
Gantt charts provide a standard format for displaying project schedule information by listing project activities and their corresponding start and finish dates in a calendar format. Symbols include:
Black diamonds: Milestones Thick black bars: Summary tasks
25
26
27
SMART Criteria
Milestones should be:
Specific
Measurable
Assignable
Realistic Time-framed
28
29
Slack or float is the amount of time an activity can be delayed without delaying a succeeding activity or the project finish date.
30
Add the duration estimates for all activities on each path through the network diagram.
The longest path is the critical path. If one or more of the activities on the critical path takes longer than planned, the whole project schedule will slip unless the project manager takes corrective action.
31
32
There can be more than one critical path if the lengths of two or more paths are the same. The critical path can change as the project progresses.
33
35
36
Crashing activities by obtaining the greatest amount of schedule compression for the least incremental cost.
Fast tracking activities by doing them in parallel or overlapping them.
37
38
Multitasking Example
40
42
Example:
PERT weighted average =
8 workdays + 4 x 10 workdays + 24 workdays = 12 days 6 where: optimistic time= 8 days most likely time = 10 days pessimistic time = 24 days Therefore, youd use 12 days on the network diagram instead of 10 when using PERT for the above example.
44
Schedule Control
Perform reality checks on schedules.
45
Schedule Control
Goals are to know the status of the schedule, influence the factors that cause schedule changes, determine that the schedule has changed, and manage changes when they occur. Tools and techniques include:
Progress reports. A schedule change control system. Project management software, including schedule comparison charts, such as the tracking Gantt chart. Variance analysis, such as analyzing float or slack. Performance management, such as earned value (see Chapter 7).
46
47
48
49
Chapter Summary
Project time management is often cited as the main source of conflict on projects, and most IT projects exceed time estimates. Main processes include:
Activity definition Activity sequencing Activity resource estimating Activity duration estimating Schedule development Schedule control
51