5 Aggregate Planning
5 Aggregate Planning
Operations
Current Machine and Distribution & Marketing
Workforce capacity and Customer needs, Demand
plans for future Forecast, Competition
Materials
Aggregate Accounting & Finance
Supplier capabilities,
Plan Cost data, Financial
Storage capacity,
condition of the firm
Material availability
Engineering
Human Resource
New products, Product
Labour-market conditions,
Design, Technology
Training capacity
changes
Aggregate Planning
Aggregate Planning Strategies
There are two pure planning strategies available to the aggregate planner
Level Strategy
Chase Strategy
Firms may choose to utilize one of the pure strategies in isolation, or they
may opt for a strategy that combines the two
Advantage – Inventory is
held at the lowest level possible
Disadvantage – Unhappy
employees, problems with
labor unions, risk of
unavailability of skilled
employee when needed
Aggregate Planning
Aggregate Planning Methods or Techniques
Graphical and Charting Method – Two dimensional model relating
cumulative demand to cumulative output capacity. Easy and Simple to
understand
Optimal Models
a) Linear Programming – Mathematical model used to formulate
aggregate plan
b) Linear Decision Rules – A set of linear equations are solved to
calculate optimal workforce, output rate and inventory level
Heuristic Models – Based on past data on aggregate planning.
Management coefficient model uses regression method
Computer Simulation in Capacity Evaluation - Provides what if analysis
of various situations and optimum performance level
Aggregate Planning
Problem 1
In a textile firm a worker is capable of tailoring 3 garments per day. Assume the
time taken to tailor each garment is same.
Given:
Hiring Cost = Rs 3000; Layoff Cost = Rs 4000; Current employee strength = 40
Aggregate demand for the next 4 months is given in the following table.
Based on the given information generate a production plan by following the
varying workforce strategy
Working 24 25 23 24
Days
Aggregate Planning
Solution
For the month of June
Number of units produced /worker 3 x 24 = 72 units
Total output of 40 workers = 40 x 72 = 2880 units
Deficit = Demand – Production = 3170 – 2880 = 290
No of additional workers = 290 / 72 = 4
Cost of hiring = 4 x 3000 = Rs 12000
Similarly deficit / Surplus and number of workers hired or laid off are calculated
for the other months
Aggregate Planning
Months Jun July August September
Working days 24 25 23 24
Units / worker 72 75 69 72
Workers available 40 44 40 42
Total Output 2880 3300 2760 3024
Demand 3170 3000 2900 2660
Deficit / Surplus 290 (-) 300 140 (-) 364
# of workers 4 (-) 4 2 (-) 5
hired / laid off
Hiring / Lay off 12000 16000 6000 20000
cost (H) (L) (H) (L)
Total # of workers 44 40 42 37
Total Cost 12000 16000 6000 20000
Aggregate Planning
Problem 2
Aggregate demand for product X for the next four months in given in the following
table. Given:
Opening stock of inventory = 500 units;
Inventory holding Cost = Rs 40/unit; Shortage cost = Rs. 30/unit
Worker productivity = 20 units / day ; Worker strength = 10
Based on the above information generate a production plan with varying inventory
levels.
Working 23 24 22 23
Days
Aggregate Planning and Master Production Schedule
Solution
Inventory carrying cost = Excess inventory x Per unit inventory holding costs
Excess inventory in one month is taken as the beginning inventory for the next
month
Aggregate Planning and Master Production Schedule
For the month of June Total production = 23 x 10 x 20 = 4600
Closing inventory = 500 + 4600 – 5000 = 100
Inventory carrying cost = 40 x 100
Months Jun July August September
Opening stock of 500 100 300 0
inventory
Working Days 23 24 22 23
Actual Production 4600 4800 4400 4600
Demand Forecast 5000 4600 5200 4800
Closing Inventory 100 300 -500 -200
Shortage Cost 0 0 15000 6000
Excess Inventory 100 300 0 0
Inventory 4000 12000 0 0
carrying cost
Aggregate Planning
Back orders
Current order commitments are fulfilled in future assuming that the customers
are ready to wait for delivery
Smoothens production but sometimes results in stock out cost
Subcontracting
Allows level production and sources additional output required from the
subcontractors
Plant capacity
Plant capacity is adjusted by varying the equipment capacity
Aggregate Planning
Master Production Schedule
Master Production schedule (MPS) defines the type and volume of each
Two major sources of input for MPS are forecasts (for Make-to-stock items)
(MRP)
Aggregate Plan
Tentative Master
Schedule
Yes Yes
Final Master Schedule
1 2 3 4 5 6
Forecast 30 35 38 32 32 30
Orders 23 40 24 22 38 22
Projected on-hand
inventory 10 50 12 60 22 72
MPS quantity 0 80 0 80 0 80
MPS start 80 80 80
Aggregate Planning and Master Production Schedule
Solution
Forecast for the 2nd week is 35 units. But the order received is for 40 units.
Inventory on hand at the end of first week is 10 which is not sufficient to satisfy
the second week’s requirements. So to make up for the deficient the organisation
schedules for MPS quantities.
As the lead time is one week the production should commence in the first week
itself to satisfy the requirements of the second week.
There is no requirements of MPS quantities in the 1st , 3rd and 5th week
Aggregate Planning and Master Production Schedule
Material Requirement Planning
Material requirement planning (MRP) is the scientific technique for planning,
ordering and usage of materials at various levels of production and for monitoring
the stocks (inventories) during these transactions.
MRP Input
Master Production Schedule – When and how much quantity of finished
products are required
Bill of Material – List of materials and their quantity required to produce one
unit of product
Inventory Record File – Complete record of each material held in inventory
Aggregate Planning and Master Production Schedule
MRP System Information Processing
Explosion – Disassembling the end products into components and moving
backward to determine the production and purchasing activity for each component.
Netting – Developing a material requirement plan for each item in the BOM for
each time bucket
Offsetting – Uses the information from Explosion and Netting to determine the
planned order releases either internally through production or from a supplier
MPS
MRP Inventory
Bill of Processing Record
Material Explosion File
Netting
Offsetting
Primary Secondary
Reports Reports