Transmission Network Planning and Design
Transmission Network Planning and Design
Transmission Network Planning and Design
Guidelines/Parameters
At this stage some guidelines as to the planning parameters should be decided upon with customer and entered into the Planning tool - these will generally include. A ) For existing coverage area expansion :
No. of frequency spots being used / applied for MW emission ? Latest NW plan showing various configurations of MW hops on-air along with capacities. Minimum antenna size recommended for MW ? Maximum antenna size allowed ? Maximum loading capacity of a MW radio hop allowed in %age ? Per hop availability of MW hop required ? Maximum loading of terminating ports of a BSC allowed ? Existing Lease line details required along with capacities for Abis traffic, if any? Existing Lease line details required along with capacities for Ater traffic ? Minimum no. of BTS required in loop configuration ? Maximum no. of BTS allowed in chain configuration ? Any STM-1 hop to be planned with 2xSTM-1 XPIC configuration. Inter BSC traffic running on LL / MW ? Any POI transmission system to be planned ? Would transmission be planned for both co-located BTSs in different frequency bands ?
BoQ Preparation
Once the nominal connectivity plan is prepared, it can broadly be known as to how many 7GHz/15GHz/18GHz/23GHz links are required based on the spectrum availability for a circle. Further the capacities of each of the link i.e. 4E1/8E1/16E1/STM-1 and MUXs can be finalized based on the above covered inputs on capacity projections. It should be noted that at any point of time the utilization of the MW link should be maintained at less than 80% or whatsoever given by customer.
11
12
13
Network Architecture
Transmission is of major important element in any mobile network, affecting both the service quality as well as the cost of the mobile operator. Careful transmission dimensioning and planning from the initial state is thus certainly worthwhile from the business point of view. Figure illustrates the logical connection in GSM network.
MSC MGW MSS
TCSM
BSC
BSC
BTS BTS
BTS BTS
14
The transmission core network is planned for imbibing the capacity requirements for a 2.5G rollout in the following phases of the rollout. A three-tier topology is planned for the metro as well as state Network. The multi tier approach will help in the aggregation and maintenance of the nodes more efficiently. Tier 1 -The fiber Bb for every circle is planned to carry MGW-MSC server traffic, Inter MGW traffic and Ater traffic in case of metro circles while in case of state circle it may carry all MGW-MSC server traffic, Inter MGW traffic and partial Ater traffic, as in case of state circles MW BB may also carry some Ater traffic. Tier 2 The MW rings of STM and high capacity PDH radios are formed starting from the TRS nodes and PoPs. These rings will encapsulate the maximum access capacities and backhauls on to the nearest transmission nodes. The transmission planned on microwave links offers the fastest means for network rollout and capacity expansion in the access. Furthermore, operational expense is considered less expensive than laying own cable or leasing connection. Tier 3 The PDH 16 E1 radios are deployed on the MW STM rings. These hops will rope in all the existing traffic on to the nodes. These hops are downgradable to lower capacity radios by which efficient usage of BW can be done and hence freq spots can be better managed. Apart from above three tiers , transmission planner is also committed to provide POI connectivities which includes connectivity of L1 and L2 exchanges.
15
16
RNC/MSC
Node/Hub
Node/Hub
Network Topologies
18
Ring Topology
In fig BTS-sites are connected as a ring (loop). The capacity requirement is the total sum of the individual capacity requirements.
BTS 4
BTS 5
BTS 6
BTS 8
19
20
Star Topology
Each BTS is connected to the BSC/Hub Site independent of the rest of the traffic. This causes high concentration of hops at Hub site resulting in frequency interference and threshold degradation. This topology is mostly used in areas with LOS limitations or it applies to an area where we can afford to loose redundancy of BTSs as compared to the cost of carrying backhaul traffic. This is not suited to city network. The BTS will not have redundant path and only option is to have equipment redundancy. The hops used in this topology can be 1+0 or 1+1 depending on whether there are further sites connected in chain to any arm of the star or as per customer inputs.
BTS 1
BTS 1
BTS 1
BTS 1 BTS 1
21
22
Chain Topology
A number of sites connected in sequence, where every intermediate site is connected to only two sites in the chain. In case there are more than 3 sites in a chain , then the links will be planned as 1+1. In case it is not possible to close any other route and in case a BSC happens to fall in a chain, redundancy for the BSC should be planned on alternate media or leased lines. This type of configuration consists of linking RBS-sites in a chain such that the previous RBS sites in the chain act as active repeaters for the last one; see the fig illustrates two chains converging to a common RNC/MSC. In this particular case, the configuration can also be extended to a tree configuration by adding more RBS-sites to each existing RBS-site, but without closing the tree foliage to become a ring. Parts of a chain can also be used in mixed topologies.
BTS BSC
BTS
BTS
BTS
BTS
BTS
23
At the very bottom of the network hierarchy (farthest from the RNC/MSC), where capacity is relatively low (2 Mbit/s), the paths are normally unprotected. Closer to the RNC/MSC where the capacity is accumulated, it is strongly recommended to implement some degree of protection. A Cascaded configuration is similar to the chain/tandem configuration described in this section, but the traffic may be concentrated at some BTS-sites in the chain (hubs). Protection is strongly recommended in the feeder link.
24
Spur Topology
A spur is a single link connected to a hub site or a chain site. Spurs shall be planned as 1+0 only unless there is a special requirement to have a 1+1 link
26
Metro city NW
For e.g. A big city having high penetration of BTSs would like as follows , where sites are fashioned in star or loop fashion across SDH ring.
27
Medium city NW
Sometimes we come across the situation that there are not enough BTSs in a city but a BSC is located in a city so as to cater Abis traffic to remote cities on Lease lines . The MW of this city having BSC may look like as follows :
28
29
Clusters of Microwave
The network is divided into sub-networks (clusters) having BTS-sites distributed around a common centre. All clusters are then connected to a common centre site. Clusters present many advantages: The overall availability is increased if the cluster connections to the centre are protected. Shorter paths from all sites to the centre site. More flexible rollout. Distributed transmission capacity.
RNC/MSC
This kind of NW is constructed in a city where lot of Fibre points are available and LL is available from these nodes till BSC in SNCP protection. These small clusters are also called as islands.
30
Summary
Chain/tandem configurations are suitable when providing radio coverage along roads or rivers. In this case the radio base station is often of omni-directional type. Tree configurations are suitable in smaller or medium sized networks. Star configurations are suitable for small networks. Ring configurations are suitable when high availability is required.
31
Capacity Planning
32
33
34
35
37