Four different jobs can be done on four different machines.
The set-up and
take-down time costs are assumed to be prohibitively high for change overs.
The matrix below gives the cost in rupees of producing job I on machine j.
Machines
M1 M2 M3 M4
J1 5 7 11 6
Jobs
J2 8 5 9 6
J3 4 7 10 7
J4 10 4 8 3
How should be the jobs be assigned to the various machines so that the total cost is minimized?
5 7 11 6
8 5 9 6
4 7 10 7
10 4 8 3
Cost Matrix 0 2 6 1
3 0 4 1
0 3 6 3
7 1 5 0
Row Reduction Matrix
0 2 2 1
3 0 0 1
0 3 2 3
7 1 1 0
Column Reduction Matrix
0 2 2 1
3 0 0 1
0 3 2 3
7 1 1 0
No. of Lines= 3< 4(Order 0 1 1 0
of the Matrix)
4 0 0 1
0 2 1 2
8 1 1 0
No. of Lines= 3< 4(Order 0 0 0 0
of the Matrix)
5 0 0 2
0 1 0 2
8 0 0 0
No. of Lines= 4=Order of the Matrix, Hence
Optimum Solution is achieved
Solution-1
M1 M2 M3 M4
J1 0 0 0 0
J2 5 0 0 2
Optimum Assignment Policy
J3 0 1 0 2 Jobs Machines Optimum Cost
J1 M3 11
J4 8 0 0 0 J2 M2 5
J3 M1 4
J4 M4 3
Total Rs.23
Solution-2
M1 M2 M3 M4
J1 0 0 0 0
J2 5 0 0 2
Optimum Assignment Policy
J3 0 1 0 2 Jobs Machines Optimum Cost
J1 M1 5
J4 8 0 0 0 J2 M2 5
J3 M3 10
J4 M4 3
Total Rs.23
Hence, the given problem is of Multiple Optimal Solution