Project Cost Resource Management
Project Cost Resource Management
DR AFSHAN NASEEM
14
On Day X:
• PLANNED VALUE (BCWS) = 18 + 10 + 16 + 6 = 50
• EARNED VALUE (BCWP) = 18 + 8 + 14 + 0 = 40
• ACTUAL COST (ACWP) = 45 (from your project tracking)
Therefore:
• Schedule Variance = BCWP – BCWS = 40 - 50 = -10 (behind schedule)
• Schedule Performance Index = 40 / 50 = 0.8, or 80% of plan
• Cost Variance = BCWP - ACWP = 40 - 45 = -5 (over budget)
• Cost Performance Index = 40/45 = .8923
Example Project
• Suppose BCWP is $300K & BCWS is $400K
ACWP = $325K
Engineer
Designer
Why Work in Teams?
Perform Tribal ?
Groupthink!
Form Norm
Storm
Time
We believe in teamwork because…
RESOURCE
MANAGEMENT
Resource
Week 8
Week 7 Resource Histogram
Week 6
Week 5
Week 4
Week 3
Week 2
Week 1
40 hrs
4.0
3.0
B B B B E E F J J G
2.0
C C C C C F E E J
1.0
A A A A D D G G H H
W1 W2 W3 W4 W5 W6 W7 W8 W9 W10
Resource Histogram
Resource Histogram - Leveling
Example
Time and resource estimates for a breakfast in bed project
Activity Effort Duration
(person-min) (min)
Butter toast 1 1
Pour orange juice 1 1
Boil egg 0 4
Slice bread 1 1
Fill pan with water 1 1
Bring water to boil 0 3
Toast bread 0 2
Take loaded tray to bedroom 1 1
Fetch tray, plates, cutlery 1 1
Initial project plan for a simple project
7 mins
Orange
4 mins
Bread Toast Butter
Orange
Bread Toast Butter
4
3
2
1
0
0 1 2 3 4 5 6 7 8 9
Time (min)
Revised plan with levelled resources
Activities requiring operator time
0 1 2 3 4 5 6 7 8 9
Orange
Bread Toast Butter
Water Boil water Boil egg Bedroom
Tray
Staff required
4
3
2
1
0 0 1 2 3 4 5 6 7 8 9
Time
(min)
Revised plan with levelled resources and warm
toast Activities requiring operator time
0 1 2 3 4 5 6 7 8 9
4
3
2
1
0 0 1 2 3 4 5 6 7 8 9
Time
(min)
Discussion