Overview and Short Comparison Between FIDIC's Red Book & New Red Book
Overview and Short Comparison Between FIDIC's Red Book & New Red Book
Overview and Short Comparison Between FIDIC's Red Book & New Red Book
November 2010
History and development The Fourth Edition was published in September 1987
In November 1996, FIDIC published a document entitled Supplement to Fourth Edition 1987- Conditions of Contract for Works of Civil Engineering ConstructionReprinted 1992 with Further Amendments. It is intended to provide the user with alternative arrangements in three controversial areas of the Red Book, thus giving him a choice in the method to be used for: settlement of disputes; payment; and preventing delay in certification for the purpose of payments.
The following MDBs have all participated in the preparation of the Red Book:
African development bank Asian development Bank Black Sea Trade and Development Bank Caribbean Development Bank European Bank for Reconstruction and Development Inter-American Development Bank International Bank for Reconstruction and Development Islamic Bank for development Bank Nordic Development Bank.
Main differences
An overall review of the New Red book indicated that the contractual impartiality of the Engineer has been diminished compared to the position in the Red Book.
For a more detailed analysis, the tables below highlight the main differences between the Red Book and the New Red Book.
Main differences
Red Book
2.1(a) The Engineer shall carry out the duties specified in the Contract () 3.1-
=> The New Red Book introduces an express statement regarding the relationship between the Employer and the Engineer
Engineer means the person appointed by the Engineer means the person appointed by Employer to act as Engineer for the purposes the Employer to act as the Engineer for the of the Contract and named as such in Part II of purposes of the Contact and named Appendix these Conditions to Tender, or other person appointed from time to time by the Employer and notified to the Contractor under Sub-Clause 3.4 [Replacement of the or => The definition in the New Book is larger and includes Engineer]other person
appointed from time to time by the Employer and notified to the Contractor
Clause 2.1
Clause 3.1
=> There are no significant differences between the two books. However the New Red Book has a more elaborated text in relation to the duties of the Engineer.
Red Book
Clause 2.3
Clause 3.2
=> In the New Red Book, unless agreed by both parties, the Engineer shall not delegate the authority to determine matters in accordance with SubClause 3.5 (Determinations). Any approval, consent, instruction, notices in accordance with the delegation, shall have the same effect as though it had been an act of the Engineer.
NA
(d) any delay, impediment or prevention by the Employer, and Sections] is or will be delayed by any of the following
fairly to entitle the Contractor to an extension of the Time the Employers other contractors on the Site (.)
=> a copy to the Employer. personnel (as referred to in the New Red Book means with The Employer the Engineer and the assistants so, the New Red Book entitles the Contractor to claim for an extension of time for any delay or prevention by the Engineer or his assistants.
Main differences
a- Obligations
Red Book
Clause 8.1 the Works and remedy any defects and he shall provide all superintendence, labour, all other things.
3) Contractor
New Red Book (1999)
Clause 4.1 complete the Works and shall remedy any defects in the Works. The Contractor shall provide the Plant and and all Contractors Personnel.
The Contractor shall execute and complete The Contractor shall design, execute and
materials, Plant, Contactors Equipment and Contractors Document specified in the Contract The Contractor shall give prompt notice to The Contractor shall be responsible for the the Engineer of any error, omission, fault or adequacy, stability and safety of all Site other defect in the design of or Specificationoperations and of all methods of construction. for their Works.
The Contractor shall, whenever required by the Engineers submit details of the arrangements and methods which the Contractor proposes to adopt for the execution of the Works. The Contractor shall also submit to the Engineer
=>The New Red Book has a more elaborated text Documents. the the Contractors concerning Obligations of the Contractor.
=> In the Red Book, the Contractor has no equivalent right of termination.
NA
=>In the New Red book and for the advantage of the Contractor this provision is deleted.
This presentation contains a random selection of information. This presentation and its content should not be taken, and are not intended to be taken, as a legal advice by any recipient or reader . Al-Jad does not provide any warranties or guarantees in relation to any information or material provided in this presentation. Should you wish to receive formal legal advice, please contact one of our team leaders.
www.al-jad.com