Bridge Repair and Methodology

Download as pptx, pdf, or txt
Download as pptx, pdf, or txt
You are on page 1of 85

Part 3:

Bridge Repair and Methodology


Reference:
REPAIR OF
CONCRETE BRIDGE
SUPERSTRUCTURE
AND
SUBSTRUCTURE
REPAIR METHOD
1. EPOXY INJECTION
2. CAULKING
3. PATCHING
4. RECASTING CONCRETE
5. CARBON FIBER SHEET BONDING TO DECKSLAB
6. PARTIAL DECKSLAB REPLACEMENT
7. WATERPROOFING ON DECKSLAB
8. FAST SETTING MORTAR CONTINUED DECKSLAB
9. PROTECTIVE MORTAR
10.CARBON FIBER SHEET/PLATE BONDING TO CONCRETE GIRDER
11.JACKETING WITH CONCRETE
EPOXY INJECTION

• Epoxy injection is used to restore


structural soundness of structures
exhibiting inactive cracks.
• Cracks with more than 0.3 mm up to
3.0 mm widths can be bonded and
sealed by injecting low viscosity
epoxy.
Work Sequence
1.Cleaning of Cracks.
2.Fitting of Injector
3.Sealing of Cracks at the Surface
4.Fitting of Injector
5.Injection of Epoxy
6.Curing of Injected Material
CAULKING
• Crack widths could be more than
3.0 mm with depth of less than
300 mm.
• In this case, the top surface
edges should be chipped or sawn
to form a V-type or U-type
groove, in order to provide a
caulking for inlet of gravity flow
of resin into the crack by
injection pump.
Work Sequence
1.Cleaning of the cracks.
2.Preparation of Caulking
3.Drilling Holes and Fixing the
Injection Pipes
4.Injecting Epoxy Grout
5.Curing of Injected Material
PATCHING
Patch repair is performed to restore small areas REBAR
where sound concrete is damaged by spalling,
scaling and impact. This method of repair is
generally applied using trowel and require none or
minimum formworks. The patch thickness is REPAIR MORTAR

limited to a maximum of 100 mm depth of hollow


surface.
• Type A Patching is used for defects without
REBAR RUST INHIBITIVE PRIMER
exposed rebar while
• Type B Patching is applied to defect of surfaces
with exposed rebar.
REPAIR MORTAR
Portland cement mortar is used for Type-A and
Polymer cement mortar is used for Type-B.
Work Sequence
1.Removal of Defective Concrete
2.Chipping and Cleaning of Concrete and
Rebar
3.Application of Epoxy Bonding Resin
4.Placing Cement Mortar
5.Curing
RECASTING CONCRETE
Recasting Method, which involves casting
of the damaged area, by placing concrete
or grouting mortar on the formwork, is
usually most suitable for severely
damaged concrete, or for largely damaged
areas with densely spaced rebars.
If concrete placing by vibration is often a
problem, grout and free flowing self-
compacting concrete should be developed
to minimize the vibration required.
Work Sequence
1. Removal of Concrete
2. Preparation of Old Concrete and
Rebar
3. Cutting of Deteriorated Rebar and
Adding New Rebar
4. Setting Formworks
5. Mixing of Mortar
6. Mortar Grouting
7. Curing and Removal of Formworks
CARBON FIBER SHEET BONDING TO
DECK SLAB
Carbon fiber sheet for reinforced concrete
repairs and strengthening systems consists
of a combination of carbon fiber reinforcing
material and adhesive resin such as epoxies
and other materials.

This composite product is intended to


enhance the capacity of the concrete deck
slab and extend its service life.
APPLICATION CRITERIA
Work Sequence
1.Preparation of Concrete
2.Application of Primer
3.Adjustment of Unevenness with
Putty
4.Application of Epoxy Resin for
Undercoat
5.Installation of Longitudinal Layer
CFS
6.Installation of Transversal Layer CFS
7.Squeezing out of Entrapped Air
8.Surface Protection
PARTIAL DECK SLAB
REPLACEMENT
Partial replacement of slab is carried out to replace
portion of the concrete that has been severely
damaged.

If damaged portion is not removed, further


deterioration is expected, which could impair the
strength, stability and serviceability of the structure.

The cause of such damage could be corrosion of


reinforcement, fracturing, spalling, delamination,
honeycomb or water leakage.
Work Sequence
1.Support of Existing Structure
2.Removal of Deck Slab Concrete
3.Preparation of Old Concrete and Rebar
4.Setting of Formworks
5.Cutting of Existing Rebar and Addition
of New Rebar
6.Placing of Concrete
7.Curing and Removal of Formworks
WATERPROOFING ON DECK
SLAB
Concrete is naturally alkaline and therefore
protects the steel. However, the effect of its
contact with water and corrosive materials
reduces the alkaline environment and allows an
electrolytic process to start, thus corroding the
rebar. The result of the corrosion and rusting is
to expand the rebar which then damages and
eventually destroys the surrounding concrete of
the deck. The primary protection against this
destructive damage is through installation of
waterproofing membrane on the deck slab.
Application Criteria
Work Sequence for Rubberize
Membrane Type
1. Preparation of Deck Surface
2. 1stLayer (Primer)
3. 2ndLayer (Base Coat)
4. 3rdLayer (Intercoat)
5. 4thLayer (Top Coat)
6. 5thLayer (Tack Coat)
7.Asphalt Pavement
Work Sequence for Rubberize Membrane
Type
1. Preparation of Deck Surface
2. 1stLayer (Primer)
3. 2ndLayer (Base Coat)
4. 3rdLayer (Intercoat)
5. 4thLayer (Top Coat)
6. 5thLayer (Tack Coat)
7.Asphalt Pavement
FAST SETTING MORTAR CONTINUED
DECK SLAB
Most of RCDG bridges are simple span
bridges. Furthermore, there are many
multiple span RCDG bridges designed
as simple spans with gaps between the
spans.
In order to strengthen the stability of
the bridge structure, continued deck
slab method is adopted to reduce the
bridge maintenance work and to
maintain good performance.
Work Sequence
1. Removal of Deck Slab Concrete
2. Setting of Formworks
3. Addition of Longitudinal /
Transverse Rebar
4. Apply Epoxy Resin to Existing
Concrete Surface for Proper
Bonding to Fast-setting Mortar
5. Pour Fast Setting Mortar
6. Finishing of Surface, Curing
PROTECTIVE MORTAR
• Protective mortar is made from
polymer cement with lithium
nitrate which is effective against
chloride ions.
• After or during application of
appropriate repair method,
protective mortar shall be applied
to concrete member.
Work Sequence
1. Surface Preparation
2. Mix Powder and Emulsion
One (1) kg of powder and 180g of emulsion
shall be mixed by hand. Use rubber gloves.
During mixing, do not add water.
3. Application of PCM with Lithium
Nitrite
4. Curing of PCM with Lithium Nitrite
CARBON FIBER SHEET/PLATE
BONDING TO CONCRETE GIRDER
Carbon fiber sheet/plate for
reinforced repair and strengthening
systems are combination of carbon
fiber sheet/plate material and
resins such as epoxies and other
adhesive materials, acting as a
composite material to enhance the
capacity and extend the life of
concrete structures
Application Criteria
Work Sequence for CFS
1.Preparation of Concrete
2.Application of Primer
3.Adjustment of Unevenness with
Putty
4.Application of Epoxy Resin for
Undercoat
5.Installation of CFS(1stlayer)
6.Squeezing Out of Entrapped Air
7.Over Coating Resin Application
8.Installation of CFS(2ndlayer)
9.Surface Protection
Work Sequence for CFP
1.Preparation of Concrete
2.Application of Primer
3.Adjustment of Unevenness with
Putty
4.Application of Epoxy Resin on CFP
5.Installation of CFP
6.Squeezing Out of Entrapped Air
7.Pressure Attachment of CFP
JACKETING WITH CONCRETE
Concrete jacket is applied to
protect the deteriorated concrete
due to corrosion of rebars,
damage due to rapid water flow
or broken due to continuous
impact from materials flowing in
the channel such as drift woods.
Work Sequence
1.Removal of Deteriorated
Concrete
2.Addition ofRebar
3.Setting-up of Formworks
4.Placing of Concrete
5.Curing of Concrete
REPAIR OF
STEEL BRIDGE
SUPERSTRUCTURE
AND
SUBSTRUCTURE
OUTLINE
A. TYPE OF DEFECTS
B. PROCEDURE FOR SELECTING REPAIR METHOD
C. REPAIR METHOD
TYPE OF DEFECTS

• CORROSION
• PAINT PEEL OFF
• LOOSE CONNECTION
• HEAT DAMAGE
PROCEDURE FOR SELECTING REPAIR METHOD
PROCEDURE FOR SELECTING REPAIR METHOD
PROCEDURE FOR SELECTING
REPAIR METHOD
LOOSE CONNECTION
REPAIR METHOD
• REPAINTING
• STEEL PLATE ADDING
• CARBON PLATE BONDING
• TIGHTENING/RETIGHTENING OF HIGH TENSION BOLT
• SPECIAL ANTI CORROSION PAINT
REPAINTING
The service life of steel bridges could be expected to exceed 50 years if
its surface is kept in good protection using suitable paint coating.
However, if corrosion occurs, repainting is the only restoration and
effective method for steel structures. Before repainting, the surface, at
first be washed by fresh water to remove any salt from sea water
environment. Relevant surface preparation shall be applied for the
corroded areas to remove rust.
【 During new 【 Loss of sectional 【 Corrosion 】
construction 】 area 】
POINT OF PAINTING
• Proper Preparation before painting (Cleaning by water spray)
• Remove existing paint and rust layer by Grinder
• Check the specification of Material
• Painting interval
• Adequate paint layer
• primer + Coat + 2 paint layer (Total 4layer)
• Safety gears (eyeglass, groves)
STEEL PLATE ADDING
Steel girders near sea shore are prone to corrosion which could
accelerate, consequently leading to section loss, especially of the
bottom flange plates and sections near the bearings.
There were incidences where existing steel bridges near sea shores
were not maintained for around 20 years. Severe corrosion had
occurred causing significant section loss and defective bolt holes. In
such cases, strength of the lower flange section shall be restored
considering the original designed area. This is implemented by adding
steel plates or angles connected with high tension bolts
STEEL PLATE ADDING
POINT OF STEEL PLATE ADDING AND
REPLACEMENT OF HIGH TENSION BOLTS
• Steel Plate adding
• Proper Preparation
• Cleaning by water spray
• Remove existing paint and rust layer by Grinder
• Epoxy caulking between existing and new plate
• Proper paint after plating
• Replacement of HTB
• Proper Preparation
• Cleaning by water spray
• Remove existing paint and rust layer by Grinder
• Proper tool for fasten
CARBON FIBER PLATE
BONDING
• Repair method using carbon fiber plate (CFP) bonding to steel plate
provides the same function as the additional steel plates presented
in previous slides.
• CFP method involves simple application of bonding to steel bridge
surface using epoxy resin adhesive.
CARBON FIBER PLATE
BONDING
TIGHTENING/RETIGHTENING OF
HIGH TENSION BOLT
SPECIAL ANTI CORROSION
PAINT
REPAIR OF
EXPANSION JOINTS
& BEARINGS
ASPHALTIC PLUG JOINT

TYPE OF ASPHALTIC PLUG JOINT

Considerations:
• usual gap of concrete is around 20 mm

• temperature here in the Philippines is 27°C ± 10 °C


• movement of the bridge span is 12x10⁻⁶/°C x 20mx(± 10 °C)= ±2.4mm if
the span length is 20m.
• movement of the traffic load is approximately < 5mm
• total movement of the usual span RCDG is below ± 10mm
APPLICATION CRITERIA

Asphaltic plug joints are mainly applied on RCDG bridges and steel girder
bridges on fixed bearings. This repair method shall be implemented if the
following conditions are rated as “Bad” as per suggested condition rating criteria:

- Water leakage: detected area >50%


- Abnormal Space/ Noise: Detected
- Difference in Elevation: >30mm at expansion gap
- Deteriorated Sealant: Pourable joint sealant almost completely lost.
Work sequence
1. Dismantle Existing Damaged 3. Install steel frame
Asphalt Joint Sealant

2. Chipping surface concrete 4. Rebar Anchor


Work sequence
5. Pouring Flexible 7. Pouring Flexible Asphalt
Asphalt
-poured to the chipped off edges -flexible asphalt poured as second layer

height of pouring is half of total thickness

6. Installation of Expansion Sheet


REPLACEMENT OF EXPANSION JOINT
This repair method is intended for damaged steel type and rubber
type expansion joints, which would be replaced with suitable
water-proof type expansion joints.
APPLICATION CRITERIA
The replacement of steel expansion joint shall be implemented if the following conditions are
rated as “Bad” as per suggested condition rating criteria:
• Water Leakage: Detected area > 50%
• Abnormal space/noise: Detected
• Difference in elevation: Difference in elevation is >30mm at expansion gap
• Displacement: Pourable joint sealant maybe almost completely lost
• Cracking: Cracking on primary members especially in welded parts

Meanwhile, replacement of rubber expansion joint shall be implemented if the following


condition criteria are rated “Bad”:
• Water leakage: detected area >50%
• Abnormal Space/ Noise: Detected
• Difference in Elevation: >30mm at expansion gap
• Rupture: Rubber seal dislodged or peeled-off
• Abnormal Space/ Noise: Detected
• Deteriorated Sealant: Joint sealant maybe almost completely lost.
Work sequence
1.Cut concrete surface 3. Set up new expansion joint

2. Chipping off concrete/ 4.Pouring Concrete


Dismantling defective expansion joint
REPLACEMENT OF
BRIDGE BEARING

SAMPLE OF REPLACEMENT BEARING RUBBER BEARING

APPLICATION CRITERIA
Replacement of bearing shall be implemented if existing rubber
bearings already exhibited severe cracks and abnormal bulging.
Old steel bearings need to be replaced especially if loose connections
were observed.
Work sequence
1. Jack up girder 3.Cast New Bearing Seat and
Set up New Bearings

2. Dismantle existing Bearing 4.Jack Down Girder after


and chipping bearing base Curing
Work sequence

5.Dismantle Jacks and


Temporary Supports for the
Final Work
EXTENSION OF BEARING SEAT
Normally, the bearings transmit all the loads (dead load, live load, wind pressure, and
others) from the superstructure to the substructure. Consequently, reaction is concentrated
near the bearing seat. This sometimes causes damage to the bearing seat.

APPLICATION CRITERIA
Bearings are sometimes installed close to the edge of the concrete coping. There
are cases that these coping edges break off due to support reactions from traffic
impact loading. This signifies risk of superstructure collapse as the required bearing
seat was reduced.
EXTENSION OF BEARING SEAT
Work sequence
1. Chipping and 4. Formwork
Drilling Holes

3. Arrangement
of re-bars

2. Anchor Bar Fitting 5. Pouring concrete


REPAINT OF STEEL BEARING

REPAINT OF STEEL BEARING

APPLICATION CRITERIA
Steel bearings shall be subject to repainting if based on results of
bridge inspection, a “bad” rating is given due to observed severe
corrosion or section loss of more than 20%.
Work Sequence

2. Surface Preparation for


1. Scaffolding Steel Bearings 3. Painting

Required Materials:
• Zinc-rich base primer
• Polyurethane Aluminum Paint
• Aluminum paint shall consist of aluminum bronze powder or
paste of the required fineness and composition to which shall
be added the specified amount of agent component.
• Thinner
• Modified epoxy polymide primer
• Special Anti-Corrosion paint DPWH Standard Specification
ITEM 709
• Paint also applies to this work item.
SPECIFICATION
Material Requirements Repainting shall be applied according to three grades of surface
preparation as follows:
SPECIFICATION FOR 1ST GRADE SURFACE
PREPARATION .

THE MATERIAL SHALL BE APPROVED BY THE ENGINEER THROUGH MILL CERTIFICATE OF THE SUPPLIER.
SPECIFICATION
SPECIFICATION FOR 2ND GRADE SURFACE PREPARATION

THE MATERIAL SHALL BE APPROVED BY THE ENGINEER THROUGH MILL CERTIFICATE OF THE SUPPLIER.
SPECIFICATION
SPECIFICATION FOR 3RD GRADE SURFACE PREPARATION .
PHYSICAL AND MATERIAL TEST AND SPECIFICATION IS MENTIONED IN BELOW TABLE.

THE MATERIAL SHALL BE APPROVED BY THE ENGINEER THROUGH MILL CERTIFICATE OF THE SUPPLIER. APPROPRIATE
MATERIAL SHOULD BE SELECTED IN ACCORDANCE WITH MANUFACTURER’S INSTRUCTIONS.
THANK YOU!

You might also like