Bridge Repair and Methodology
Bridge Repair and Methodology
Bridge Repair and Methodology
• CORROSION
• PAINT PEEL OFF
• LOOSE CONNECTION
• HEAT DAMAGE
PROCEDURE FOR SELECTING REPAIR METHOD
PROCEDURE FOR SELECTING REPAIR METHOD
PROCEDURE FOR SELECTING
REPAIR METHOD
LOOSE CONNECTION
REPAIR METHOD
• REPAINTING
• STEEL PLATE ADDING
• CARBON PLATE BONDING
• TIGHTENING/RETIGHTENING OF HIGH TENSION BOLT
• SPECIAL ANTI CORROSION PAINT
REPAINTING
The service life of steel bridges could be expected to exceed 50 years if
its surface is kept in good protection using suitable paint coating.
However, if corrosion occurs, repainting is the only restoration and
effective method for steel structures. Before repainting, the surface, at
first be washed by fresh water to remove any salt from sea water
environment. Relevant surface preparation shall be applied for the
corroded areas to remove rust.
【 During new 【 Loss of sectional 【 Corrosion 】
construction 】 area 】
POINT OF PAINTING
• Proper Preparation before painting (Cleaning by water spray)
• Remove existing paint and rust layer by Grinder
• Check the specification of Material
• Painting interval
• Adequate paint layer
• primer + Coat + 2 paint layer (Total 4layer)
• Safety gears (eyeglass, groves)
STEEL PLATE ADDING
Steel girders near sea shore are prone to corrosion which could
accelerate, consequently leading to section loss, especially of the
bottom flange plates and sections near the bearings.
There were incidences where existing steel bridges near sea shores
were not maintained for around 20 years. Severe corrosion had
occurred causing significant section loss and defective bolt holes. In
such cases, strength of the lower flange section shall be restored
considering the original designed area. This is implemented by adding
steel plates or angles connected with high tension bolts
STEEL PLATE ADDING
POINT OF STEEL PLATE ADDING AND
REPLACEMENT OF HIGH TENSION BOLTS
• Steel Plate adding
• Proper Preparation
• Cleaning by water spray
• Remove existing paint and rust layer by Grinder
• Epoxy caulking between existing and new plate
• Proper paint after plating
• Replacement of HTB
• Proper Preparation
• Cleaning by water spray
• Remove existing paint and rust layer by Grinder
• Proper tool for fasten
CARBON FIBER PLATE
BONDING
• Repair method using carbon fiber plate (CFP) bonding to steel plate
provides the same function as the additional steel plates presented
in previous slides.
• CFP method involves simple application of bonding to steel bridge
surface using epoxy resin adhesive.
CARBON FIBER PLATE
BONDING
TIGHTENING/RETIGHTENING OF
HIGH TENSION BOLT
SPECIAL ANTI CORROSION
PAINT
REPAIR OF
EXPANSION JOINTS
& BEARINGS
ASPHALTIC PLUG JOINT
Considerations:
• usual gap of concrete is around 20 mm
Asphaltic plug joints are mainly applied on RCDG bridges and steel girder
bridges on fixed bearings. This repair method shall be implemented if the
following conditions are rated as “Bad” as per suggested condition rating criteria:
APPLICATION CRITERIA
Replacement of bearing shall be implemented if existing rubber
bearings already exhibited severe cracks and abnormal bulging.
Old steel bearings need to be replaced especially if loose connections
were observed.
Work sequence
1. Jack up girder 3.Cast New Bearing Seat and
Set up New Bearings
APPLICATION CRITERIA
Bearings are sometimes installed close to the edge of the concrete coping. There
are cases that these coping edges break off due to support reactions from traffic
impact loading. This signifies risk of superstructure collapse as the required bearing
seat was reduced.
EXTENSION OF BEARING SEAT
Work sequence
1. Chipping and 4. Formwork
Drilling Holes
3. Arrangement
of re-bars
APPLICATION CRITERIA
Steel bearings shall be subject to repainting if based on results of
bridge inspection, a “bad” rating is given due to observed severe
corrosion or section loss of more than 20%.
Work Sequence
Required Materials:
• Zinc-rich base primer
• Polyurethane Aluminum Paint
• Aluminum paint shall consist of aluminum bronze powder or
paste of the required fineness and composition to which shall
be added the specified amount of agent component.
• Thinner
• Modified epoxy polymide primer
• Special Anti-Corrosion paint DPWH Standard Specification
ITEM 709
• Paint also applies to this work item.
SPECIFICATION
Material Requirements Repainting shall be applied according to three grades of surface
preparation as follows:
SPECIFICATION FOR 1ST GRADE SURFACE
PREPARATION .
THE MATERIAL SHALL BE APPROVED BY THE ENGINEER THROUGH MILL CERTIFICATE OF THE SUPPLIER.
SPECIFICATION
SPECIFICATION FOR 2ND GRADE SURFACE PREPARATION
THE MATERIAL SHALL BE APPROVED BY THE ENGINEER THROUGH MILL CERTIFICATE OF THE SUPPLIER.
SPECIFICATION
SPECIFICATION FOR 3RD GRADE SURFACE PREPARATION .
PHYSICAL AND MATERIAL TEST AND SPECIFICATION IS MENTIONED IN BELOW TABLE.
THE MATERIAL SHALL BE APPROVED BY THE ENGINEER THROUGH MILL CERTIFICATE OF THE SUPPLIER. APPROPRIATE
MATERIAL SHOULD BE SELECTED IN ACCORDANCE WITH MANUFACTURER’S INSTRUCTIONS.
THANK YOU!