Project Control: American University in Cairo Egypt Presented by Dr. Hesham A. Aziz
Project Control: American University in Cairo Egypt Presented by Dr. Hesham A. Aziz
Change orders
Progress Reports
Indirect & Overhead costs Other Contract costs Lump-sum Contract costs
Project Control
Labor costs
Equipment costs
Project Manger
Project completion price Programmed status
MICRO LEVEL
Project team
Changes In scope
Abortive work Future problem Site instructions And variations areas Dr. Hesham A. Aziz
Time-Phase Baseline Plan Corrects the failure of most monitoring systems to connect a projects actual performance to its schedule and forecast budget. Systems that measure only cost variances do not identify resource and project cost problems associated with falling behind or progressing ahead of schedule.
Earned Value Cost/Schedule System An integrated project management system based on the earned value concept that uses a time-phased budget baseline to compare actual and planned schedule and costs.
10
11
12
13
14
15
16
17
18
The slope of each graph is the ratio of the weight multiplier to the time required for the work to be performed.
19
Over Laps
20
Over Laps
21
22
23
3 1
24
25
26
Earned value analysis makes use of the following variables: Actual cost of the works performed (ACWP); Budgeted cost of the works performed (BCWP); Budgeted costs of the works specified (BCWS); Scheduled time for work performed (STWP); Actual time for work performed (ATWP); Cost Variance (CV); Schedule variance (SV); Budget at completion (BAC); Estimate at completion (EAC); Variance at completion (VAC).
28
Total work package budgeted cost = 1 000 000 The EVA analysis is taken up to week 6 (week 6 is time now). The actual progress or works performed is 70 per cent. This means: Budgeted cost of the works performed (BCWP) = 1 000 000 70% = 700 000 Actual cost to date = 750 000 Work scheduled to date = 60% Budgeted cost of the works scheduled (BCWS) = 1 000 000 60% = 600 000
Dr. Hesham A. Aziz 29
Position at week 6
30
Position at week 7
31
32
33
34
Estimate at Completion
Risk
Schedule Delay
$
Actual Cost
Planned Value
Earned Value
Dr. Hesham A. Aziz
Time
35
The variance of completion (VAC) is the difference between the planned and actual cost. The cost variance is the result of a comparison of how much the work has cost in comparison with what it was budgeted to cost, both in relation to works actually completed. Schedule variance (SV) is the difference between budgeted cost for the works completed and performed and the budgeted cost of the works scheduled The budget at completion (BAC) is the sum of all the individual budgets (BCWS) that make up . It is sometimes known as the baseline. The estimate at completion (EAC) is the estimated total cost . It is the sum of all direct and indirect costs to date plus authorized work remaining. The EAC can also be expressed in terms of a revised estimate. The cost accounting process of the PCCS involves looking at cost variance (CV) and schedule variance (SV) in order to assess the performance of individual packages and groups of packages. This can be done in several ways. The two most common are by direct evaluation of the variances themselves or by conversion of the variances to indices.
Dr. Hesham A. Aziz 36
Scheduled time for work performed (STWP) This is the estimated time required to perform a defined amount of work. Actual time for work performed (ATWP) This is the actual time taken to perform a defined amount of work. Cost Variance (CV) The cost variance is the budgeted cost of work performed (BCWP) minus the actual cost of work performed (ACWP). This is normally abbreviated to the formula:
CV = BCWP ACWP
Cost variance is therefore a comparison of how much the work has cost in relation to what it was budgeted to cost, both figures being in relation to works actually completed. Schedule variance (SV) The schedule variance is the difference between budgeted cost for the works performed (BCWP) and the budgeted cost of the works scheduled (BCWS). This is normally abbreviated to the formula:
SV = BCWP BCWS
Schedule variance is therefore a measure of the performance of the works in relation to budgeted costs.
Dr. Hesham A. Aziz 37
Estimate at completion (EAC) :is the estimated total cost . It is the sum of all direct and indirect costs to date plus authorized work remaining.
EAC = BAC CV
EAC can also be expressed in terms of the cost variance index (CVI) as
39
CV = BCWPACWP = 75 00090 000 = 15 000 (i.e. a cost overrun of 15 000) SV = BCWPBCWS = 75 00050 000 = 25 000 (i.e. ahead of schedule by 25 000) TV = STWP ATWP = 3 months 2 month = 1 month (i.e. one month ahead of time schedule) CV ratio =BCWP/ACWP=75 000/90 000= 0.83 SV ratio =BCWP/BCWS=75 000/50 000= 1.5 TV ratio =STWP/ATWP=3/2= 1.5
Dr. Hesham A. Aziz 40
Cost/Schedule Graph
41
42
Example budget and actual costs to end of month 4 Example planned and actual schedule performance Dr. Hesham A. Aziz 43
The critical ratio can often be used to trigger alarm bells if work performance falls below a certain level. The critical ratio is equivalent to (actual progress / scheduled progress) (budget cost / actual cost) A critical ratio of unity or more is good and means that actual performance is better than planned performance. Conversely, a critical ratio less than unity is poor and is an indication of underperformance.
44
CVI > 1.0: good CVI < 1.0: bad CVI = 1.0: ok . And Schedule Variance Index (SVI) =BCWP/BCWS so that SVI > 1.0: good SVI < 1.0: bad SVI = 1.0: ok
45
CVI > 1.0, SVI > 1.0 Excellent: the project is under cost and ahead on programmed. CVI > 1.0, SVI = 1.0 Good: the project is under cost and is on schedule. CVI > 1.0, SVI < 1.0 Good/bad: the project is under cost but behind on programmed. CVI = 1.0, SVI > 1.0 Good: the project is on cost and ahead of programmed. CVI = 1.0, SVI = 1.0 Good: this scenario means that the project is on cost and on schedule. CVI = 1.0, SVI < 1.0 Bad: the project is on cost but is behind schedule CVI < 1.0, SVI > 1.0 Good: this scenario is probably caused by faster than expected working practices. CVI < 1.0, SVI = 1.0 Poor: the project has a cost overrun and is on programmed. CVI < 1.0, SVI < 1.0 Very bad: this is the worst case. The project is running over cost and behind on programmed.
Dr. Hesham A. Aziz 46
Critical-ratio analysis
Zone A: Take no action Zone C: Act immediately Zone A1: Observe and note
Zone B: Record and monitor Zone D: Emergency response required Zone A2: Investigate and correct
47
48
49
50
CAC
A1 A2 A3 A4 A5 A11 A22 A33 A44 A55 A66
ACWP
6000 6000 6500 4100 2300 7200 8500 8000 3000 3000 5500
BCWP
5000 6000 6300 3600 1800 7200 8400 9000 4000 3000 5000
BCWS
10000 8000 7000 3000 1000 6000 7000 9000 4000 1385 909
CV
-1000 0 -200 -500 -500 0 -100 1000 1000 0 -500
SV
-5000 -2000 -700 600 800 1200 1400 0 0 1615 4091
Comments Very over budget and very late. On cost but very late Over budget and late. Over budget but ahead of schedule Over budget but ahead of schedule On cost and way ahead of schedule. Over cost but way ahead on schedule. Under cost and on schedule. Under cost and on schedule. On cost and way ahead of schedule Over cost but way ahead of schedule Over cost but well ahead.
Total
-800
2006
51
53
FIGURE 13.14
55
57