Conflict Dispute
Conflict Dispute
Conflict Dispute
CE 422
CONFLICT MANAGEMENT
AND DISPUTES RESOLUTION
Prepared by:
Engr. Ernesto F. Capinding, Jr.
TOPICS
OUTLINE CONFLICT MANAGEMENT AND
DISPUTE RESOLUTION
1. Conciliation
2. Mediation
3. Adjudication
4. Arbitration
5. Litigation
CONFLICT MANAGEMENT AND
DISPUTE
CONFLICT
• A serious disagreement or argument.
• Forcing
• Confronting the problem
• Compromising
• Smoothing
• Withdrawing
1. Forcing
• involves one party using its authority acquired by virtue of position in the
organization, rank or technical knowledge to force through its point of view.
• Used in a project environment where there is a health and safety issue, or in an
emergency posing a risk of serious physical damage.
• In most of the situations where forcing has been used to solve a conflict, one party
almost certainly feels aggrieved with a consequent adverse effect on morale and
future cooperation.
• This could occur where one party has more authority or power (financial,
political or organizational) or where the arguments put forward are more cogent.
• does not mean complete surrender, as it may just not be opportune or politically
wise at this particular time to be more assertive.
• While this may appear to be a sign of weakness, there may be good reasons for
taking this stance:
One may be aware that the dispute will blow over when the other party’s anger
has cooled down or a confrontation is likely to inflame the situation even
more.
One may also feel that the possibility of winning the argument is small, so that
by making what may be considered a small concession, good relations are
maintained.
2. There may be delay in release of areas as per contract. Besides, site conditions differ to a
large extend from those described in the contract document.
3. The owner may desire to get the work done at a faster pace than is required by the
contract document.
7. There may be levy of liquated damages (LD) on the contractor. Other recoveries from
bills may also lead to contractor raising the claim.
In a letter dated June 30, 1998, a contractor makes a claim for (an amount)
additional work in dewatering of foundations, resulting from unforeseen rains
in the month of May and the item not being provided for the contract. The
details of the rainfall and the costs incurred in terms of manpower, equipment,
power consumption, overtime payments made, are annexed to the claim along
with photographs.
In a letter dated July 13, 1998, the owner acknowledge the receipt of the a
foresaid letter from the contractor, and inform them of the owner’s decision to
(a) impose LD for the delay of work, and (2) recover the amount (towards LD).
Does the matter define a dispute?
I. Conciliation
• Informal process in which the parties are assisted by one or more neutral
parties in their efforts towards settlement.
• The main purpose of conciliation is to establish communications between
the parties so that negotiations can be resumed.
• Conciliators should not try to apportion blame, but to focus on the common
interests of the parties and the systemic reasons for the breakdown of
relationships.
• it requires the agreement of both parties, this also means that both parties
have to agree as to who would be the adjudicator.
• process: follow strict adjudication procedures
…thank you!