Chap05 - Project Monitoring and Control
Chap05 - Project Monitoring and Control
Chap05 - Project Monitoring and Control
Learning Outcomes
Understanding what is tracking, monitoring and control
and its benefits
Understanding Project Control Process
Understanding Earned Value Technique (EVM) and
solving EVM problems based on specific short cases
Project Change Management and Control Processes
Project Tracking, Monitoring and Control:
• Project Tracking-fact finding processes
• Project monitoring-analysis of these facts
• Project control-progress against the plan
• Murphy Law
• Benefits of PMC: Meeting its planned objectives (timeframe, budget, performance), reveal problems
early, accountability and communication, motivate staff, draw lessons
• Project tracking and monitoring information: written status reports, schedule performance, resource
analysis, Financial analysis, project performance review presentations
• Project Control Processes: identify potential problems early, compare the data, make recommendations
• Achieving self-control: clear definition of role, personal plan, skills and resources, feedback, clear
definition of authority
• EVM technique: integrates scope, time and cost data and for a snapshot in time. Early warning system
Setting a baseline/ entering actual information
• Bringing performance under control: take care of CPM- resources, activities, adjusting resources, no out
of scope work, new risks, issues
• Bringing costs under control: less expensive resource, adjust time frame, plan optimised for resources
• Change-controlled and communicated
• Change control process: change request in change control form, size of change, impact analysis,
review/approval by change control board, Accept/Reject/Put-on-hold change
Definitions
• Project Tracking is defined as the fact-finding processes and ,
• Project Monitoring is defined as the analysis of these facts collected
– Both are needed for effective management of a project.
• Project Control compares progress against the plan so that corrective
action can be taken when a deviation
– Control processes also predict what may happen in the future if the present
conditions continue.
If the EV line is below the AC or PV line, there are problems in those areas/project.
Activity Rules
• There are multiple methods for determining Earned Value. The rules for
determining Earned Value should be documented in the Planning Phase.
– The rules are all based on the percent complete of an activity and include:
• 0/100 rule: this rule allows the project to earn 100% of the value of each
activity only when it has been completed.
– It is considered the most conservative of the Earned Value rules. Even if the activity is
90% complete, only 0% is earned until the activity is 100% complete.
• 50/50 rule: this rule allows the project to earn 50% of the value of an activity
as soon as the activity starts.
– The last 50% can only be earned after the activity has completed.
• Proportional rule: this rule uses the actual effort or duration spent so far
on an activity to determine the portion of the activity that is complete.
– This rule is the most common rule used and is supported by most software applications
such as Microsoft® Project.
– For example, if the activity was estimated to take 10 days and 5 days have already been
spent working on the activity, then the proportional percent complete is 50%.
– Alternatively, If the activity is estimated to take 20 effort hours and 10 hours have
already been expended to date, then the activity is 50% complete and the project can
earn 50% of the value of the activity.
Issues with Percent Complete for EVM Calculations
• Once the percent complete is known, then the total Planned Value (or
budgeted value) for that activity is multiplied by the percent complete to
determine the Earned Value.
– For example, if the activity was budgeted (planned) to cost $100, and the
percent complete of that activity at a point in time is 50%, then the Earned
Value for the activity is $50 (50% x 100 = 50).
– There is some risk with this rule if activities are underestimated, since the
project could be reporting 50% of the activity as earned, however more than
50% of the work or duration is still remaining to finish the activity. For this
reason, some Project Managers require team members to not only report the
effort hours expended to date, but they also require team members to
estimate the remaining effort hours of work. In this way, they can adjust for
the proper Earned Value percent.
– Additionally, if the project has held themselves to the estimating rule of no
activity being more than 10 days in duration, then this risk is also mitigated.
9-14/15
Interpreting EVM Results
• Negative numbers for cost and schedule variance indicate problems in
those areas
• CPI and SPI less than 100% indicate problems
– Problems mean the project is costing more than planned (over budget) or taking longer
than planned (behind schedule)
• Zero variances (very rare);
• Problem indicators variance >10% or $ variance >$50,000 at the control
account level
• Monthly trends turning negative or downward
• Schedule variances usually indicate cost variances will follow
• When Actuals > Baseline or Latest Revised Estimates (LRE) means a new
Baseline / LRE needs to be developed to see what program cost will be
• When BCWP increases with no increase in ACWP (Should not be adding
budget if actuals are not indicating it is needed)
Tools PM have to bring SPI under Control
9-17/15
Change Control - Overview
• Change must be controlled and communicated.
• A change control process is used to manage changes to the baseline plan
for scope, cost, or schedule.
– Changes in scope would include such things as: added features or functions to the
product, any new deliverables, any new requirements, any added or removed activities
that affect the content/requirements of the project deliverables.
– Changes in cost would include such things as: additions or subtractions to the budget to
complete the project when performance metrics are outside the variance limits.
– Changes in schedule would include such things as: needing additional time to complete
the project deliverables, or change to original commitment to deliver the project
Milestones.
• To reiterate, the changes we are discussing here are changes that would
breach a measurement variance as defined in the Quality Plan.
– For example, if we determined a cost variance of plus or minus 5% was an acceptable
variance for budget, then we can make budget adjustments within that variance without
requiring a Change Order.
– If however, the budget change breaches the variance limit, then we will need to
document a Change Order. Similarly this scenario holds true for the assessment of
variance to scope and schedule.
9-18/15
Project Change Management
• The Change control Form and Change Log are the primary artifacts.
9-21/15
Variance Analysis using Spending Curves
Acceptable Variances
If you are doing a well-defined construction job, the
variances (cost & schedule) can be in the range of
+3–5 percent. If the job is research and This generally
development, acceptable variances increase happens because the
generally to around +10–15 percent. original estimate was
too conservative
It is not enough to recognize a variance. Its
cause must be determined so that
corrective action can be taken.