Untitled

Download as pptx, pdf, or txt
Download as pptx, pdf, or txt
You are on page 1of 10

INTRODUCTION

PEDA is State Nodal Agency for Implementation of Renewable


Projects/Schemes in the State. Under this following 03 Programmes of
Biogas/CBG are being implemented in the State.
1. New National Biogas and Organic Manure Progamme. (NNBOMP)
2. Biogas Power Generation (off-grid) Thermal application Programme.
(BPGTP)
3. Waste to Energy Programme.
NNBOMP Scheme

Under this scheme Domestic type Biogas Plants in the range of capacity from 1
cum to 25 cum are taken up .
•Uses of Domestic type Biogas Plants.;-
•Cooking
•Biogas can be used in a specially designed burner for cooking. A biogas plant of
6 cum. capacity is sufficient for providing cooking fuel to a family of 10 to 12
members.
•Lighting:-    

Gas lamps can be fueled by biogas. The requirement of gas   for powering a 100
candle lamp (60 W) is 0.13 cum. per hour.
Pattern of Central Financial Assistance for 2020-21
Sr No. Particulars of Central Biogas Plants under NNBOMP (size 1 to 25 cubic metre biogas per day)
Financial Assistance (CFA)

A Central subsidy Rates 1 cubic Metre 2-6 Cubic 8-10 cubic 15 cubic metre 20-25 cubic
Applicable (in Rs. Per Metre metre metre
plant))

1 For the State of Punjab 7500 12,000 16,000 20,000 25,000


2 Additional Subsidy for 1600 1600 1600 Nil Nil
cattle dung based biogas
plants if linked with
sanitary toilets, only for
individual households1600
(Rs. Per biogas Plants) fixed
Biogas Power Generation (Off-grid) and Thermal application
Programme (BPGTP)

Objective:-
To promote Decentralized Renewable Energy Source (DRES) of power generation,
specifically in the small capacity range (3 Kw to 250 kw) and thermal energy for
heating/cooling from the biogas produced from Biogas Plants of 30 m3 to 2500 m3 size,
operated based on the availability of required quantity of biodegradable organic waste (s).
Procedure of implementation:-
The proposals of the project under the scheme is developed and prepared as per available
and proposed feeds stocks and requirement of power /thermal load/cooling load and its
handling management at the users end. The proposals are submitted by the designated
Programme implementing agencies (PIAs) of the scheme to the MNRE in the prescribed
format for a principal approval.
Central Financial Assistance (CFA)

Power generating capacity Biogas plant capacity (in cubic CFA/subsidy limited to the following ceiling or 35% of the
(Kw) metre) project cost whichever is less
Power Generation Thermal application

3-20 Kw Rs. 35,000/- (Rupees Thirty five Rs. 17,500/- (Rupees Seventeen
30 m3 thousand only )per kw thousand five hundred only)per
To Kw eq thermal/cooling
200 m3
 
 
>20 kw up to 100 kw Biogas plants of above 200 cu. Rs. 30,000/- (Rupees Thirty Rs. 15,000/- (Rupees fifteen
Metre size or any combination thousand only) per kw thousand only )per Kw eq
of above plants or approved thermal/cooling
alternate matching
capacity/design

>100 kw up to 250 kw 1000 cu metre biogas plant of Rs. 25,000/-(Rupees Twenty five Rs. 12,500/-(Rupees twenty
single digester or combination thousand) per Kw thousand five hundred only) per
of above plants or approved kw eq thermal /cooling
alternate matching
capacity/design
Waste to Energy/CBG Programme

Under this programme Generation of Biogas from biomethanation of Urban waste


including segregated MSW/Agricultural Waste/industrial wastes/Effluents or mix of
these wastes.
Components:-
1. Generation of Biogas from Biomethanation of Urban waste including segregated
MSW/Agricultural Waste/Industrial Waste/Effluents or mix of these wastes ; and
2. BioCNG/Enriched Biogas production from Biogas generated.
Central Financial Assistance (CFA)
Out put CFA
Biogas Rs. 1.0 crore (per 12000m3 Biogas/day
(Maximum CFA-Rs. 10 crore/project)
Bio CNG/Enriched Biogas/Compressed Rs. 4.0 crore per 4800 kgs of BioCNG/day
Biogas generated from 12000m3 Biogas/day (Mweq)
(maximum CFA-Rs. 10 crore/project)
Power (based on Biogas) a) Gas engine/turbine route
Rs. 3.0 crore/MW(Maximum CFA-Rs. 10
crore/project)

b) Boiler + steam turbine route


Rs. 1.5 crore/MW (Maximum CFA-

Rs. 10 crore/project
Procedure of implementation

1. The developers of new/expansion WTE projects including projects based on


MSW intending to avail financial support are required to submit the request of
application form along with enclosers. After getting all statutory clearances to
this Ministry through Financial Institutions =/Banks before COD of the plant for
‘’in principle’’ approval of CFA .
2. A copy of the proposal is also be submitted to the concerned State Nodal
Agency for information
‘’ In-Principle’’ approval
3. A Project Advisory Committee(PAC) for Waste to energy projects constituted
with the approval of Secretary, MNRE under the Chairmanship of Joint Secretary
(In-charge) MNRE evaluate and recommend the project proposals for financial
support. The Ministry issue ‘’in Principle’’ approval with the concurrence of IFD and
approval of Secretary, MNRE subject to fulfilling of all eligibility conditions for grant
of financial support within 45 days from the date of PAC.
Different types of Biogas Plants

New National Biogas and Organic Manure Programme Biogas Power Generation(Off-grid) Thermal application
Programme (BPGTP)

Compressed Bio Gas Project Village handiaya, Power/CBG Project at Haibowal Dairy Complex,
Distt Barnala Ludhiana
Thanks