Use of Pert and CPM Model in Projects
Use of Pert and CPM Model in Projects
Development of Project Network Time estimation Determination of Critical Path Scheduling of the activities when resources are limited Crashing of the Project Network Cost controlling
Construction of a plant
Building of a river valley project Training of a manpower Starting a new venture Characteristics of the above projects that make them amenable to analysis by PERT and CPM: - Project broke down into set of jobs - Jobs must be performed into certain sequence - Jobs can be start or stop in an independent manner
1 Receive Guests
3 Take Dinner 4
a succeeding event.
Denoted
numerically
by
pair
of
preceding and succeeding event. Each event should have a unique number. No loops in the project network Not more than one activity can have the same preceding and succeeding event.
TIME ESTIMATION
Three time values are obtained for each activity, - Optimistic time (to) - Most likely time (tm) - Pessimistic time (tp) Average time:
Calculate the Earliest occurrence time (EOT) for each event - Earliest Starting time
EST(i, j) = EOT(i)
- Earliest Finishing time EFT(i, j) = EOT(i) + d(i, j)
CONT.
Obtain the Critical and Slack paths Compute the Activity floats
Total float (i, j) = LOT(j) - EOT(i) - d(i, j) Free Float (i, j) = EOT(j) - EOT(i) - d(i, j)
All Events occur at their earliest time (EST & EFT) May have Time lags in completion of certain activities
2 days (b) 2
1 day (e) 6
4
2 days (c)
Event
EOT
LOT
Activity
Duration
EST
EFT
a(1-2)
10
2
3 4 5
1
2 5 5
3
2 5 5
b(1-3)
c (1-5) d(2-5) e(3-5) f(3-4)
2
8 4 6 5
0
0 1 2 2
2
2 3 3 5
(1-3)
(2-4) (3-4) (2-5) (4-5)
12
2 8 15 2
500,000
1,000,000 250,000 100,000 750,000
6,000,000
2,000,000 2,000,000 1,500.000 1,500,000
Total Cost = 15,600,000 Resource Constraint: Release of funds 1st year - 6,900,000 2nd year - 6,800,000 3rd year - 1,900,000
Activity ( i, j )
Duration (Months)
(1 - 2) (1 - 3) (2 - 4) (3 - 4) (2 - 5) (4 - 5)
13 12 2 8 15 2
0 0 13 12 13 20
0 6 24 18 13 26
Measures of Variability Steps involved in calculating the Standard deviation of the duration of critical path: Determine the standard deviation of the duration of each activity on the critical path Determine the standard deviation of the total duration of the critical path. Formula to calculate the standard deviation of each activity is,
CONT..
Variance = 2 Variance = Sum of variances of activity durations on critical path. Simple Example:
Optimistic time(weeks)
Accountant X Accountant Y
Pessimistic time
5 7
Duration 4 4
3 1
Variance for X is 2 = ((5-3)/6)2 = 0.11 Variance for X is 2 = ((7-1)/6)2 = 1 Y is less certain than X, so accept the contract with X
CONT
Z Probability distribution of completing a project on the specified date job D Specified date to complete a job T Mean Standard deviation for critical path duration Simple Problem: If the project has a critical duration of 28 weeks and its standard deviation is 3.07, then what is the probability of completing a project in 20 days. Probability of completing project in 20 days is Z=(20-28)/3.07 Z = -2.6 From cumulative probability distribution table Z(-2.6) = 0.005
CPM MODEL
Focus of CPM analysis is on variations in activity times as a result of changes in resource assignments.
Cost associated with the project is of two components, Direct costs and
Indirect costs.
resources.
Time and Direct Cost of the project are inversely proportional Indirect cost and time are directly proportional
Crashing activity
Crash cost Slope = crash cost per unit time Normal Activity
INDIRECT COSTS
Project Duration
PROCEDURE
Obtain the critical path in the normal network. Determine the project duration and direct cost.
Examine the cost-time slope of activities on the critical path obtained and crash the activity which has the least slope.
Identify the new critical path after crashing, now determine the
project duration and cost.
Repeat steps 2 and 3 till activities on the critical path are crashed.
PROBLEM ON CRASHING
Activity 1-2 1-3 2-4 3-5 2-5 4-6 5-6 6-7 5-7
C
D E F G
27
24 21 20 19 1/2
49,500
52,500 55,200 56,400 57,600
54,000
48,000 42,000 40,000 39,000
1,03,500
1,00,500 97,200 96,400 96,600
COST CONTROLLING
Basic Principle of NCS: Costs are planned, measured, analyzed and controlled in terms of
project activities.
Costs incurred to date Budgeted Costs to date Value of work done to date Cost over-run(under-run) to date Time over-run(under-run) to date
EG 1: If a budgeted cost for the particular activity is Rs.1,000 and it should be completed in 1day. The actual cost incurred is Rs.800 for completing the 2/3rd of work in 1day. What is the cost variance?
Thank You