Group 10 Term Paper
Group 10 Term Paper
DEPARTMENT
OF
INDUSTRIAL AND
MANAGEMENT ENGINEERING
MBA- 671A
Dr Subhas C.Misra
Submitted By
1.Introduction.......................................................................................................................................................................... 5
Risk Identification ................................................................................................................................................................... 5
Risk Q u a n t i f i c a t i o n.................................................................................................................................................................. 5
Risk Response.......................................................................................................................................................................... 5
Risk Cont rol............................................................................................................................................................................. 6
1.1Risk management and construction.................................................................................................................................. 6
1.2The aim of the study......................................................................................................................................................... 6
1.3About the Sydney Opera House ....................................................................................................................................... 6
1.4About the Building........................................................................................................................................................... 7
1.5Design Stage .................................................................................................................................................................. 10
1.6Construction stage.......................................................................................................................................................... 10
2.Risk management strategies at S.O.H ................................................................................................................................ 11
2.1Financial ........................................................................................................................................................................ 11
2.2Political .......................................................................................................................................................................... 11
2.2.1Media and public deception............................................................................................................................................ 11
2.2.2Deceptive cost estimate.................................................................................................................................................. 11
2.2.3Political construction date .............................................................................................................................................. 11
2.2.4Political design changes ................................................................................................................................................. 11
2.3Structural........................................................................................................................................................................ 11
2.3.1The Supporting points .................................................................................................................................................... 11
2.3.2The roof.......................................................................................................................................................................... 12
2.3.3Lack of suitable boundary condition .............................................................................................................................. 12
2.4Technical........................................................................................................................................................................ 12
2.4.1Design errors and omissions........................................................................................................................................... 12
2.4.2Fitness for purpose ......................................................................................................................................................... 12
2.5Construction................................................................................................................................................................... 12
2.6What goes wrong Consequences?.................................................................................................................................. 13
3.Risk identification quantification ....................................................................................................................................... 13
3.2Qualitative risk analysis ................................................................................................................................................. 14
3.2Risk response ................................................................................................................................................................. 15
3.2.2Risk transfer ................................................................................................................................................................... 16
3.2.3Mitigate the risk ............................................................................................................................................................. 16
4.Assessment forms............................................................................................................................................................... 16
5.Lessons learned .................................................................................................................................................................. 20
6.Conclusion ......................................................................................................................................................................... 20
1. Introduction
Risk management is one of the most critical project management practices, to ensure a
project be successfully completed Risk management is thus in direct relation to the
successful project completion. Project management literature describes a detailed and
widely accepted risk management process, which constructed from four iterative phases
known as risk management plan
Risk identification
Risk estimation
Risk response
Planning and execution
Risk Identification
In this stage, we identify and name the risks, there are different sorts of risks and we need
to decide on a project by project basis what to do with each type.
Risk Quantification
Risk need to be quantified in two dimensions. The impact of the risk needs to be assessed.
The probability of the risk occurring needs to be assessed. For simplicity, rate each on a 1
to 4 scale. The larger the number, the larger the impact or probability. By using a matrix,
a priority can be established.
Risk Response
There are four actions you can do about a risk. The strategies are:
Avoid the risk. Do something to remove it. Use another supplier for example.
Deflect the risk. Make someone else responsible. Perhaps contracting out or
insurance against (damage , liability, personnel liability etc)
Mitigate the risk. Take actions to lessen the impact or chance of the risk
occurring. If the risk relates to availability of resources, draw up an agreement and
get sign- off for the resource to be available.
Accept the risk. The risk might be so small the effort to do anything is not
worthwhile or a contingency plan may be developed to deal with possible effects.
Risk Control
The final step is to continually monitor risks to identify any change in the status, or if
they turn into an issue. It is best to hold regular risk reviews to identify actions
outstanding, risk probability and impact, remove risks that have passed, and identify new
risks.
There are nearly 1000 rooms in the Opera House including the five main auditoria. There
is also a Reception Hall, five rehearsal studios, four restaurants, six theatre bars,
extensive foyer and lounge areas, sixty dressing rooms and suites, library, an artists'
lounge and canteen known as the "Green Room", administrative offices and extensive
plant and machinery areas. The building covers about 1.8 hectares (4.5 acres) of its 2.2
hectare (5.5 acre) site. It has about 4.5 hectares (11 acres) of usable floor space. It is
approximately 185 m (611 ft) long and 120m (380 ft) wide at its widest point. The
highest roof vault (above the Concert Hall) is 67m (221 ft) above sea level.
The roofs are made up of 2,194 pre-cast concrete sections. These sections weigh up to
15.5 tones (15 tons) each. They are held together by 350 km (217 miles) of
tensioned steel cable. The roofs weigh 27,230 tones and are covered with exactly
1,056,056 Swedish ceramic tiles arranged in 4,253 pre-cast lids.
The entire building weighs 161,000 tones. It is supported on 580 concrete piers sunk up
to 25 m (82 ft) below sea level. The roofs are supported on 32 concrete columns up to 2.5
m (8 ft) square. The exterior and interior walls, stairs and floors are faced with pink
aggregate granite which was quarried at Tarana in New South Wales. The two woods
used extensively to decorate the interiors are brush box and white birch plywood which
were both cut in northern NSW. There are 6,225 sq m (67,000 sq ft) of glass, made in
France, in the mouths of the roofs and other areas of the building. It is in two layers - one
plain and the other demi-topaz tinted. About 2,000 panes in 700 sizes were installed.
There are 645 km (400 miles) of electrical cable. 120 distribution boards regulate the
power supply, equivalent to the needs of a town of 25,000 people. Twenty-six air-
conditioning plant rooms move more than 28,500 cubic meters (1,000,000 cubic feet) of
air per minute through 19.5 km (12 miles) of ducting.
Fig 2 Sydney opera house (Ref. 6)
In spite all uncertainty, the initial project cost estimate was pit at $7million.The
government would use profits from a series of state run lotteries to pay the project.
The government was worried that the people scrutinizing the design might raise question
about the potential problems that would stall the project they thus quickly mover ahead
and divided the work into three main contracts: the foundation and the building except
the roof, the roof, and the interior and equipment.
6. Construction stage
Many of the world’s best-known construction companies were involved in building
Sydney Opera House including Arups Structural Engineering, Hornibrook and Rider
Hunt, the construction work of S.O.H was divided into three distinct stages as follows
(Ref. 19)
Stage I
Sub structure, concrete structure from the foundation up to the auditoria seating levels
excluding any finishes.
Stage II
Superstructure or shells, concrete roof vaults or major and minor halls an restaurants,
including the claddings.
Stage III
Everything not included in stages I and II, stage towers, all interior finishes, exterior
paving and cladding, glass walls, all electrical and mechanical services.
After he was elected premier of New South Wales in 1965, Askin attempted to force
Utzon reduce costs by withholding payments. In 1966 Utzon resigned and returned to his
native Denmark. He never even returned to see his masterpiece completed.
The construction of the Sydney Opera House was now handed over to a group or
Australian architects. Fortunately, the exterior had already been completed by then so that
the impact of the altered design on the overall structure was minimal. The project was
finally completed in 1973 after a construction period of 14 years and an expenditure of
over $A100 million, almost 15 times the estimated budget.
2. Risk management strategies at S.O.H
1. Financial
Despite of all cost escalation, taxpayer had little to pay .Virtually all the costs were
covered by the proceeds of State Lotteries. The continued need to subside the
runningcosts of the opera house were financed by the continuation of the Lottery State.
The first estimate for the Sydney Opera House was $7.2 million in Australian dollars.
Once started, however, costs kept rising and just to complete the building cost $102
million.
2. Political
Political risks are often occur in government project as they often hide information
affecting the community's support, which in turn affect the effectiveness of the feasibility
study. S.O.H we mostly severely effect by political decisions
3. Structural
4. Technical
Utzon, ware of possible technical problems since his design required advanced technology
not yet available, requested additional time to tackle those challenges Utzon faced the task
of converting the concept into a design form which a structure could be built, but he had
no prior experience in the design and construction of such a large building. Because of this
lack of plans, detailed design drawings, and estimates of materials, little existed from
which cost could be determined.
2.5 Construction
Engineers who revised the concept noted that the roof shells were much larger and wider
than any shells seen so far. Further, because they stuck up so height, they would act like
sails in strong winds blowing up the harbour. Thus, the roof would have to be carefully
designed and constructed to resist such wind pressure.
The construction was estimated to take about five years at a cost of a $7 million. Ignoring
his request, the government pressured Utzon into starting construction in 1959, two years
ahead of the architect's proposed schedule.
The lack of preparation soon backfired. After the completion of the grand podium
with an enormous, 86 meter (282ft) wide stair, several years were spent reworking the
design of the roof.
Three tower cranes imported from France for this job costing $100,000 each and it
was the first building constructed in Australia using tower cranes.
Unfortunately the roof shells were too heavy for the supporting columns that were
already built, so these were demolished and rebuilt.
Engineer
Contractor
Contractor
2. Risk response
1. Risk Avoidance
As discussed most of the risk could be avoided by only
Completed design .
Estimating at a very detailed level.
Not selecting untested design .
Using local Architecture office will reduce many and more communication and
experienced architecture designer
2. Risk transfer
Using a fixed price contract will transfer construction risk to the contactor.
Obtaining Insurance to cover costly risks.
4. Assessment forms
Following a three assessment forms for 3 of the significant risks
Performa for a Qualitative Risk Assessment (sheet 1)
Consequence Medium
Construction stage
Statement of risk:
Cost and schedule overrun
Incomplete design
Consequence High
Design stage
Construction
stage
Statement of risk:
major source of
complainttime
consuming
(the factor that could cause it to occur)
Statement of risk:
Insufficient working drawing details
Late and in adequate information
Major costly errors.
(the factor that could cause it to occur)
Lack of management
Interest conflict between project participation
Incomplete design
6. Conclusion
Study clearly identifies the great importance of risk management on construction projects,
negligence will lead to an expensive cost effecting the project successes.
A risk analysis project shows a large number qualitatively ranked as 1 , those risks have a
high probability of occurrence and height consequence shared between the client 42% ,
the contractor 36% and the engineer 21% .
This indicates that it was a very risky project nevertheless risks were either downplayed
or ignored , and not much was done to keep them under control, the project management
strategies was only focused on keeping the project going no matter how it is going .
Finally although the opera house put Sydney on the world map, both architecturally and
culturally but from project management perspective it was a spectacular failure as a
consequence of ignoring risk management.
References
21 | P a g e