Construction of A House: M. Usman Butt 2011-MS-CH-56 Nadeem Hussain 2011-MS-CH-55 Kashif Hafeez 2011-MS-CH-33
Construction of A House: M. Usman Butt 2011-MS-CH-56 Nadeem Hussain 2011-MS-CH-55 Kashif Hafeez 2011-MS-CH-33
M. Usman Butt
2011-MS-CH-56
Nadeem Hussain
2011-MS-CH-55
Kashif Hafeez
2011-MS-CH-33
Introduction
Predecessor
Successor
Successor
Predecessor
Successor
Relationship
B
Successor
A
Predecessor
Lag B
Successor
FINISH TO FINISH- FF
B
Successor
A
Predecessor
Lag
B
Successor
START TO FINISH- SF
Relationship in which the finish of successor activity
depends on the start of its predecessor activity
A
Predecessor
B
Successor
A
Predecessor
Lag
B
Successor
Project Overview
Project ID Construction of a House
Work Days/week 6
Phases
(Code 1) Description
FEAS Feasibility
PROC Procurement
CONS Construction
DESG Design
FNSH Finishes
HAND Handover
Floors
(Code 3) Description
GF Ground Floor
FF First Floor
EX External Works
WBS
1. Construction of House
2. Feasibility Stage
3. Architectural and Structural Design Stage
4. Procurement / Tendering Stage
5. Construction / Execution Stage
6. Mobilization and Site Clearance
7. Earth Works
8. Structural Works
9. Foundations
10. Ground Floor
11. First Floor
12. External Work
13. MEP Works
14. Ground Floor
15. First Floor
16. External Works
17. Finishing Works
18. Ground Floor
19. First Floor
20. External Works
21. Demobilization and Project Handover
ACTIVITIES
1) Project Start
2) Determination of the need of facility
3) Cost / Benefit Analysis
4) Environment Impact Analysis
5) Feasibility report preparation
6) Analysis of feasibility report
7) Yes/ No Decision
8) Architectural Layout
9) Structural Layout
10)Architectural Design
11) Structural Design
12)MEP Design
13)Interior Design
14)Submission of Drawings
15)Pre-qualification of contractors
16)Selection of pre-qualified contractors
17)Tender Floating
18)Tender negotiations
19)Award of Contract
20)Mobilization
21)Site Clearance
22)Site Layout and Preparation
23)Bulk Excavation
24)Structural Excavation
25)Foundations
26)Columns – GF
27)Beams / Slabs – GF
28)Block Masonry – GF
29)Plumbing & Electrical Rough - in -GF
30)Plaster – GF
31)Doors / Windows – GF
32)Floor Finishing – GF
33)Plumbing Fixtures – GF
34)Electrical Finishes – GF
35)Painting – GF
36)Columns – FF
37)Beams / Slabs – FF
38)Block Masonry - FF
39)Plumbing & Electrical Rough - in - FF
40)Plaster – FF
41)Doors / Windows – FF
42)Floor Finishing – FF
43)Plumbing Fixtures – FF
44)Electrical Finishes – FF
45)Painting – FF
46)Underground Water tank
47)External Plaster
48)External Paint
49)Punch List
50)Project handover
CONSTRAINTS
• 1340 Finish on before 08 May 2013