Lecture Seven
Lecture Seven
Lecture Seven
CHAPTER SEVEN
CONTRACT
EYOB E. (MSc.)
Principles of Contract
Contract is a written agreement between two
3
4
5
6
Legal definition of contract: According to the
civil code of Ethiopia, art. 1675:
A contract is an agreement whereby two or
more persons as between themselves create,
vary or extinguish obligations of a proprietary
nature.
In other words, a contract is
an agreement that affects the legal
relationship between two or more parties.
7
Elements of a contract
Contract requires four basic elements
◦ – Mutual agreement
• Offer & acceptance
◦ – Legal objectives
◦ – Valid consideration
◦ – Legal capacity of the parties
Mutual agreement
◦ Must have evidence that there was a “meeting of th
e minds”
• Offer ‐clear & unambiguous
• Acceptance ‐clearly accepting deal offered,
indication of consent,
8
legal objective
The thing being contracted for must be legal
Most construction contracts are legal,
9
legal capacity
– In simplest form, parties must be
◦ Of age
◦ Mentally competent
– In construction environment, parties must
have
◦ Legal authority to issue and execute contracts
◦ May have to be properly licensed to have
legal capacity
10
Valid consideration
In exchange for the offer of performance, the
11
Content of construction contract
◦ Identity of parties
◦ Promises and responsibilities
◦ Scope of the work
◦ Price and payment terms
◦ Project execution plans
12
Purpose of construction contract
Describe the scope of work
Establish timeframe
Establish cost and payment provisions
Set forth obligations and relationships
Manage multiple risks
Establish control mechanisms
Minimize disputes
Improve economic return on investment
13
Types of Construction Contracts
Contracts for the execution of civil engineering
works are of following type:
a) Lump sum contract
b) Unit rate contract
c) Lump sum and schedule contract
d) Cost plus fixed fee contract
e) Cost plus percentage of cost contract
14
◦ The contractor is fully responsible to quantify the
volume of works based on the given specifications
and drawings. (must be careful not to overestimate
or underestimate)
◦ Lump sum contract are typically used for
buildings.
◦ Difficult to make adjustments.
◦ is more suitable for works for which contractors
have prior construction experience
◦ Not suitable for unpredictable work conditions
15
B. Unit Rate Contract
◦ Also called Item rate contract
◦ Fixed Unit prices are submitted for each item of
work.
◦ Used for works whose quantities can be estimated
in advance.
◦ Changes in drawings and quantities can be made as
required by the owner within the agreed limits.
◦ Items whose actual quantity varies from the
estimated quantity by more than 15 or 20%, either a
bove or below, are sometimes subject to
renegotiation of the unit price.
16
C. Lump sum and schedule rate contract
◦ Combines the features of the Lump sum and
schedule contracts
◦ schedule rate contract is based on only agreed unit
prices of the intended work items with out
estimated quantities of the works.
◦ Additional items are amounted as per the attache
d item rate.
17
D. Cost plus
◦ Used when it is impossible to predict their costs
during the negotiation, bid,
and award process.
Factors:
◦ unpredictable and extreme weather conditions,
transportation problems, combat or war, or contr
acts where the amount of effort that will be requir
ed depends on different factors.
◦ Cost plus contracts take many forms: the most
common cost plus fixed fee and cost plus a
percentage.
18
D.1. Cost plus Fixed Fee Contact
◦ Is desirable when the scope and nature of the wor
k can at least be broadly defined.
◦ The amount of fee is determined as a lump sum
from a consideration of the scope of work, its
approximate cost, nature of work, estimated time
of construction, manpower and equipment
requirements etc.
◦ The contractor will not be tempted to increase the
cost to get more revenue.
D.2. Cost plus Percentage of Cost Contract
◦ The tendency of the contractor to increase the cost
of work to earn more profit by way of percentage o
f enhanced actual cost is the major demerit of this
contract type.
19
Contract Documents
The main contract documents are:
◦ Invitation to tender,
◦ Instruction to tender,
◦ Form of tender ,
◦ The Agreement,
◦ Condition of contract( General and Particular),
◦ Specification (General and Particular),
◦ Bill of Quantities,
◦ Drawings,
◦ Addenda and
◦ Appendix to Tender.
20
In the Ethiopian Construction Industry the
following
standard conditions of contracts are commo
nly used:
FIDIC (1987) –Condition of Contract
2006 -Public Procurement Agency(PPA),
Development (MoWUD)
1987 –Building and Transport Construction
and Design Authority (BaTCoDA)
21
FIDIC Conditions of Contracts
FIDIC has evolved into a leading body for
development of model standard forms of
contract for use in the international
construction industry.
FIDIC conditions of contracts have two
parts:
◦ General Condition of Contract
◦ Particular Conditions of Contract
22
FIDIC Conditions of Contracts
◦ 1957 –RED BOOK
for civil engineering works
◦ 1963 – YELLOW BOOK
For mechanical and Electrical works
◦ 1987 –OLD FIDIC
Comprises the RED and YELLOW Books.
◦ 1995 –ORAGE BOOK
For Design Build and Turnkey Projects
◦ 1999 –GREEN BOOK
For short period projects ( 6 months)
Low contract value ($ 500,000)
◦ 1999 –SILVER BOOK
For turnkey for power plants, factories and facilities
◦ MBD –Harmonized Edition
2004, World Bank tried to harmonize the FIDIC
conditions to suite its procurement needs. 23
Quiz II
What is the difference between lump sum
contract and Unit rate contract? If the
estimated quantity in the contract BOQ is
found to be less than the actual quantity
which needs to be excavated on site, which
contract type (Lump sum or Unit rate) would
be advantageous for the contractor? Briefly
explain.
24
Contract Management :
25
Contract administration
Identifying contractual responsibilities of
Stakeholders.
◦ Reviewing the Terms of Contract Documents
◦ Preparing and Monitoring Responsibility Summary
Sheets.
Determining and understanding the
construction components of the project.
◦ Reviewing the Contract Drawings and Technical
Specifications
◦ Prepare Construction Methods and Over all
Sequences Sheets
◦ Review submitted (Integrated) Schedules and
Breakdowns for operations such as Organizational
Breakdowns, Resources Breakdowns & Schedules
and Time Schedules.
26
Report Project Status daily and / or and
Completions.
Certify qualities of materials, shop drawings,
samples, and works.
Measure Works, Record Site Potentials and
27
Contract Closing
Closing of Contract looks into issues related
to Maintenance Period and Remedial works,
Dealing with Left Over Claims and Disputes, if
any, Closing of Accounts and Completion
Certificates.
28
Claim and dispute management
29
Dispute in simple terms is a difference in a
line of thought.
Claim is mostly concerned with entitlements
Claim
administration
process
31
Major causes of claims
poor or unclear tender and/or contract
documents,
poor or inadequate administration of
responsibilities by stakeholders,
Unforeseen or uncertain situations during
execution
Changed conditions, or variations
Additional works, and
Delay in approving payment and time
extension.
32
Alternative dispute resolution mechanisms
Preventive dispute resolution system
◦ ALLIANCING: is generally a tender arrangement
where all the principal tenderers organize into
groups with common aims, prior to submitting the
tender.
◦ DISPUTE REVIEW BOARDS (DRB): a representative
from the owner, one from the contractor and a
third, selected by these two representatives. The
third member chairs the board.
The members usually have experience in the kind of
construction work being undertaken and are also
familiar and experienced in dispute resolution.
It is important that all the board members are
independent of any of the contracting parties,
although they are selected and paid by them.
33
Amicable Dispute Resolution System: used
to administer the claim in a less formal, simple
procedure, more flexible, and less adversarial
mode so as to avoid the time and cost
implication of claim processing.
Amicable Dispute Resolution System includes
Negotiation, Mediation, Conciliation and use of Mini
‐Trials
34
MEDIATION
a process in which the parties to a dispute,
with the assistance of a neutral third party
(the mediator), identify the disputed issues
develop options consider alternatives
and try to reach an agreement.
The mediator has no advisory or
determinative role in regard to the content
of the dispute or the outcome of its
resolution but may advise on or determine
the process of mediation whereby resolution
is attempted. 35
CONCILIATION
Conciliation is in many respects similar to
mediation. The conciliator is still an
independent third party but the difference is
that the conciliator may make more specific
suggestions to resolve the dispute. The
conciliator may also have a more powerful
role in the various meetings.
36
Judgmental Dispute Resolution System
◦ the formal common law system is applicable to
bring the closure of claim processing.
◦ Includes Arbitration and Litigation
Litigation:
◦ means going to court and being judged by a public
appointed jury. This process is quite expensive as
the public judiciary system is less efficient and time
taking.
37
Arbitration
after hearing both sides in a judicial manner, the
decision is made by a person or persons other than
a court .
ARBITRATOR
He is chosen and paid by the disputants
He does not sit in public
He acts in accordance with privately chosen procedure
as long as he doesn’t violate public Policy
When the law allows he is set up to the exclusion of
the state courts
His authority and powers are only whatever he is give
n by the disputant’s agreement
38
Advantages of arbitration
◦ The Arbitrator is an expert in the field
◦ The procedures are open to the parties
◦ Hearing are private
◦ The decision is binding
39
THANK YOU!
40