Carmel Heights MIS Report 10th Jan
Carmel Heights MIS Report 10th Jan
Carmel Heights MIS Report 10th Jan
INCOR,BANGALORE
Monthly MIS report
11thJanuary 2022
1.0 INTRODUCTION
Salient information related to the development
• UPVC Door & Windows: M/s. Sohom Fenster ( Tower A ) • Shaft ACP Trap Doors : M/s. Prisicca and Gabriella
• UPVC Door & Windows: M/s. Eco Care Prime (Tower A & C)
• Wooden Floor – M/s. Galaxy Designs
• Door Hardware's : M/s. Spray Systems
• STP : M/s. Crystal Drops
• Fire & Non Fire Doors : M/s. Crystal Engineering
• BESCOM & CEIG : M/s. Tesla Electric & Engineering
Incor Carmel Heights Tower A Finishes
Cumulative
Achieved Planned
Achieved Achieved
Sl. Start Date Completion up to for
Activity Contractor up to as on date Remarks
No R0 Date R2 December January
November 11-01-2023
2022 2023
2022
Bore packing,
waterproofing & 17 floors waterproofing completed.
1 screed
JMC 20-07-2022 30-01-2023 16 1 1 0 18th floor works is on hold due to interior
designs
(1st to 18th floor)
Plumbing 1st Fix Prem Upto 17th floor completed. 18th floor works are
2 (1st floor to 18th floor) Plumbing
17-06-2022 04-02-2023 16 1 1 0
on hold due to interior designs
12 Primer coat JMC 09-11-2022 05-03-2023 0 0 8 0 3 units completed. Further works in progress
( 1st to 18th floor ) Due to 18th floor works date is going upto March 2023.
13 Electrical Wiring SB 09-11-2022 03-03-2023 0 10 8 5 15 floors completed. 16th floor works in progress.
( 1st to 18th Floor ) Electrotech Due to 18th floor works date is going upto March 2023.
Only one unit completed. A 203.
Internal Painting 1st
14 JMC 12-11-2022 07-03-2023 0 0 9 0 Due to 18th floor works date is going upto March 2023.
coat ( 1st to 18th floor )
Incor Carmel Heights Tower A Finishes
Cumulative
Achieved Planned Achieved
Achieved
Start Date Completion up to for as on date
Sl. No Activity Contractor up to Remarks
R1 Date R2 December January 11-01-
November
2022 2023 2023
2022
Works are delaying due to painting work front
Electrical Switch &
constrain.
15 plate fixing(1st to 18th SB Electric 4-11-2022 07-03-2023 - 2 9 0
Floor) Due to 18th floor works date is going upto
March 2023.
Toilet False Ceiling
16 Board fix (1st to 18th JMC 17-11-2022 11-03-2023 - 0 8 0 Due to 18th floor works date is going upto
floor) March 2023.
Acid wash & grout (1st Due to 18th floor works date is going upto
17 JMC 18-11-2022 13-03-2023 - 0 8 0
floor to 18th floor) March 2023.
CP & Sanitary Fix (1st Prem Due to 18th floor works date is going upto
18 20-11-2022 15-03-2023 - 0 8 0
to 18th floor) Plumbing March 2023.
De snags( 1st to 18th Due to 18th floor works date is going upto
19 All 20-11-2022 16-03-2023 - 0 9 0
floor ) March 2023.
Internal paint Final Due to 18th floor works date is going upto
20 23-11-2022 18-03-2023 - 0 9 0
Coat( 1st to 18th floor ) JMC March 2023.
Wooden Flooring ( 1st Galaxy Due to 18th floor works date is going upto
21 26-11-2022 20-03-2023 - 0 9 0
to 18th Floor ) Designs March 2023.
Hand Over( 1st to 18th Due to 18th floor works date is going upto
22 floor ) All 27-11-2022 23-03-2023 - 0 9 0 March 2023.
Incor Carmel Heights Tower C Finishes
Cumulative Achieved Achieved
Planned for
Start Date Completion Achieved up to as on date
Sl. No Activity Contractor January Remarks
R0 Date R2 up to December 11-01-
2023
November 2022 2023
2022
Bore packing,
waterproofing & 14 floors completed. 1st & 16th above floor
1 screed JMC 04-07-2022 21-01-2023 11 3 4 0 works in progress.
(1st to 18th floor)
Plumbing 1st Fix Prem 01-08-2022 29-01-2023 13 floors completed. 14th & above floor works
2 (1st floor to 18th floor) Plumbing
10 2 6 1
in progress.
Internal Main Flooring 10 floors completed. 11th & 12th floor works in
5 & Skirting 1st to 18th JMC 05-08-2022 19-02-2023 6 2 5 2 progress
floor
MS Hand Railing 14 floors completed. North & West elevation
6 Balcony JMC 31-10-2022 25-01-2023 5 7 6 1 completed. East & south side works are in
(1st to 18th Floor) progress.
Incor Carmel Heights Tower C Finishes
Cumulative
Achieved Planned
Achieved Achieved
Start Date Completion up to for
Sl. No Activity Contractor up to as on date Remarks
R1 Date R2 December January
November 11-01-2023
2022 2023
2022
IPS Flooring 14 floors completed. 15th floor works in
7
(1st to 18th Floor)
JMC 16-08-2022 25-01-2023 11 2 5 1 progress.
Boxing & False Ceiling
14 floors completed. 15th and above floor
8 Channel fix JMC 15-11-2022 30-01-2023 3 8 7 3 works are in progress.
(1st to 18th floor)
Electrical Wiring SB
13 ( 1st to 18th Floor ) Electrotech 24-11-2022 15-03-2023 0 0 6 0 807 & 1607 completed.
De snags
19 All 15-12-2022 29-03-2023 - - 5 0
( 1st to 18th floor )
Revised GFC’s are required to commence further. Still, Basement slab works are completed with
1 Tower 2
Manohar consultant details.
2 Clubhouse Revised GFC’s are required to commence further.
3 Tower 1 18th Floor Details
Painting works
Tower A – West Elevation Tower A - Lift Works Tower C – West Elevation
Tower 2 – Basement 1 floor column works completed & Awaiting for the GFC drawings
THANK