Chapter 8 Pert and CPM
Chapter 8 Pert and CPM
DECISIONS
Lecture 8
Project Scheduling PERT and CPM
Course leader : Dr. B Dayal
Mobile No.: 00251941962113
Email ID: [email protected]
Chapter: 8
Project Scheduling PERT and CPM
Canonical forms
Solved example
Duality: Introduction
Formulation of dual problems
Solved examples
Economic interpretation of duality
INTRODUCTION
THE GROWING COMPLEXITIES OF TODAY’S PROJECTS
HAVE DEMANDED MORE SYSTEMATIC AND MORE
EFFECTIVE PLANNING TECHNIQUES WITH THE
OBJECTIVE OF OPTIMISING THE EFFICIENCY OF
EXECUTING THE PROJECT.
EFFICIENCY HERE IMPLIES EFFECTING THE UTMOST
REDUCTION IN THE TIME REQUIRED TO COMPLETE THE
PROJECT WHILE ACCOUNTING FOR THE ECONOMIC
FEASIBILITY OF USING AVAILABLE RESOURCES.
THERE ARE TWO ANALYTICAL TECHNIQUES FOR
PLANNING, SCHEDULING AND CONTROLLING THE
PROJECT:
PROJECT EVALUATION AND REVIEW TECHNIQUE
(PERT).
CRITICAL PATH METHOD (CPM).
INTRODUCTION
DEFINITION OF PERT
PERT IS AN EVENT ORIENTED NETWORK
GIVING EMPHASIS ON IMPORTANT
STAGES OF COMPLETION OF TASK.
DEFINITION OF CPM
CPM IS A DETERMINISTIC NETWORK TO
ESTABLISH A TRADE-OFF FOR OPTIMUM
BALANCING BETWEEN SCHEDULED TIME
AND COST OF THE PROJECT.
PERT CPM
PLANNING SCHEDULING & CONTROLLING
INTRODUCTION
PERT
TOTAL PROJECT DURATION IS REGARDED AS A
RANDOM VARIABLE AND THEREFORE ASSOCIATED
PROBABILITIES ARE CALCULATED SO AS TO
CHARACTERISE IT.
IT HAD TO COPE WITH ASSOCIATED UNCERTAINTIES
IT IS AN EVENT ORIENTED NETWORK.
NORMALLY USED FOR PROJECTS INVOLVING NON-
REPITITIVE ACTIVITIES. IN WHICH TIME ESTIMATES ARE
CERTAIN.
HELPS IN PIPELINING CRITICAL AREAS IN A PROJECT.
CPM
BASICALLY DETERMINISTIC NETWORK.
SUITABLE FOR ESTABLISHING A TRADE-OFF FOR
OPTIMUM BALANCING BETWEEN SCHEDULE TIME AND
COST OF THE PROJECT.
NORMALLY USED FOR PROJECTS INVOLVING
ACTIVITIES OF REPITITIVE NATURE.
PROJECT SCHEDULING BY
PERT – CPM (CONTD)
PROJECT CONTROL
REFERS TO RE-EVALUATING ACTUAL
PROGRESS AGAINST THE PLAN. IF
SIGNIFICANT DIFFERENCES ARE
OBSERVED THEN RE-SCHEDULING MUST
BE DONE TO UPDATE AND REVISE THE
UNCOMPLETED PART OF THE PROJECT.
NETWORK COMPONENTS
EVENTS
AN EVENT REPRESENTS A POINT IN TIME THAT
SIGNIFIES THE COMPLETION OF SOME ACTIVITY AND
THE BEGINNING OF NEW ONE.
COMMONLY REPRESENTED BY CIRCLES (NODES) IN THE
NETWORK DIAGRAM.
THEY DO NOT CONSUME TIME AND RESOURCES.
IDENTIFIED BY NUMBERS.
ACTIVITIES
REPRESENT PROJECT OPERATIONS OR TASKS TO BE
CONDUCTED.
REPRESENTED BY AN ARROW.
THEY CONSUME TIME AND RESOURCES.
IDENTIFIED BY THE NUMBERS OF THEIR STARTING
EVENT AND ENDING EVENT.
NORMALLY ASSIGNED ALPHABETS.
NETWORK COMPONENTS
ACTIVITY
1 2
A
STARTING EVENT COMPLETION EVENT
3 4
2
NETWORK CONSTRUCTION
Rules for constructing network diagram
From the arrow diagram, we infer that activity A is the first job. Job B
and C start only after A is over. A is called the predecessor of B and C
and B and C are called as successors of A.
NETWORK CONSTRUCTION
Dummy activities:
There is a need for dummy activity when the project contains groups of
two or more jobs which have common concurrent predecessors. The
time and resources consumed by dummy activity is zero.
ES1 = 0, ES2 = 20, ES3 = 23, ES4 = 39, ES5 = 39, ES6 = 57, ES7 = 67
The activity table is as given below:
Activity (I, j) Duration Dij Earliest latest Total float TFij Free floats FFij
Start ESi Completion Start LSij Completion
ECij LCj
(1, 2) 20 0 20 18 38 18 0
(1, 3) 23 0 23 0 23 0* 0
(1, 4) 8 0 8 31 39 31 31
(2, 5) 19 20 39 38 57 18 0
(3, 4) 16 23 39 23 39 0* 0
(3, 7) 24 23 47 43 67 20 20
(4, 5) 0 39 39 57 57 10 0
(4, 6) 18 39 57 39 57 0* 0
(5, 6) 0 39 39 57 57 18 18
(5, 7) 4 39 43 63 67 24 24
SOLVED PROBLEM 3
Solution:
The critical path 1 – 3 – 4 – 6 – 7
The duration to complete the project = 67 days
PROJECT MANAGEMENT - PERT
Probability and cost consideration in project
scheduling.
Let A = The optimistic time, which will be required if the
execution of the project goes extremely well.
B = The passimistic time, which will be required if everything
goes bad.
M = The most likely time, if execution is normal.
Then, expected duration of each activity D = (A+B +4M)/6
Variance V = {(B – A)/6}2
SOLVED PROBLEM 4
A project is represented by the network shown below and
has the following data:
TASK A B C D E F G H I
OPTIMISTIC TIME 5 18 26 16 15 6 7 7 3
PESSIMISTIC TIME 10 22 40 20 25 12 12 9 5
MOST LIKELY TIME 8 20 33 18 20 9 10 8 4
3 6 7
F I
B H
A E
1 2 D 5
G
C
4
EXAMPLE 4 (CONTD)
Determine the following:
Expected task time and their variance.
Earliest and latest expected times to reach each
event.
The critical path.
The probability of an event occurring at the
proposed completion data if the original contract
time of completing the project is 41.5 weeks.
The duration of the project that will have 95%
chances of being completed.
EXAMPLE 4 (CONTD)
Determine the following:
Expected task time and their variance.
Earliest and latest expected times to reach each
event.
The critical path.
The probability of an event occurring at the
proposed completion data if the original contract
time of completing the project is 41.5 weeks.
The duration of the project that will have 95%
chances of being completed.
EXAMPLE 4 (CONTD)
Solution:
Using the formula we can calculate expected activity times and variances
in the following table:
Duration D = (A +B + 4M) / 6
Variance V = [(B – A) / 6]2
Durations and variances for each activity
Activity a b m D V
1 – 2 (A) 5 10 8 7.833 0.694
1 – 3 (B) 18 22 20 20.00 0.444
1 – 4 (C) 26 40 33 33.00 5.444
2 – 5 (D) 16 20 18 18.00 0.444
2 – 6 (E) 15 25 20 20.00 2.777
3 – 6 (F) 6 12 9 9.00 1.000
4 – 7 (G) 7 12 10 9.555 0.694
5 – 7 (H) 7 9 8 8.00 0.111
6 – 7 (I) 3 5 4 4.00 0.111
Forward pass:
E1 = 0; E2 = 7.833; E3 = 20; E4 = 33; E5 = 25.833; E6 = 29; E7 = 42.555
EXAMPLE 4 (CONTD)
Backward pass:
L7 = 42.555; L6 = 38.555; L5 = 34.555; L4 = 33; L3 = 29.555; L2 =
16.555; L1 = 0
• The critical path is shown with thick line in the figure. The critical
path is 1 – 4 – 7 and the completion time is 42.555 weeks.
• The last event will occur only after 42.555 weeks. For this we
require only the duration of critical activities.
Expected length of critical path = 33 + 9.555 = 42.555 weeks
Variance of critical path length = 6.138
EXAMPLE 4 (CONTD)