Lecture#1 Guide Bank
Lecture#1 Guide Bank
Stream b
baank Protection
nk
Guide Banks
By: Melkamu T.
2.1 General
• Guide banks
• Groynes or spurs
• Pitching of banks and provision of launching aprons
• rip rap, or retaining structures
• back filling or reshaping the bank
• Checkdams/drop structures
• bioengineered solutions
• Applying erosion controls on the catchment
2.2 Types of Stream Bank protection works
Washing away of soil particles from the bank by a strong current – due to
erosion
Undermining of the toe of the bank by eddies, followed by a collapse of
overhanging material deprived of support – due to erosion
2.2 Types of Stream Bank protection works
This is because if the river channel is wide, the length of the guide banks
should ensure the safety of the approach embankments against the worst
embayment (cutting-off and meandering of channel).
2.2.1 Guide banks : Design principles
2.2.1 Guide banks : Design principles
Greater the radius, flatter the curve and lesser the probability of
formation of intense eddies.
on the downstream, the rivers fans out so as to attain its normal width
the d/s portion should ensure the safety of approach embankments and
prevents the river from attacking them.
This is possible by providing short guide bund with sharp curved head.
A radius equal to half the radius (usually 0.3 to 0.5R1) at the u/s side
may be adopted and sweep angle of 45o to 60o may be provided.
2.2.1 Guide banks : Design principles
Side slopes generally kept as 2H:1V but may vary from 1.5H:1V
to 3H:1V depending upon the construction material and the
height of the bund.
The size and weight of stone for pitching can be determined from graph
(see graph).
For average velocities up to 2 m/sec, burnt clay brick on edge can be used
as pitching material.
For an average velocity up to 3.5 m/sec, pitching of stone weighing from
40 to 70 kg (0.3 to 0.4 m in diameter) and
for higher velocities, cement concrete blocks of depth equal to the
thickness of pitching can be used.
2.2.1 Guide banks : Design principles
The rear side of the shank portion is not pitched but is generally coated
with 0.3 to 0.6 m earth for encouraging vegetation growth or turfing of
the slope is normally found to be adequate.
The thickness of the pitching on the river side may be calculated by:
t = 0.06Q1/3
Otherwise, scour will occur at the toe with subsequent undermining and collapse
of the stone pitching.
The required size of stone for the apron can be obtained from the curves. In case
of non-availability of required size of stones, cement concrete blocks may be
used.
The apron is generally laid in a width equal to 1.5 times the depth of the scour
below the original bed
2.2.1 Guide banks : Design principles
The total scour below HFL is taken as xR, where R is the Lacey’s normal scoured
depth given by:
R = 0.47(Q/f)1/3
The depth of scour below the original river bed, D is then found by:
Generally, the slope of the launched apron for calculation of the quantity
can be taken as 2:1 for loose boulders or stones, it may be taken as 1:5:1
for concrete blocks.
The thickness of the launched apron is 1.25t (normally 25 to 50% more),
where t is the thickness of stone pitching.
The volume of stone required in the launching apron per meter length is
estimated as:
Vs = (22+12)x D x (1.25t) = 2.8tD
If the width of the launched apron is 1.5D, then the thickness of the
launched apron is given as:
Solution:
The water way between two guide bands,
The Lacey’s regime water way, P = clear water way
= 4.75Q
= 4.75 6000 = 368m
Allowing 20% extra for piers, etc., the net spacing between the two
guide bunds at the site, L = 1.2x368 = 440m
The d/s end of the bund may be curved to make an angle of 60o with
R2 = R1/2 = 194/2 = 87m.
To be more safe and make an allowance for future settlements, etc., let
us make top level = 106m
Therefore, D = 1.25x10.36 -4 = 9m