Lecture 7 Engineering Economics Present Worth Analysis
Lecture 7 Engineering Economics Present Worth Analysis
21S3101
Engineering Management
Del Institute of Technology
SUMMARY OF DISCRETE COMPOUNDING INTEREST FACTORS
21S3101
Engineering Economics
21S3101
Engineering Economics
A A
P F
Middle of Middle of
Year 0 Year 1 End of Year 1 Year 2 End of Year 2
Jan 1 Jun 30 Dec 31 Jan 1 Jun 30 Dec 31
A A
P F 21S3101
Engineering Economics
Sunk costs
Sunk cost should be disregarded. Only the current and future differences
between alternatives should be considered.
Borrowed money viewpoint
Distinguished between two aspects of money : financing and investment.
Income taxes
Income taxes, like inflation and deflation, must be considered to find the
real payoff of a project.
21S3101
Engineering Economics
Situation Criterion
Neither input nor Maximize
output fixed (output - input)
For fixed input Maximize output
21S3101
Engineering Economics
Situation Criterion
Neither input nor Typical, general case Maximize (present worth
output is fixed of benefits minus present
worth of costs), that is,
maximize net present
worth
21S3101
Engineering Economics
Example 1 :
A firm is considering which of two mechanical devices to install to reduce
costs in particular situation. Both devices cost $1000 and have useful lives of
5 years and no salvage value. Device A can be expected to result in $300
savings annually. Device B will provide cost saving of $400 the first year but
will decline $50 annually, making the second year savings $350, the third
year savings $300 and so forth. With interest at 7% which device should the
firm purchase? 21S3101
Engineering Economics
21S3101
Engineering Economics
Example 2 :
A purchasing agent is considering the purchase of some new equipment for the
mailroom. Two different manufacturers have provided quotations. An analysis of
the quotations indicates the following :
21S3101
Engineering Economics
• The criterion is called the net present worth criterion and written simply
as NPW:
• The field of engineering economy and this text often use Present Worth
(PW), Present Value (PV), Net Present Worth (NPW), and Net Present
Value (NPV) as synonyms. 21S3101
Engineering Economics
Take a look at the next slides on how the assumptions are used
in solving the problem with LCM approach!
21S3101
Engineering Economics
Example :
A purchasing agent is considering the purchase of some new equipment
for the mailroom. Two different manufactures have provided quotations.
An analysis of the quotations indicates the following :
As Figure shows, it is not necessary for the analysis period to equal the useful life of
an alternative or some multiple of the useful life. To properly reflect the situation at
the end of the analysis period, an estimate is required of the market value of the
equipment at that time.
21S3101
The calculations might be easier if everything came out
Engineering Economics
even, but this is not essential.
04/01/2023 Wesly Mailander Siagian 23
Useful Lives Different from the Analysis Period
Example :
A diesel manufacturer is considering the two alternative production
machines with specific data are as follows :
Alternative 1 Alternative 2
Initial cost $50,000 $75,000
Estimated salvage value at end of useful life $10,000 $12,000
Useful life of equipment, in years 7 13
The manufacturer uses an interest rate of 8% and wants to use the PW method to
compare these alternatives over an analysis period of 10 years.
Estimated market value end of 10-year analysis period for alternative 1 is $20,000
and alternative 2 $15,000.
21S3101
Engineering Economics
21S3101
Engineering Economics
21S3101
Engineering Economics
Solution :
To compute the capitalized cost, it is necessary to first compute an end-of-
period disbursement A that is equivalent to $8 million every 70 years.
21S3101
Engineering Economics
Solution :
A = P (A/P, i, n)
= $ 8,000,000 (A/P, 7%, 70)
= $ 8,000,000 (0.0706)
= $ 565,000
$ 565,000
𝐶𝑎𝑝𝑖𝑡𝑎𝑙𝑖𝑧𝑒𝑑 𝑐𝑜𝑠𝑡 𝑃 =
0.07
= $ 8,071,000 21S3101
Engineering Economics