Road Construction Methods
Road Construction Methods
CONSTRUCTION
METHODS
TYPES
Individual Removal of Trees
Disposal of Debris
CONSTRUCTION METHODS - EARTHWORKS
CLEARING AND GRUBBING
EQUIPMENT REQUIREMENTS
Dump Truck (10 cum.)
Payloader (1.5 cum.)
Bulldozer
CONSTRUCTION METHODS - EARTHWORKS
CLEARING AND GRUBBING
1. Right-of-way limits must be provided with stakes, as reference in determining the
vertical/horizontal control.
2. Trees that are selected for preservation must be protected, while trees that are
needed to be cut/ball shall be identified.
3. After establishment of construction limits, scarify up to a depth of 150mm.
4. Haul the excavated materials to a designated approved disposal area or stockpile.
5. Clearing shall extend one meter beyond the toe of the fill slopes or beyond
rounding of cut slopes for the entire length of the project.
CONSTRUCTION METHODS - EARTHWORKS
REMOVAL OF STRUCTURES AND OBSTRUCTIONS
Consist of the taking away, wholly or in part, and the satisfactory disposal
of all structures within the construction site and right-of-way which are not
designated to remain. It shall also include the salvaging of materials and
backfilling.
TYPES
Existing Pavements Electrical Post and Lines
Existing Drainage Structures Cable and Telephone Lines
Underground Waterline Residential Houses & Buildings
CONSTRUCTION METHODS - EARTHWORKS
REMOVAL OF STRUCTURES AND OBSTRUCTIONS
EQUIPMENT REQUIREMENTS
Backhoe w/ Breaker (0.80 cum.)
Dump Truck (10 cum.)
Minor Tools
CONSTRUCTION METHODS - EARTHWORKS
REMOVAL OF STRUCTURES AND OBSTRUCTIONS
1. Simultaneously with the clearing and grubbing works, removal of obstructions,
both overhead and underground utilities in particular waterlines and telephone
lines, shall be undertaken.
2. There will be no separate payment for excavating for the removal of structures
and obstructions, or for backfilling and compacting the remaining cavity.
CONSTRUCTION METHODS - EARTHWORKS
EXCAVATION
Consists of all the excavation for grading and draining the roadway. It also
includes loading, hauling and placing the excavated materials from roadway
cuts to construct embankments or its disposal to a designated location.
TYPES
TYPES
Structure Excavation Shoring, Cribbing and Related
Bridge Excavation Works
Foundation Fill
Pipe Culverts and Drain Excavation
Excavation ordered below Plan
Elevation
CONSTRUCTION METHODS - EARTHWORKS
STRUCTURE EXCAVATION
EQUIPMENT REQUIREMENTS
Dump Truck (10 cum.)
Backhoe (0.80 cum.)
Minor Tools
CONSTRUCTION METHODS - EARTHWORKS
STRUCTURE EXCAVATION
1. Prior to structure excavation, all necessary clearing and grubbing shall have been
performed.
2. Trenches shall be excavated to the lines and grades or elevations shown on the
Plans.
3. For Pipe Culverts: The width of the excavation shall be at least 300 mm greater
than the horizontal outside diameter of the pipe.
4. The foundation surface shall provide a firm foundation of uniform density
throughout the length of the culvert.
CONSTRUCTION METHODS - EARTHWORKS
EMBANKMENT
The work or volume of earthen material necessary in the formation of
embankment roadway thru the use of suitable materials which may be
sourced along the road traverse or borrow from an outside source. These
materials are brought and compacted together to a specified degree to form
a stable embankment to bring the road to a desired grade or to elevate it
above flood level.
TYPES
TYPES
In a fill section, the sub grade is the top of the embankment or the fill.
In a cut section, the sub grade is the bottom of the cut.
CONSTRUCTION METHODS - EARTHWORKS
SUBGRADE PREPARATION
EQUIPMENT REQUIREMENTS
Motorized Road Grader (140 hp)
Vibratory Roller (10 mt)
Water Truck (16000 L)
CONSTRUCTION METHODS - EARTHWORKS
SUBGRADE PREPARATION
1. Prior to commencing preparation of the subgrade, all culverts, cross drains, ducts and
the like (including their fully compacted backfill), ditches, drains and drainage outlets
shall be completed.
2. Compaction shall be done by rolling using vibratory road roller or tandem steel roller.
3. Conduct one group of three in-situ density tests for each 500 sq.m. or fraction thereof
of compacted layer. If it fails to meet the minimum 95% density, additional rolling
shall be undertaken until such time that the required compaction is obtained.
4. The succeeding structural layers should proceed immediately after preparation of
the subgrade.
CONSTRUCTION METHODS
PART II – SUBBASE AND BASE COURSE
Aggregate Subbase Course
Aggregate Base Course
CONSTRUCTION METHODS – SUBBASE & BASE
COURSE
AGGREGATE SUBBASE COURSE
Refers to the structural sub-layer material of a roadway placed directly on
top of the sub-grade.
CONSTRUCTION METHODS – SUBBASE & BASE
COURSE
AGGREGATE SUBBASE COURSE
EQUIPMENT REQUIREMENTS
Motorized Road Grader (140 hp)
Vibratory Roller (10 mt)
Water Truck (16000 L)
CONSTRUCTION METHODS – SUBBASE & BASE
COURSE
AGGREGATE SUBBASE COURSE
1. Check the subgrade if it is already completed in accordance with the plans and
specifications before proceeding with the laying of subbase course materials.
2. Provide blue-tops at every 20 meters interval (marked staked) for vertical control
reference, to be placed along the side of the roadway.
3. Laying and spreading of aggregate sub base materials shall be done using road
grader on a prepared subgrade in a quantity which will provide the required
compacted thickness.
CONSTRUCTION METHODS – SUBBASE & BASE
COURSE
AGGREGATE SUBBASE COURSE
4. Appropriate crown/cross slope should be maintained during laying/spreading
operation to ensure proper draining.
5. Compaction should be done using a vibratory road roller or tandem roller with a
minimum weight of 10 tons. A maximum compacted thickness for any layer shall
not exceed 150 mm.
6. No laying, spreading, rolling and compaction operations shall be done when it is
raining or when the laid subbase course is fully saturated with rain.
CONSTRUCTION METHODS – SUBBASE & BASE
COURSE
AGGREGATE SUBBASE COURSE
7. Rolling/compaction shall progress gradually from the sides to the center, parallel
to the center of the road and shall continue until the whole surface has been rolled
up to the number of passes required based on the trial section result where 100%
compaction is attained. Progress rolling should provide 300 mm. overlap of the
width of the wheel for each succeeding parallel passes to ensure level compacted
surface.
8. Allowable tolerance for thickness of layer is plus or minus 20mm.
CONSTRUCTION METHODS – SUBBASE & BASE
COURSE
AGGREGATE SUBBASE COURSE
9. Conduct one group of three in-situ density tests for each 500 sq.m. or fraction
thereof of compacted layer. If it fails to meet the minimum 100% density,
additional rolling shall be undertaken until such time that the required compaction
is obtained.
CONSTRUCTION METHODS – SUBBASE & BASE
COURSE
AGGREGATE BASE COURSE
In flexible pavement, it is the load-carrying portion and provides the
structural capacity to bituminous concrete slabs by carrying the load and
distributing it to the soil under the layers of asphalt concrete.
The life and riding qualities of asphalt concrete surface depends directly on
the care exercised in the construction of aggregate base course.
CONSTRUCTION METHODS – SUBBASE & BASE
COURSE
AGGREGATE BASE COURSE
EQUIPMENT REQUIREMENTS
Motorized Road Grader (140 hp)
Vibratory Roller (10 mt)
Water Truck (16000 L)
CONSTRUCTION METHODS – SUBBASE & BASE
COURSE
AGGREGATE SUBBASE COURSE
1. Check the preparation of the existing surface if it is already completed in
accordance with the plans and specifications before proceeding with the laying of
base course materials.
2. Laying and spreading of aggregate sub base materials shall be done using road
grader on a prepared subgrade/subbase in a quantity which will provide the
required compacted thickness.
3. Appropriate crown/cross slope should be maintained during laying/spreading
operation to ensure proper draining.
CONSTRUCTION METHODS – SUBBASE & BASE
COURSE
AGGREGATE BASE COURSE
4. Compaction should be done using a vibratory road roller or tandem roller with a
minimum weight of 10 tons. A maximum compacted thickness for any layer shall
not exceed 150 mm.
5. Rolling/compaction shall progress gradually from the sides to the center, parallel
to the center of the road and shall continue until the whole surface has been rolled
up to the number of passes required based on the trial section result where 100%
compaction is attained. Progress rolling should provide 300 mm. overlap of the
width of the wheel for each succeeding parallel passes to ensure level compacted
surface.
CONSTRUCTION METHODS – SUBBASE & BASE
COURSE
AGGREGATE SUBBASE COURSE
6. No laying, spreading, rolling and compaction operations shall be done when it is
raining or when the laid subbase course is fully saturated with rain.
7. Conduct one group of three in-situ density tests for each 500 sq.m. or fraction
thereof of compacted layer. If it fails to meet the minimum 100% density,
additional rolling shall be undertaken until such time that the required compaction
is obtained.
8. Allowable tolerance for thickness of layer is plus or minus 10mm.
CONSTRUCTION METHODS
PART III – SURFACE COURSE
Bituminous Prime Coat
Bituminous Tack Coat
Bituminous Concrete Surface Course
Portland Cement Concrete Pavement
CONSTRUCTION METHODS – SURFACE COURSE
Design Mix/ Job Mix and Trial Paving
CONCRETE:
DESIGN MIX
STAR MATERIAL TRIAL PAVEMENT
PASSED? TRIAL MIX
T TEST SECTION TESTING
ASPHALT:
JOB-MIX
ACQUIRE NEW
MATERIALS PASSED?
contractor shall construct a test section using the trial mix design. START PAVING
The trial section shall be located either on an outside area or on
actual construction lane site.
END
APPLICATION TEMPERATURE
135°C (min.) to 148.89°C (max.)
CONSTRUCTION METHODS – SURFACE COURSE
BITUMINOUS CONCRETE SURFACE COURSE
EQUIPMENT REQUIREMENTS
Asphalt Paver (80 hp)
Pneumatic Tire Roller (10 mt)
Tandem Steel Roller (10 mt)
Water Truck (16000 L)
Minor Tools
CONSTRUCTION METHODS – SURFACE COURSE
BITUMINOUS CONCRETE SURFACE COURSE
1. 3 weeks prior to production, the contractor shall submit in writing a job-mix
formula.
2. Before placing the bituminous mixture, the existing surface shall be cleaned of
loose deleterious materials.
3. The mixture shall be spread and distributed to the grade and elevation in
accordance with the approved plans by means of an Asphalt Paver over the entire
width or partial width as may be practicable.
4. The longitudinal joint in one (1) layer shall be offset that in the layer immediately
below approximately 15 cm.
CONSTRUCTION METHODS – SURFACE COURSE
BITUMINOUS CONCRETE SURFACE COURSE
5. The joint in the top layer shall be at the center line of the pavement if the roadway
comprises of two (2) lanes.
6. Mechanical spreading shall be used on areas with irregularities or unavoidable
obstacles.
7. The mixture shall be placed at a temperature not less than 107°C.
8. Rolling/compaction shall progress gradually from the sides to the center, parallel
to the center of the road and shall continue until the roller marks are eliminated
and a minimum of 97 mass percent of the density has been obtained. Progress
rolling should provide overlap equal to ½ the roller width.
CONSTRUCTION METHODS – SURFACE COURSE
BITUMINOUS CONCRETE SURFACE COURSE
9. For paving in abutting a previously placed lane, the longitudinal joint shall be
rolled first followed by the regular rolling procedure.
10. For super-elevated curves, the rolling shall begin at the low side and progresses to
the high side overlapping of longitudinal trips parallel to the center line.
11. Rollers shall move at a slow but uniform speed with the drive roll or wheels
nearest the paver.
12. Rolling shall be continued until roller marks are eliminated.
CONSTRUCTION METHODS – SURFACE COURSE
BITUMINOUS CONCRETE SURFACE COURSE
13. Transverse joints shall be formed by cutting back on the previous run to expose its
full depth.
14. Brush coat of bituminous material shall be used on contact surfaces of transverse
joints before additional mixture is placed against the previously rolled material.
15. Each sample of at least 150mm x 150mm or 100 mm diameter full depth shall be
neatly cut by saw or core drill.
16. At least one (1), but not more than 3 samples shall be taken for each full day’s
operation.
CONSTRUCTION METHODS – SURFACE COURSE
BITUMINOUS CONCRETE SURFACE COURSE
17. No acceptance and final payment shall be made on completed asphalt pavement
unless core test for thickness determination is conducted.
18. The compacted pavement shall have a thickness tolerance of
-5mm. Thickness in excess of the specified thickness shall not be considered in the
payment.
CONSTRUCTION METHODS – SURFACE COURSE
PORTLAND CEMENT CONCRETE PAVEMENT
Constructed by casting in place, on a prepared foundation, a concrete slab
with the top finished to provide a smooth and durable wearing surface for
traffic.
It is a mixture composed of Portland Cement, Fine Aggregates, Coarse
Aggregates and Water. Specific quantities of each component are
determined in the Design Mix.
APPLICATION TEMPERATURE
32°C (max.)
CONSTRUCTION METHODS – SURFACE COURSE
PORTLAND CEMENT CONCRETE PAVEMENT
EQUIPMENT REQUIREMENTS (Conventional Method)
Transit Mixer (5 cum.) Water Truck (16000 L)
Concrete Vibrator Concrete Saw (7.5 hp)
Batching Plant (30 cum.) Bar Cutter, Single Phase
Payloader (1.50 cum.) Minor Tools
Concrete Screeder (5.5 hp)
CONSTRUCTION METHODS – SURFACE COURSE
PORTLAND CEMENT CONCRETE PAVEMENT
EQUIPMENT REQUIREMENTS (Using Concrete Paver)
Batching Plant (30 cum.) Concrete Saw (7.5 hp)
Concrete Paver, Four-Track Concrete Vibrator
Transit Mixer (5 cum.) Bar Cutter, Single Phase
Payloader (1.50 cum.)
Water Truck (16000 L)
CONSTRUCTION METHODS – SURFACE COURSE
PORTLAND CEMENT CONCRETE PAVEMENT
1. Before commencement of concreting operations, check the adequacy of the
following:
a. Condition of subbase or base course
b. Working condition of major equipment
c. Number of hand tools and finishing tools
d. Provision for curing
e. Number of crews to place, finish and cure the concrete
CONSTRUCTION METHODS – SURFACE COURSE
PORTLAND CEMENT CONCRETE PAVEMENT
2. Check the setting of forms based on the base support, form setting and grade and
alignment.
3. During hot weather, steps shall be taken to prevent the temperature of mixed
concrete from exceeding the max. temperature of 32°C.
4. Concrete not in place within ninety (90) minutes from the time the ingredients
were charged into the mixing drum or that has developed initial set shall not be
used.
5. Concrete shall be deposited in such manner to require minimal rehandling.
CONSTRUCTION METHODS – SURFACE COURSE
PORTLAND CEMENT CONCRETE PAVEMENT
6. Concrete shall be unloaded into an approved spreading device and mechanically
spread on the grade in such manner as to prevent segregation.
7. Workmen shall not be allowed to walk in the freshly mixed concrete with boots or
shoes coated with earth or foreign substances.
8. Concrete shall be thoroughly consolidated against and along the faces of all forms and
along the full length and on both sides of all joint assemblies by means of vibrators.
9. Vibrators shall not be permitted to come in contact with a joint assembly, the grade, or
a side form. In no case shall the vibrator be operated longer than 15 seconds in any
one location.
CONSTRUCTION METHODS – SURFACE COURSE
PORTLAND CEMENT CONCRETE PAVEMENT
10. Placing of concrete should be continuous. A construction joint shall be required
when there is an interruption of more than 30 minutes in the concreting operations.
11. Concrete finishing shall be done using a longitudinal float after the concrete has
been consolidated.
12. Brooming of concrete shall be in a uniform appearance and corrugations at a depth
of 1.5mm.
13. At least one (1) set consisting of three (3) concrete beam test specimens, 150 x
150 x 525mm shall be taken from each 330 sqm. Of pavement, 230mm depth, or
fraction thereof placed each day.
CONSTRUCTION METHODS – SURFACE COURSE
PORTLAND CEMENT CONCRETE PAVEMENT
14. Curing of concrete shall be done in accordance with either one of the following
methods.
a. Cotton or Burlap Mats
b. Waterproof Paper or Polyethylene Sheets
c. Earth or Straw Curing
d. Curing Compound
15. Forms of concrete shall remain in place undisturbed for not less than twenty four
(24) hours after concrete pouring. Crowbars should be used in pulling out nails
and pins.
CONSTRUCTION METHODS – SURFACE COURSE
PORTLAND CEMENT CONCRETE PAVEMENT
16. Cutting of contraction joints/weakened plane joints shall be done within 24 hours
after concrete pouring.
17. Joints shall be cleaned of all foreign materials and then sealed with asphalt sealant
soon after completion of the curing period and before the pavement is opened to
traffic.
CONSTRUCTION METHODS – SURFACE COURSE
PORTLAND CEMENT CONCRETE PAVEMENT (JOINTS)
1. Longitudinal Joint
a. 1 lane construction
b. With keyway
c. Use tie bars
2. Expansion Joint
a. Prevents buckling
b. Requires expansion Joint Filler
c. Use dowel bars
CONSTRUCTION METHODS – SURFACE COURSE
PORTLAND CEMENT CONCRETE PAVEMENT (JOINTS)
3. Contraction Joint / Weakened Plane Joint
a. Relieve tensile stresses
b. Prevents random cracking
c. No reinforcement required
4. Construction Joint / Cold Joint
a. Interruption of 30 mins. on concreting operation
b. Placed within the middle third of the concrete block
c. Use tie bars
CONSTRUCTION METHODS – SURFACE COURSE
PORTLAND CEMENT CONCRETE PAVEMENT (JOINTS)
Size, Length and Spacing of Dowel/Tie Bars
CONSTRUCTION METHODS – SURFACE COURSE
REPLACEMENT OF DETERIORATED PCCP SLABS
1. The engineer and the contractor shall conduct a joint survey to confirm current
conditions and identify the PCCP slabs to be replaced.
2. The contractor shall remove broken/deteriorated PCCP slabs in accordance with
the Plans, Specifications or as directed by the engineer.
3. The subgrade and subbase course are prepared in accordance with the
specifications or as directed by the engineer.
CONSTRUCTION METHODS – SURFACE COURSE
REPLACEMENT OF DETERIORATED PCCP SLABS
4. Existing tie bars on longitudinal joints are to be retained if these are still in good
condition. Where necessary, new tie bars shall be installed on drilled holes and
bonded with high viscosity epoxy resin.
5. Install forms while the side surfaces of the existing PCCP shall be free from loose
concrete.
6. Pour concrete; perform the required surface texturing, cutting and curing.
7. Thoroughly clean the joints and apply sealants adequately.
CONSTRUCTION METHODS – SURFACE COURSE
WIDENING OF PCCP PAVEMENT
TYPES
Asphalt
Concrete
CONSTRUCTION METHODS – MISCELLANEOUS
STRUCTURES
SIDEWALK
EQUIPMENT REQUIREMENTS
One Bagger Mixer
Concrete Vibrator
Water Truck (16000 L)
Concrete Saw (7.5 hp)
Minor Tools
CONSTRUCTION METHODS – MISCELLANEOUS
STRUCTURES
SIDEWALK
1. Excavation shall be made to the required depth and width required that will
permit the installation and bracing of forms.
2. For asphalt sidewalk, the prepared bed course shall be applied with prime coat
prior to application of the asphalt mixture and then compacted by rolling with a
hand operated roller.
3. For concrete sidewalk, all forms shall be staked securely in position at the correct
line and level prior to concreting. The surface shall be cut through to a depth of
10mm with a trowel at intervals of 1m.
THANK YOU!!!