Estimation and Costing
Estimation and Costing
Prepared by
R.BALAMURUGAN
Assistant Professor
Department of Civil
Engineering
CE8701 ESTIMATION, COSTING AND VALUATION ENGINEERING LTPC
3003
OBJECTIVE:
The students will acquire knowledge in estimation, tender practices, contract
procedures, and valuation and will be able to prepare estimates, call for tenders and
execute works.
UNIT IV CONTRACTS
9
Contract – Types of contracts – Formation of contract – Contract conditions –
Contract for labour, material, design, construction – Drafting of contract documents
based on IBRD / MORTH Standard bidding documents – Construction contracts –
Contract problems – Arbitration and legal requirements.
UNIT V VALUATION
9
Definitions – Various types of valuations – Valuation methods - Necessity –
Capitalised value – Depreciation – Escalation – Valuation of land – Buildings –
Calculation of Standard rent – Mortgage – Lease
ESTIMATION
Estimation is the scientific way of working out the
approximate cost of an engineering project before
execution of the work.
Department of Civil
Engineering
ESTIMATE
An estimate of the cost of a construction job is the
probable cost of that job as computed from plans
and specifications.
Department of Civil
Engineering
UNITS OF MEASUREMENTS
The units of measurements are mainly categorized
for their nature, shape and size and for making
payments to the contractor.
a) Single units work like doors, windows etc, is expressed in numbers.
b) Works consists linear measurements involve length like cornice,
fencing, hand rail etc., are expressed in running meters (RM)
c) Works consists areal surface measurements like plastering, white
washing, partitions of specified thickness etc., are expressed in
square meters.
d) Works consists cubical contents which involve volume like earth
work, cement concrete, Masonry etc., are expressed in Cubic meters.
Department of Civil
Engineering
NEED OF ESTIMATION & COSTING
1. It help to work out the approximate cost of the project in order
to decide its feasibility with respect to the cost and to ensure
the financial resources.
3. It is used for framing the tenders for the works and to check
contractor’s work during and after the its execution for the
purpose of making payments to the contractor.
2) SPECIFICATIONS
a) General Specifications:
This gives the nature, quality of work and materials in general terms
to be used in various parts of wok. It helps to form a general
idea of building.
• Detailed Specifications:
This gives the detailed description of the various items of work
laying down the Quantities and qualities of materials, their
proportions, the method of preparation workmanship and
execution of work.
Department of Civil
Engineering
3) RATES
For preparing the estimate the unit rates of each item of work
are required.
1. For arriving at the unit rates of each item.
2. The rates of various materials to be used in the construction.
3. The cost of transport materials.
4. The wages of labor, skilled or unskilled of masons, carpenters,
Amador, etc.,
LUMPSUM:
While preparing an estimate, it is not possible to work out in
detail in case of petty items. Items other than civil
engineering such items are called lump sum items or simply
L.S.Items.
Department of Civil
Engineering
Factors to be considered for estimation
1. Each type of work requires a different method of construction.
Construction may be of an ordinary house or office and it may
also be of a Dam, Tunnel, Multistory building, Airport, Bridge,
or a Road, already in operation. Each of these works requires
totally different construction techniques, type of machinery,
and formwork.
2. Quality of labour and labour output varies in different localities.
Department of Civil
Engineering
Factors to be considered for estimation (-ctd-)
4. Ground conditions vary and change the method of
construction. For example, excavation may be dry, wet, hard,
soft, shallow or deep requiring different efforts.
Department of Civil
Engineering
TYPES OF ESTIMATES
Department of Civil
Engineering
Rough (or) approximate estimate
• Preliminary or approximate estimate is required for
studies of various aspects of work of project and for its
administrative approval.
• It can decide, in case of commercial projects, whether
the net income earned justifies the amount invested or
not. The approximate estimate is prepared from the
practical knowledge and cost of similar works.
• The following are the methods used for preparation of
approximate estimates.
• Plinth area method
• Cubical contents methods
• Unit base method.
Department of Civil
Engineering
1) Plinth area method
cost of construction = Plinth area x plinth area rate.
2) Cubical Contents Method
It is more accurate that the other two methods viz., plinth area method
and unit base method.
cost of construction = Total cubical contents x Local Cubic Rate.
• Unit Base Method
. For public buildings, cost. Per person (cost per capita) is used. For
example,
Students hostel - cost per student
Hospital - Cost per bed
Hotel - Cost per Guest
Department of Civil
Engineering
EXAMPLE 1
• Prepare a Rough-cost Estimate of a residential building
project with a total plinth area of all building of 1500 sq.m.
given that:
• Plinth Area Rate = Rs: 950.00 / sq. ft.
• Extra for special architectural treatment = 1.5 % of the
buiding cost.
• Extra for water supply and sanitary installations = 5 % of
the building cost.
• Extra for internal installations = 14 % of the buiding cost
• Extra for Electric & Sui gas services = 16 % of buiding cost
• Contigencies 3 % overall
• Supervision charges = 8 % overall
•Department
Design charges = 2 % overall
of Civil
Engineering
EXAMPLE 2
• Prepare a Rough-cost Estimate based on unit costs of per unit plinth
area basis of a four storeyed office building having a carpet area of
2000 sq.m. for obtaining the administrative approval of the
Government. It may be assumed that 30 % of the built up area will be
taken by the corridors, verandas, lavatories, staircase, etc. and 10 % of
built up area will be occupied by walls. The following data is given:
Department of Civil
Engineering
Example 2 (ctd)
Department of Civil
Engineering
DETAILED ESTIMATE
• Detailed estimates are prepared by carefully and separately
calculating the costs of various item of the work that constitute
the whole project from the detailed working drawings after the
design has been finalized.
Department of Civil
Engineering
DETAILED ESTIMATE
Department of Civil
Engineering
BILL OF QUANTITIES
Description No Measurements Quantity Total Remarks
Sr. No
of item Quantity
Department of Civil
Engineering
PRICED BILL OF QUANTITIES
Department of Civil
Engineering
DETAILED ESTIMATE
• Each item of the work is then multiplied by its estimated current
rate calculated by a fixed procedure to find out cost of the item.
• At the end, a total of all items of the work are made to get the
total estimated cost.
• The rates are usually as per Schedule of Rates for the locality plus a
premium to allow for rise in labor and material rates over and
above the schedule of rates.
Department of Civil
Engineering
DETAILED ESTIMATE
Besides drawings and details of measurements and calculation of quantities (Bill
of Quantities), the following documents are also usually submitted with the
detailed estimate for obtaining Technical Sanction:
Department of Civil
Engineering
METHODS OF DETAILED ESTIMATE
• The dimensions, length, breadth and height or depth are to be
taken out from the working drawings (plan, elevation and
section).
Department of Civil
Engineering
LONG WALL & SHORT WALL METHOD (or)
SEPARATE WALL METHOD
Department of Civil
Engineering
LONG WALL & SHORT WALL METHOD
Department of Civil
Engineering
CENTER LINE METHOD
• In this method, total length of center lines of walls, long and
short, has to be found out.
Department of Civil
Engineering
CENTER LINE METHOD
For rectangular, circular polygonal (hexagonal, octagonal
etc.,) buildings having no inter or cross walls, this method is
quite simple.
Department of Civil
Engineering
Problem-1
Estimate in detail the quantities of following
items of work for a given plan and section as
shown in Fig.1 using Centre line method and
Long wall & short wall method.
Concrete in foundation
Brickwork in 1st step in foundation
First class brickwork in super structures
Department of Civil
Engineering
Department of Civil
Engineering
Estimation of Quantity of Concrete in
Foundation
Center Line method:
Total Length of Center Line = 5.3+5.3+4.3+4.3 = 19.2 m
Length of Long wall = 5.3+0.9 = 6.2 m Length of Short wall = 4.3-0.9 = 3.4 m
Quantity of concrete in foundation = 2 x (6.2+3.4) x 0.9 x 0.3 cu.m
Department of Civil
Engineering
Estimation of Quantity of Brickwork in
1st step Foundation
Department of Civil
Engineering
Center Line method:
Total Length of Center Line = 5.3+5.3+4.3+4.3 = 19.2 m
width of foundation = 0.6 m
Total quantity of brickwork in 1st step foundation = 19.2 x 0.9 x 0.3 cu.m
Department of Civil
Engineering
Long Wall & Short Wall method:
Length of Long wall = 5.3+0.6 = 5.9 m Length of Short wall = 4.3-0.6 = 3.7 m
Quantity of brickwork in 1st step foundation = 2 x (5.9+3.7) x 0.6 x 0.3 cu.m
Department of Civil
Engineering
Estimation of Quantity of
Brickwork in super structure
Department of Civil
Engineering
Center Line method:
Total Length of Center Line = 5.3+5.3+4.3+4.3 = 19.2 m
width of wall = 0.3 m Total quantity of brickwork in wall = 19.2 x 3.5 x 0.3 cu.m
Department of Civil
Engineering
Long Wall & Short Wall method:
Length of Long wall = 5.3+0.3 = 5.6 m Length of Short wall = 4.3-0.3 = 4.0 m
Quantity of brickwork in wall = 2 x (5.6+4.0) x 0.3 x 3.5 cu.m
Department of Civil
Engineering
Problem-2
Estimate in detail the quantities of following items
of work for a given plan and section as shown in
Fig.2 using Centre line method and Long wall &
short wall method.
Concrete in foundation
Brickwork in 1st step in foundation
First class brickwork in super structures
Department of Civil
Engineering
Department of Civil
Engineering
Estimation of Quantity of Concrete in
Foundation
Center Line method:
Total Length of Center Line = (4 x 5.3) +(3 x 4.3) = 34.1 – 0.9 = 33.2 m
width of foundation = 0.9 m
Total quantity of concrete in foundation =33.2 x 0.9 x 0.3 cu.m
Department of Civil
Engineering
Long Wall & Short Wall method:
Length of Long wall = 5.3+5.3+0.9 = 11.5 m Length of Short wall = 4.3-0.9 = 3.4 m
Quantity of concrete in foundation= [ (2x11.5) + (3X3.4) ] x 0.9 x 0.3 cu.m
Department of Civil
Engineering
References:
• https://www.wikipedia.org/
• https://nptel.ac.in/course.php
• https://www.vidyarthiplus.com/studymat
erials.php
THANK YOU
Department of Civil
Engineering