Premiere Manufacturing Case Study, Step 1: Background: The Present Situation
Premiere Manufacturing Case Study, Step 1: Background: The Present Situation
W&I 26,600
Y&J 12,100
D, G & L 5,900
Sequence of Operations by Process in
Identifying Value Stream
Additional Considerations for
Value Stream Selection
The long-term agreement that Premiere has made with Cord commits
Premier to improving on-time delivery and cutting costs associated
with the manufacture of #4, #6, #8, and #10 coolant hoses. In effect,
this means that Cord has selected the target value stream on which
Premier needs to focus. Nevertheless, the core team performs a
product-routing analysis to form a clearer picture of the process routes
for each product type.
The product-routing analysis reveals some important facts:
Products #4 and #6 share the same process route, while products #8 and
#10 share a slightly different process route.
The process route for products #4 and #6 is slightly less complex than the
process route for products #8 and #10.
The total volume of products #4 and #6 is 80 percent of the total quality
produced for Cord.
Premiere Manufacturing, Product-Routing
Analysis (grouped by process)
20,160 #4 ● ● ● ● ●
10,080 #6 ● ● ● ● ●
4,360 #8 ● ● ● ● ● ●
3,200 #10 ● ● ● ● ● ●
Premiere Manufacturing Case Study, Step 2
(cont'd)
In addition, analysis of ordering patterns over the past three
months shows that demand for #4 and #6 hoses is nearly
constant, whereas demand for #8 and #10 hoses is more
sporadic. Given these facts, the team reasons that it is best
to focus first on improving the process for making #4 and #6
hoses, then tackle the process for making #8 and # 10 hoses.
–Poor lighting
–Dirty equipment
to point of use
Two Pillars of Toyota Production System
JIT Production
Continuous flow and ability to replenish a single part pulled by
customer
Only those units ordered, just when needed in the exact amount
needed
Jidoka (Autonomation)
Automation to mistake proof
Automation with a human touch
Goal of zero defects with continuous flow
Separate human work from machine work
Develop Poka-Yoke devices
The Toyota Production System
Three Stages of Lean Production
Takt Time
202 (TCT)
#Operators needed = 3.36
60 (takt time)
Origin of Kanban
In Japanese, Kanban means card, billboard or sign
It refers to inventory control card used in pull system
Also used synonymously with inventory control system
in TPS
Kanbans manage flow of material in and out of
supermarkets, lines and cells
Can be used to regulate orders from the factor to
suppliers
Kanban Control of Material Flow
Types of Kanban
Kanban Rules
An upstream operation cuts steel rods for a cell that makes three
slightly different but related products. One product starts with a
3-inch diameter rod that is 8 inches long, the second product
starts with a 4-inch diameter rod that is 10 inches long, and the
third product starts with a 5-inch diameter rod that is 12 inches
long. Since the cell requires three different sized rods, you could
establish a FIFO lane to ensure that the rods are processed
downstream in the order that they were cut.
On the other hand, if each of the three products were made from
the same-sized steel rod, you could establish an in-process
supermarket from which parts could be pulled when needed.
Flow Using Supermarkets
Advantages:
Allows for flow when using shared equipment.
Disadvantages:
ҳ Quality is harder to monitor and correct when producing in
small batches.
ҳ Erosion of takt image.
ҳ Loss of control.
Flow Using FIFO Lines
Advantages:
Allows for flow when potential for chronic failure of upstream
process exists.
Allows for flow during tool changes
ҳ Loss of control.
Level Production
Product A B C D E
Pack-out quantity 25 25 25 25 25
# of Kanbans 12 8 8 2 2
Heijunka (Load Leveling) (cont'd)
Runner Qualifications:
• Understands value stream production requirements
• Communicates well
such as breaks and lunch that reduce available mean-time between failures, uptime, or
time overall equipment effectiveness (the product
Total available daily production time of availability, performance, and quality
(subtract regularly planned downtime rates)
occurrences from the total time per shift) Shifts on which the process operates
Quantity of parts shipped per month and per because they can reduce net available time for
day (by part) a particular process)
Cycle times Disruptions in manufacturing flow
• 3,360 #6 hoses per month (20 days = 168 hoses per day)
Creating Current State Map (cont'd)
Enter process attributes in the data boxes in process icons. Show value added
time (cycle time), change-over time, available time, and up time in each box
Attributes defined
For each operation, availability is, in effect, the available production time. This is
determined by taking the shift time or total available production time – 8.5 hours
(510minutes) in the Premiere Manufacturing case study – and subtracting regular
planned down-time occurrences (a 30-minutes unpaid lunch and two 10-minute paid
breaks). Therefore, the available production time is 460 minutes, or 27,600 seconds.
Changeover times given are per shift
Changeover times are not considered planned downtime occurrences. Therefore, they
diminish an operation’s available production time to give you actual operating time.
Uptime is calculated by dividing actual operating time by available time. Actual
operating time for each operation equals available production time minus changeover
time. For example, the uptime calculation for machining looks like this:
uptime = 27,600 seconds – 3600 seconds
27,600
uptime = 87%
In upper right hand corner, shift time, planned breaks and total available
production time
Creating Current State Map (cont'd)
Creating Current State Map (cont'd)
→ Inventory turns
→ Days of inventory on-hand
→ Defective parts per million (DPPM) or sigma level
→ Total value stream WIP
→ Total cycle time, or total value adding time (VAT)
→ Total lead time
→ Uptime
→ On-time delivery
→ Overall equipment effectiveness
→ First-time-through capability
→ Health and safety record (including OSHA recordable and
reportable incidents)
Metric Stratification
After reviewing the list of common metrics and the customer’s requirements.
Premiere’s core implementation team drafts a list of the metrics that will work
best for tracking progress toward the targets. The team reviews the metrics
with management and gains their buy-in. Figure 5-3 shows the metrics and the
baseline figures determined during current-state mapping.
The team also calculates the number of days of WIP on-hand between each
operation. Daily WIP is determined by dividing the actual quantity of hoses by
the daily total quantity of hoses required by the customer. The team calculates
daily customer requirements (demand) by dividing the number of hoses required
per month (10,080)by the number of shipping days per month (20)
Premiere Manufacturing Case Study, Step 5
(cont'd)
Total number of hoses (#4 and #6) required per day:
10,080 hoses required per month + 20 shipping days per month = 504 hoses per day.
WIP calculations (#4 and #6 hoses combined):
Raw material prior to machining
2,500 hoses (504 hoses per day = 5 days on-hand
Between machining and deburring
5,040 hoses (504 hoses per day = 10 days on-hand
Between deburring and crimping
3,500 hoses (504 hoses per day = 7 days on-hand
Between crimping and testing
2,000 hoses (504 hoses per day = 4 days on-hand
Between testing and marking
2,000 hoses (504 hoses per day = 4 days on-hand
Between marking and shipping (finished goods)
2,000 hoses (504 hoses per day = 4 days on-hand
Total inventory (in days)
5 + 10 + 7 + 4 + 4 + 4 = 34 days on-hand
Premiere Manufacturing Case Study, Step 5
(cont'd)
Total Product Cycle Time
To determine the total product cycle time, also referred to
as total value adding time, the core implementation team
studies the current-state map and lists the cycle times for
each operation:
• Machining: 45 seconds
• Deburring: 5 seconds
• Crimping: 40 seconds
• Marking: 50 seconds
By adding together the cycle times for each operation, the
team calculates the following total product cycle time:
45 seconds + 5 seconds + 40 seconds + 30 seconds + 50
seconds = 170 seconds
Premiere Manufacturing Case Study, Step 5
(cont'd)
Total Value Stream Lead Time
To determine total value stream lead time, the team turns to the current-state map to see
how long it takes for material to flow through the process once an order was released to
the production floor. Here are the times (which, coincidentally, correspond to the
number of day of WIP between the operations):1
• 5 days prior to machining
• 10 days between deburring and crimping
• 7 days between deburring and crimping
• 4 days between crimping and testing
• 4 days between testing and marking
• 4 days between marking and shipping
5 + 10 + 7 + 4 + 4 + 4 = 34 days
A total value stream lead time of 34 days means that it takes at least this long to complete
a customer order. In other words, Premiere’s lead time is close to seven five-day work-
weeks! Given that the value-adding time or total value stream cycle time is just 170
seconds, the team realizes that the opportunity for improvement is tremendous.
_______
1
Although it is not always true that the lead time will equal the total number of days of WIP inventory in the
value stream, the measures are often very close. This is because the time that WIP is idle and waiting to be
processed is huge compared to the actual time that material is being processed.
Premiere Manufacturing Case Study, Step 5
(cont'd)
On-Time Delivery
Premiere’s shipment compliance or on-time delivery is only 88 percent due to the
following factors:
• Uptime issues at the machining operation
• Constantly shifting production schedules
• 95 percent on-time delivery on average between internal suppliers and customers,
resulting in cumulative on-time percentage of 81.4 percent (.95 x .95 x .95 x .95 –
81.4 percent)
Defective PPM-External
The team researches quality data and finds that the current internal defect rate,
expressed in parts per million (ppm), is 5,000. The defects are mainly produced by
the marking operation. Despite the high internal defect rate, Premiere passes on
relatively few of the defects to Cord. However, the external defect rate, 45 ppm, is
still high by lean manufacturing standards, because the goal of a lean enterprise is
zero defects. The team decides that it is important to track both internal and
external defect rates, but since the external defect rate is the best reflection of how
well Premiere is serving its customer, this is the metric that the team chooses to
display on the storyboard.
Premiere Manufacturing Case Study, Step 5
(cont'd)
Uptime
The team determines the cumulative uptime measure for the
value stream based on the uptime measures for each operation:
• Machining: 87 percent
• Deburring: 100 percent
• Crimping: 99 percent
• Testing 99 percent
• Marking: 99 percent
0.87 x 1 x 0.99 x 0.99 x 0.99 = 0.844 (84 percent)
After agreement is reached on all the data, the team transfers
the information to its Value Stream Management storyboard.
Identification of Waste
The process for mapping the future state takes place in three
stages:
Customer demand stage – understanding customer demand
for your products, including quality characteristics, lead
time, and price.
Flow stage – implementing continuous flow manufacturing
throughout your plant so that both internal and external
customers receive the fight product, at the right time, in the
right quantity.
Leveling stage – distributing work evenly, by volume and
variety, to reduce inventory and WIP and to allow smaller
orders by the customer.
Mapping The Future State
Premier Manufacturing Case Study – Step 6,
Begin the Future-State Map
Premiere Manufacturing has committed to producing to takt
time and has reached consensus with supervisors and workers.
The customer, Cord, Inc., has agreed to accept daily deliveries
of 504 units in reusable containers of 24 units each but would
like to work toward flexible amounts. Cord will continue to
send a 30-day forecast and will now begin to send orders daily.
Premiere will continue to provide its supplier with a monthly
forecast and weekly orders. Over the short term, Premiere has
agreed to continue receiving weekly deliveries from their
supplier, ABC, Inc., but ABC is willing to work toward
providing more frequent deliveries if necessary.
Mapping the Future State
Demand
• What is the demand? In other words, what is the takt time?
• Are you overproducing, underproducing, or meeting demand?
• Can you meet takt time (or pitch) with current production capabilities?
• Do you need buffer stock? Where? How much?
• Will you ship finished goods right after the final operation or use a finished-goods supermarket?
• What improvement tools will you use to improve our ability to fulfill demand?
Flow
• Where can you apply continuous flow?
• What level of flow do you need?
a. “Move on, make one” (one-piece flow)?
b. Small lots?
c. Cell design? What type?
• How will you control upstream production?
a. In-process supermarket?
b. Kanban?
c. FIFO?
• What other improvement methods will help to achieve continuous flow?
Leveling
• What types of kanban cards will you use?
• How will kanban cards be distributed?
• Where in the process will you schedule production requirements?
• Will you use a heijunka box?
• What will the runner’s route be?
Step 6: Customer Demand Worksheet
Step 6: Customer Demand Worksheet
(cont'd)
Step 6: Customer Demand Worksheet (cont'd)
Premiere Manufacturing Case Study – Step 6,
Demand Stage: Determining Takt Time and Pitch
Takt Time
During Step 4, the team determined the available production time as 460 minutes (510
total available minutes minus 50 minutes of regularly scheduled breaks) or 27,600
seconds.
The team also determined that their customer, Cord, requires 504 hoses daily (10,080
hoses per month over a 20-day shipping month).
They calculate the takt time as follows:
Takt time = 27,600 seconds (available production time) ÷ 504 hoses (required
daily production quantity)
Takt time = 55 seconds per hose
Pitch
Cord has requested shipments in containers that hold 24 units. The team calculates the
pitch as:
Pitch = 55 seconds (takt time) x 24 units per container (pack-out quantity)
Pitch = 1,320 seconds or 22 minutes
The team adds this information to their storyboard (see following page).
Determine Whether you Need Buffer and
Safety Inventories
Determined whether you need to establish buffer and safety
inventories by determining whether demand is stable and
whether you have the capacity and efficiencies to meet it.
Remember that you are improving the value stream to
ensure that you can meet customer demand now. You
cannot afford to wait until the future state is completed.
That could take six months – and very possibly, longer.
Buffer
Buffer Inventory
Inventory –– Finished
Finished goods
goods available
available to
to meet
meet customer
customer demand
demand when
when
customer
customer ordering
ordering patterns,
patterns, or
or takt
takt time,
time, varies.
varies.
Safety
Safety Inventory
Inventory –– Finished
Finished goods
goods available
available to
to meet
meet customer
customer demand
demand when
when
internal
internal constraints
constraints or
or inefficiencies
inefficiencies disrupt
disrupt process
process flow.
flow.
Premiere Manufacturing Case Study – Step 6, Demand
Stage: Establishing Buffer and Safety Inventories
The team decides to establish buffer and safety inventories with one day’s
worth of finished goods in each. The team adds the appropriate icons to the
future state map.
Finished-Goods Supermarket
Obstacle Solution
→ Autonomous maintenance
Operators 1 0 1 1 1
After reviewing the current state, going to the shop floor, and talking to operators and the
production supervisor, the team decides to set a total cycle time target of 150 seconds. Achieving
this total cycle time should require only 2.7 operators.
→ Quick changeover
→ TPM
→ Autonomous maintenance
→ Standardized work
Premiere Manufacturing Case Study – Step 6, Flow
Stage: Determining Which Improvement Methods to
Use
The team has already identified some improvements necessary for
achieving targets. Now it reconsiders its list of improvement methods
and draws icons at the appropriate places on the future-state map. Here
is the list of the improvement methods the team believes will be
necessary for creating and sustaining continuous flow:
1. 5S, TPM, autonomous maintenance, and QCO at machining
2. Standardized work at the crimping/testing/marking cell
3. QCO at the crimping/testing/marking cell
4. 5S at the crimping/testing/marking cell (to address problems with new
layout) and at shipping.
By identifying TPM as an improvement method, the core
implementation team in the premiere Manufacturing case study is not
calling for a true, plant wide TPM initiative, but an isolated application
of TPM methods.
Which Improvement Methods to Use
Focus on Leveling
Note: Even though Machining is not overproducing parts, a material push arrow is still drawn between the
operation and the in-process supermarket just downstream. This indicates that the production schedule in
Machining is not based strictly on what the Crimping/Testing/Marking cell has just pulled from the in-process
supermarket.
Mapping Material and Information Flow in
Machining
3. The Machining operator will be responsible for pulling containers from the
raw materials supermarket just upstream. To illustrate this plan, the team
draws a manual material pull icon and a supermarket parts icon between
the supermarket icon and the Machining icon.
4. The Machining operator will also be responsible for pulling signal kanbans
from raw material containers and placing the signal kanbans on a special
kanban post. The supplier’s truck driver will e responsible for collecting
the signal kanbans and taking them back to the supplier’s plant. To
illustrate this part of the plan, the team draws a kanban post icon between
the supermarket icon and the supplier truck icon. A manual communication
arrow and a signal kanban icon are drawn running from the kanban post
icon to the supplier icon.
Improvement Methods
The team decides to use Visual Controls, or Visual Workplace (VW), at the
crimping/testing/marking cell and the heijunka box. It adds these icons to
the map, along with lead times and total cycle time.
Create Kaizen Plans