Pile Intregity Test
Pile Intregity Test
Pile Intregity Test
Engineering
Introduction
Objective
Equipment
Methodology
Limitations
Table, Formula and Graph
Conclusion and Recommendation
References 3
Department of Civil
Introduction Engineering
• The pile integrity test (PIT) is a fast and reliable method mostly used for
• The pile integrity test (PIT) is a non destructive testing of deep foundation like
5
Department of Civil
Figure Engineering
10
Department of Civil
Equipments Engineering
• Hand Hammer
• Motion sensor
• Processing unit
• Accelometer
11
Procedure
The proposed methodology, built on the advanced signal processing and artificial
intelligence techniques, consists of three components:
1. signal preprocessing,
2. feature extraction, and
3. ELM-based defect detection
Department of Civil
Limitations Engineering
• Pile Integrity Test does not determine the load-bearing capacity of piles
and deep foundations.(6)
• This test does not work in piles with highly variable cross-sections.(6)
• At times it is hard to distinguish the soil response, and the (pile) toe
response.(6)
• Pile Integrity Test cannot be conducted over pile caps.(6)
• Pile Integrity Test as per published literature, piles with L/D ratio up to
30 give reasonably good results. (7)
13
Department of Civil
Limitations Engineering
14
Department of Civil
Possible Pile States Engineering
Large pile impedance change - reduction in cross section area, pile toe not detected /possible
pile damage, pile damage
3
Pile condition could not be stated (reasons: pile toe not detected, large and more impedance
changes, bad concrete on pile top (BTC) cracks on pile top)
4
15
Department of Civil
Formula Title Engineering
19
Graph Department of Civil
Engineering
For each tested pile v (t) graph is presented. Below is basic v (t) graph explanation:
Remarks:
• Impedance is defined with Z=EA/c, where E is elastic modulus, A is cross section area and c
wave speed. Wave speed higher than 4100 m/s, defined from known pile length, could be
result of pile toe damage or shorter pile.
• Results of PIT measurements on piles over foundations constructions are not interpretable.
Reasons could be:
- bad connection between foundation construction and pile head (bad concrete on the pile
head)
- more sequenced variables in Impedance (Z) in pile length.
• Testing piles must be prepared for PIT test as follow:
-bad concrete on the top (head) of pile has to be removed and pile head must be cleaned and
without cracks
-piles head should be accessible and above the water level.
24
Conclusion
• The PIT (Sonic Echo, Impulse Response & Ultra seismic) techniques in detecting the defects
of piles with pile cap [5]
• PITs are not capable of detecting minor defects of the pile with pile cap, although it still
detect major defects within these piles[5]
• Determine the exact location of pile defects or pile toe [8]
• Piles with highly variable cross-sections are difficult to analyze [8]
• It can identify discontinuities & defects, pile head defects, defects in middle of the pile
length or a reduced modulus of elasticity in the pile, pile base defect or a reduced modulus
of elasticity in the pile base zone and reduced modulus of elasticity in the pile head zone.[1]
• As the energy of the light impact is very small that the produced stress wave cannot travel a
long distance, the reflection signal can not be detected by a accelerometer when the pile is
very long.[3]
• The influence of surrounded soil on the test should also be considered for better results.[3]
Conclusion
• PIT can be successfully used during initial stages of a construction to assist engineers and
contractors with quality control/quality assurance needs. It is also a valuable tool to quickly
assess as-built foundation features. [2]
• The method offers several advantages over other testing methods, including other non-
destructive tests, for its rapid deployment, mobility, speed, and cost.[2]
• A large number of foundations can be tested in a short time using PIT, probably as many as
20 foundations in one day. It is capable of quickly producing information on the possible
presence of defects such as voids, breaks, discontinuities, or inclusions, and provides
estimates on pile length. [2]
• The successful application of the technology, however, requires understanding its limitations
as well, including operator’s familiarity with the system and experience with pile
foundations, applications to drilled shafts or auger-cast piles with potentially multiple or
large variation in cross-sections, L/D ratio limits, and only where accuracy on pile length
within 10%± is tolerable.[2]
Conclusion
• Where PIT is found to have limitations, other non-destructive testing methods that can
overcome certain PIT limitations maybe considered. Obviously, these tests involve a higher
level of sophistication, require more time to perform and are more costly. Discussions on
other possible testing techniques are beyond the focus of this document. [2]
• Identification of crack in pile will be the next study area of the PIT [1]
27
References Department of Civil
Engineering
1. (MLADEN COSIC, BORIS FOLIC and RADOMIR FOLIC (2014)“NUMERICAL SIMULATION OF THE PILE
INTEGRITY TEST ON DEFECTED PILES ”, University of Belgrade, Faculty of Civil Engineering ,Marka
Milanovića 17, 15300 Loznica, Serbia ..
5. Sabana Thilakna (2015)“Integrity Testing of Model Piles with Pile Cap”, International Symposium Non-
Destructive Testing in Civil Engineering (NDT-CE) September 15 - 17, 2015, Berlin, Germany
6. Ni, S. H., Charng, J. J., and Lo, K. F. (2007). “Nondestructive evaluation of in-isolation pile shaft
integrity by Wigner-Ville distribution.” Journal of Mechanics, 23(1), 15−21
29
Department of Civil
Engineering
30