Project Control
Project Control
A Managerial Approach
Project Control
Project Control
Control is the last element in the
implementation cycle of planning-
monitoring-controlling
Control is focused on three elements of a
project
Performance
Cost
Time
Chapter 11-1
Controlling Performance
There are several things that can cause a
project’s performance to require control:
Unexpected technical problems arise
Insufficient resources are available when needed
Insurmountable technical difficulties are present
Quality or reliability problems occur
Client requires changes in specifications
Interfunctional complications arise
Technological breakthroughs affect the project
Chapter 11-2
Controlling Cost
Chapter 11-3
Controlling Time
There are several things that can cause a project’s
schedule to require control:
Technical difficulties took longer than planned to resolve
Initial time estimates were optimistic
Task sequencing was incorrect
Required inputs of material, personnel, or equipment
were unavailable when needed
Necessary preceding tasks were incomplete
Customer generated change orders required rework
Governmental regulations were altered
Chapter 11-4
Purposes of Control
Chapter 11-6
Human Resource Control
Stewardship of human resources requires
controlling and maintaining the growth and
development of people
Projects provide fertile ground for cultivating
people
Because projects are unique, it is possible
for people working on projects to gain a
wide range of experience in a reasonably
short period of time
Chapter 11-7
Financial Resource Control
Chapter 11-8
Financial Resource Control
Representation of the accounting/controlling
function on the project team is mandatory
The parent organization is responsible for the
conservation and proper use of resources owned
by the client or charged to the client
Due diligence requires that the organization
proposing a project conduct a reasonable
investigation, verification, and disclosure of all
material facts relevant to the firm’s ability to
conduct the project
Chapter 11-9
Three Types of Control
Processes
Chapter 11-11
Go/No-go Controls
Take the form of testing to see if some specific
precondition has been met
Most of the control in project management falls
into this category
This type of control can be used on almost every
aspect of a project
Must exercise judgment in the use of go/no-go
controls
Go/no-go controls operate only when and if the
controller uses them
Chapter 11-12
Information Requirements
for Go/no-go Controls
Chapter 11-13
Postcontrol
Postcontrols are applied after the fact
Directed toward improving the chances for future
projects to meet their goals
It is applied through a relatively formal document
that contains four distinct sections:
The project objectives
Milestones, checkpoints, and budgets
The final report on project
Recommendations for performance and process
improvement
Chapter 11-14
Characteristics of a
Control System
A good control system:
Should be flexible
Should be cost effective
Must be truly useful
Must satisfy the real needs of the project
Must operate in a timely manner
Sensors and monitors should be sufficiently accurate and
precise to control the project within the limits that are
functional for the client and parent organization
Chapter 11-15
Characteristics of a
Control System
Chapter 11-16
Control Systems
All control systems use feedback as a control process
The control of performance, cost, and time usually
require different input data:
Performance - engineering change notices, test results,
quality checks, rework tickets, scrap rates
Cost - budgets to actual cash flows, purchase orders,
absenteeism, income reports, labor hour charges,
accounting variance reports
Schedule - benchmark reports, status reports, PERT/CPM
networks, earned value graphs, Gantt charts, WBS, and
action plans
Chapter 11-17
Control Tools
Some of the most important tools available for the
project manager to use in controlling the project
are variance analysis and trend projection
A budget plan or expected growth curve of time or
cost for a certain task is plotted
Actual values are plotted as a dashed line as the
work is actually finished
At each point in time a new projection from the
actual data is used to forecast what will occur in
the future
Chapter 11-18
Control Tools
Trend projection
Chapter 11-19
Critical Ratio Control
Charts
Chapter 11-20
Critical Ratio
Task Actual Scheduled Budgeted Actual Critcal
Number Progress Progress Cost Cost Ratio
1 (2 / 3) X (6 / 4) = 1.0
2 (2 / 3) X (6 / 6) = .67
3 (3 / 3) X (4 / 6) = .67
4 (3 / 2) X (6 / 6) = 1.5
5 (3 / 3) X (6 / 4) = 1.5
Chapter 11-21
Critical Ratio
Chapter 11-22
Benchmarking
A recent addition to the arsenal of of project
control tools is benchmarking
Benchmarking makes comparisons to “best in
class” practices across organizations
Some successful organizations have been
benchmarked on their best practices and key
success factors for projects being conducted
in functional organizations
Chapter 11-23
Best Practices and Keys to
Success
There were four major areas found to help
projects in functional organizations:
Promoting the benefits of project management
Personnel pay for project management skills
and high risk projects through bonuses, stock
options, and other incentives
Methodology
Results of project management
Chapter 11-24
Control as a Function of
Management
The purpose of controlling is always the same: to
bring the actual schedule, budget, and
deliverables of the project into reasonably close
congruence with the planned schedule, budget,
and deliverables
Chapter 11-26
Go/No-go Controls
Response to go/no-go controls tends to be
neutral or negative
“Barely good enough” results are just as
acceptable as “perfect” results
The system makes it difficult for the worker to
take pride in high quality work because the
system does not recognize gradations of quality
The fact that this kind of control emphasizes
“good enough” performance is no excuse for the
nonchalant application of careless standards
Chapter 11-27
Postcontrols
Postcontrols are seen as much the same as a
report card
They may serve as the basis for reward or
punishment, but they are received too late to
change current performance
Because postcontrols are placed on the process of
conducting a project, they may be applied to such
areas as: communication, cooperation, quality of
project management, and the nature of interaction
with the client
Chapter 11-28
Balance in a Control
System
General features of a balanced control system:
Built with cognizance of the fact that investment in
control is subject to sharply diminishing returns
Recognizes that as control increases past some point,
innovative activity is more and more damped, and then
finally shut off completely
Directed toward the correction of error rather than toward
punishment
Exerts control only to the degree required to achieve its
objectives
Utilizes the lowest degree of hassle consistent with
accomplishing its goals Chapter 11-29
Control of Creative
Activities
The more creativity involved, the greater the degree of
uncertainty surrounding outcomes
Too much control tends to inhibit creativity
Control is not necessarily the enemy of creativity, nor does
creative activity imply complete uncertainty of
There are three general approaches to control creative
projects:
Progress review
Personnel reassignment
Control of input resources
Chapter 11-30
Progress Review
The progress review focuses on the process of
reaching outcomes rather than on the outcomes
per se
The process is controllable even if the precise
results are not
Control should be instituted at each project
milestone
The object of control is to ensure that the
research design is sound and is being carried out
as planned or amended
Chapter 11-31
Personnel Reassignment
This type of control is straightforward -
individuals who are productive are kept
Those who are not, are moved to other jobs or
to other organizations
While it is not difficult to identify those who fall
in the top and bottom quartiles, it is usually
quite hard to make clear distinctions between
the people in the middle quartiles
Chapter 11-32
Control of Input Resources
Chapter 11-33
Control of Change and
Scope Creep
Coping with changes and changing priorities is
perceived as the most important single problem
facing the project manager
The most common changes are due to the natural
tendency of the client and project team members to
try to improve the product or service
The later these changes are made in the project, the
more difficult and costly they are to complete
Without control, a continuing accumulation of little
changes can have a major negative impact on the
project’s schedule and cost Chapter 11-34
Control of Change and
Scope Creep
The project manager’s best hope is to control the
process by which change is introduced and
accomplished
This can be done with a formal change control system
that is able to:
Review all requested changes and identify all task impacts
Translate those impacts into project performance, cost, and
schedule
Evaluate the benefits and costs of the requested changes
Accept or reject the changes and communicate to all concerned
parties
Ensure that changes are implemented properly
Chapter 11-35
Effective Change Control
Procedure
Questions?
Chapter 11-41