PD03 Efficient Project Execution
PD03 Efficient Project Execution
Operationalization of PD03.421-PD03.64
27.11.2015
Classification: Internal
2013-09-25
PD03: A-standard / C&L execution of all meetings
Internal
PD03: Efficient project execution
- execution phase
LCI 2
LCI 1
LCI 3
Equinor Perform kick-off
Clarify project
meeting with
deliveries
executor
R-105730
R-105518
System drawings
IFC RFC
Utførende
R-105545
R-105959
Check of
Design- and installation RFO As-Built
construction preparations
review(s) R-105539 R-100894 R-35166
R-105545 Check of
installation
preparations
Ready for
R-105539
installation
Design freeze R-105539
R-105545
Design freeze
R-105545
Design freeze
R-105545
The following milestones shall be used - if not agreed otherwise:
LCI 0 12 weeks after contract assignment or
covered by frame agreement
3 Classification: Internal
Kick-off meeting with executor (R-105518 – conduct kick-off meeting)
Purpose
Executor/Vendor shall presesent its understanding of the task / Agreement.
From ARIS:
A meeting shall be conducted to go through the project. Executor shall present the scope of work.
The participant list shall be based on the Involvement Matrix. Meeting minutes shall be written
by a company representative.
Agenda
Executor presents its understanding of the task/Agreement
• Background, purpose
• Presentation pr. discipline of specific work tasks in engineering, together with clarifications of
uncertainties.
• Procurement strategy
• Project risik (preferably from PIMS)
• Live plan for execution of the task/Agreement, GL0587 Responsible for conducting the meeting
• Cost estimate (hours pr phase in live plan)
• Project M5 established for M&M Agreements (Equinor responsibility) Project manager Equinor
The Company presents how it plans use the organization for follow up and involvement in the
project (involvement matrix)
Participants
Desired result Equinor:
- Project manager Equinor’s team
Common understanding of tasks and project execution.
Executor:
Plan with milestones for execution of the Agreement. - Project manager Executor’s team
C
4 lassification: Internal
Clarify project deliveries (R-105730 – Clarify project deliveries)
Purpose
The meeting shall be held shortly (e.g. 2-6 weeks) after kick-off meeting with executor to ensure
common understanding of the project deliveries for engineering and completion.
The Executor shall use Equinor’s systems to show status (e.g. STID / ProCoSys, SPIR) Projects
with several part-handovers (RFOCs): As-Built shall be clarified - common, or after each part-
handover.
5 Classification: Internal
System drawings IFC (R-105545)
Purpose
System design, drawings to be prepared for status IFC:
1. Piping and instrument diagram (P&ID)
2. Cause & effect (C&E)
3. Fire protection data sheet (FPDS)
4. System control diagram (SCD)
5. Area and System Duct & and Instrumentation Diagrams (D&ID)
Responsible
Project manager Executor
Desired result
Participants, ref. Involvement matrix
IFC revision for system design documents/drawings available in STID prior design-construction Equinor:
review. - Project manager Equinor’s team
Executor:
- Project manager Executor’s team
6Classification: Internal
Design / construction review (R-105545)
Purpose
A multidiscipline review of design with focus on customer and regulatory requirements.
The result of the review is a design that i safe, user-friendly and fit-for-purpose / according to
customer needs (within SOW)
Agenda
Expectations to contents:
• Presentation of design
• Presentation of layout
• List of relevant guidewords
• Meeting memo with actions and presentations attached.
• This should be a meeting with focus on the disciplines and not a status meeting (progress, time
consumption, plan, etc. is not applicable)
Responsible
Project manager Executor
Classification:
7
2014- Internal
Milestone
Design freeze (R-105545)
Purpose
Freeze of design to be carried out at the latest one week after design / construction review.
Freeze of:
- Document list
- Tag. list
- System design, drawings to be prepared for status IFC (without «HOLD»)
1. Piping and instrument diagram (P&ID)
2. Cause & effect (C&E)
3. Fire protection data sheet (FPDS)
4. System control diagram (SCD)
5. Area and System Duct & and Instrumentation Diagrams (D&ID)
This doesn’t have to be a meeting, but a milestone where Equinor / conctractor agrees upon
design freeze.
There may be several Design Freeze in a project. This depends on the installation activities in the
project.
This we build.
Desired result Now it’s Team Pursuit to the goal line!
Responsible
• Final TAG list
• Equipment to be delivered with standard documentation Project manager Executor
• Equipment that is not delivered with standard documentation with LCI milestones in
accordance with TR2381 and GL0587
• Final document list over documentation that shall be delivered in the project
• Freeze of 3D PDMS design Participants
• Freeze of safety critical documentation
• Documentation for procurement ready Equinor:
• Documentation for maintenance engineering ready for RMM/MA (Equinor) - MOD normally - Project manager Equinor’s team
use M5 notification for this. «Brownfield» use ProCoSys.
• Documentation for other equipment acc. agreed delivery schedule for the equipment Executor:
- Project manager Executor’s team
Classification:
8 Internal
Milestone
Check of installation preparations (R-105539 - Check of installation preparations)
Purpose
This is the last check in the engineering phase to ensure that everything is at place before Action list (suggestion)
installation can start. Review to be held 3-6 weeks before installation start.
QC check list from Project enginer shall be available on teamsite two days before the review.
If there is any remaining tasks, a action list is prepared with spesific actions with responsible
person for closing the action, and a clear deadline. See checklist . No Action Deadline Responsible
This can be performed using Concurrent method, ref. «R-105531 – Use concurrent method».
1 Comm. procedure signed 13.04.2015
2 PM completed 04.05.2015
Classification:
9 Internal
Milestone
Ready for installation milestone (TR2381)
Purpose
Action list (suggestion)
All actions from «Check of installation preparations” are closed and we are ready for installation.
It's a risk-based assessment of whether the project is ready to install.
No Action Deadline Responsible
2 PM completed 04.05.2015
Responsible
Project manager Executor
Classification:
10 Internal
Milestone
RFC(Ready for commissioning) / RFO (Ready For Operation)
Purpose
Completion are important activities for planning in the project. Date for mechanical completion
(RFC) and handover to operations (RFO) are specific milestones.
Completion contains the following elements:
• Mechanical completion (executor), and handover to Commissioning – RFCC
• Commissioning activities (Executor: Equinor and/or contractor)
• Handover from the project/commissoning to Equinor operations – RFOC
When RFOC is signed, Equinor operations has taken over the responsibility for the
equipment/system and can proceed with preparations for start-up.
RFOC: Hand over from the project/commissioning to Equinor Operations are performed in
accordance with PD03.64. by preparing and signing RFOC. This is normally prepared pr system.
Requirements for the RFOC content are given in R-100831. No A-punch shall be open when Participants, ref involvement matrix
issuing RFOC. Commissioning activities that cannot be performed before start-up shall be
registered as remaining punch items. Equinor:
- Project manager Equinor’s team
Ready for safe and efficient start-up of system and equipment
Utførende:
- Project manager Executor’s team
Classification:
11 Internal
Milestone
As-Built
Purpose
All documentation and TAGs shall be in As-built status , and reserved TAGs/documents for the
project shall be «cleaned». As-Built according to TR2381
Projects with several part hand-over: As-Built shall be clarified in the «clarify project As-Built
deliveries meeting» with regards to how this shall be carried out, collectively at the end, or at each
part hand-over.
Checklist
1. PDMS
2. TAG
3. Documents
4. Punch
5. MA
6. PM program
7. LOOP/ELE Responsible
Ref: OM06.16 – Follow up and confirm LCI update to as-built Project manager Equinor
Prosject manager Equinor is responsible for finalizing all deliveries before completing the
final report.
Classification:
12 Internal