Pert and CPM: Dr. Vineet Tiwari
Pert and CPM: Dr. Vineet Tiwari
Submitted to:
Dr. Vineet Tiwari
Dept. of Management
Studies
IIIT, Allahabad
Submitted by:
Kuldeep Singh & Mohit Kumar
Research Scholars
Dept. of Management
Studies
IIIT, Allahabad
Project Management
Project: Consist of interrelated activities
Executed in a certain order
Before entire task is completed
In the form of a
Network diagram
Which helps to
Which provide
Planning:
• dividing the project in to distinct activities
• Estimating the time requirement for each activity
• Establishing precedence relationship among the activities
• Construction of the arrow diagram
Scheduling:
• Determine the start and end time for each and every activity
Controlling:
• Use the arrow diagram and time chart for continuous monitoring and process
reporting
Difference Between PERT and CPM
PERT CPM
• Used for non repetitive jobs. Exp. Research • Used for repetitive jobs. Exp. Building
activities Construction
• Probabilistic Model (Based on β • Deterministic Model
distribution)
• Three time we considered
• Timing always fixed and known
• Optimistic time • Which is shown by te
• Most likely time • It is activity oriented, which required
• Pessimistic time resources
• Mean expected time (te)
• te=
• Variance = σ2 =( )2
• it is event oriented, which does not
required resources
• And could be start of an activity, end of an
activity, non completion of an activity etc.
1 a 2
c
3
𝐸 0 1 b,5 5
3
5
c,4
10
4
Problem 1. Some Info is given regarding a project
Activity Immediate Precedence Duration (in months)
A - 2
B - 5
C - 4
D B 5
E A 7
F A 3
G B 3
H C,D 6
I C,D 2
J E 5
K F,G,H 4
L F,G,H 3
M I 12
N J,K 8
• On the basis of above problem
1. Construct the CPM network
2. Determine the Critical Path and Project Completion Time
3. Compute Total Floats and Free Floats for Non critical activities
SOLUTION of Prob. 1
8 15 20
2 9 20
2 E,7 5 J,5
8
N,8
0 A,2
F,3
K,4
5
0
5
1 B,5
3 G,3 6 L,3 9
28
16
28
16
C,4 D,5 M,12
H,6
4 i,2 7
10 16 Fig.1 CPM Diagram of Problem 1
10 12 Critical Path Shown BY Dark Line
Nodes are shown by Circle
Critical Path = 1 – 3 – 4 – 6 – 8 – 9
And in Square Box =
B–D–H–K-N
Project Completion Time = 5+5+6+4+8 = 28 Days
Column
1
2 3 4 5 6 7 8 9 10 11
Activity Duration ES EF LS LF Total
Float
Head Event Slack
L - E @ Head Event
Free Float
7–8
Tail Event Slack
L - E @ Tail Event
Independent Float
9 – 10
5–3
(A) 1-2 2 0 2 6 8 6 6 0 0 0
(B) 1-3 5 0 5 0 5 0 0 0 0 0
(C) 1-4 4 0 4 6 10 6 0 6 0 6
(D) 3-4 5 5 10 5 10 0 0 0 0 0
(E) 2-5 7 2 9 8 15 6 6 0 6 -6
(F) 2-6 3 2 5 13 16 11 0 11 6 5
(G) 3-6 3 5 8 13 16 8 0 8 0 8
(H) 4-6 6 10 16 10 16 0 0 0 0 0
(I) 4-7 2 10 12 14 16 4 4 0 0 0
(J) 5-8 5 9 14 15 20 6 0 6 6 0
(K) 6-8 4 16 20 16 20 0 0 0 0 0
(L) 6-9 3 16 19 25 28 9 0 9 0 9
(M) 7-9 12 12 24 16 28 4 0 4 4 0
(N) 8-9 8 20 28 20 28 0 0 0 0 0
PERT and CPM
CPM: Deterministic
PERT: Probabilistic (have three time estimates)
1. Optimistic time
2. Most likely time
3. Pessimistic time
Problem 2. Some Info is given regarding a project
A - 5 6 7 6 0.11
B - 1 3 5 3 0.44
C - 1 4 7 4 1.00
D A 1 2 3 2 0.11
E B 1 2 9 3 1.78
F C 1 5 9 5 1.00
G C 2 2 8 3 1.00
H E,F 4 4 10 5 1.00
I D 2 5 8 5 1.00
J H,G 2 2 8 3 1.00
SOLUTION of Prob. 2 : Critical Path = 1 – 4 – 6 – 7 – 8
C–F–H–J
10 12 Project Completion Time = 4+5+5+3 = 17 Days
6 8
2 D,2 5
i, 5
0 A,6
0 6
0
3
1 B,3
3 E,3 6 8
17
9
17
9
C,4 J,3
F,5
H,5
4 G,3 7
4 14 Fig.2 PERT Diagram of Problem 2
4 14 Critical Path Shown BY Dark Line
Nodes are shown by Circle
And in Square Box =
Solution of Problem 2 (iii) :