Contract
Contract
1. Measurement Contract
• Item rate
- Owner quotes quantity and unit
- Tenderer- rate for each item
- Payment based on actual measurement
• Percentage contract
- The client’s department draws up the schedule of items according to the
description
- Items sanctioned in the estimate with
quantities
- Rates, units and amounts shown therein.
Advantages Disadvantages
• Works can start after finalizing the • Can not predict the final value of the
initial design and BOQ. project.
• Can reduce the design cost. • Delays in contractor’s payments
• High possibility to do value engineering. (assessment of the measurements takes
time)
• Client’s risk is comparatively high
• Prices (unit rates) will be competitive
• Controlling and reporting will be a
• Contractor’s risk is comparatively low
difficult task
• A high number of consultant team may
require for handling the project (Ex: for
remeasuring)
LUMP – SUM CONTRACT
2. Lump – sum contract
- A lump sum contract may be entered into for
procuring a construction work such as ground
water pipeline installation, the quantities of
which are difficult to measure or a construction
work such as superstructure of a bridge, the
quantities of which can be measured.
- cost of entire work quoted based on scope of work, planning,
designing, working drawings all drawings, specifications
frozen before inviting tender—
- owners knows total cost of work in beginning,
- no change in scope can be made,
- if made additional payment made
Advantages Disadvantages
- Reduced total time during the contractual - A higher cost is assumed due to the higher
process by having just one process instead of risk that comes with total responsibility,
two separate ones. This does not necessarily there is less information to prepare
imply less construction time. proposals and therefore bidders assume
more risks.
- A seemingly “lower cost” when integrating - The typical way to counter the increased
“all” the elements under one provider. risk is by increasing the price.