The NPV Investment Evaluation Process
Step 1 - Calculate depreciation
Step 2 - Calculate any gain or loss on sale
Step 3 - Calculate taxable income, i.e. profit or loss
Step 4 – Calculate the tax item, i.e. tax bill or tax rebate
Step 5 - Calculate net cash-flows
Step 6 - Discount net cash-flows
Step 7 – Conclusion: NPV positive accept,
negative reject
Net Present Value
Example
Purchase price of asset $42 000.
Salvage value $1,000 at end of Year 3.
Operating net cash-inflows: Year 1 $31 000
Year 2 $29 000
Year 3 $27 000.
Feasibility study cost $4,000 – yet to be paid.
Warehouse previously rented out for $8,000 p.a. will be used for the
project.
New technician will replace existing technician.
Existing technician’s salary = $65 000 p.a.
New technician’s salary = $70 000 p.a.
Old machine can be sold for $2,500; it’s book value is $3,000.
Tax rate is 30%.
Depreciation is straight-line.
Required rate of return is 12% p.a.
Net Present Value
Step 1: Depreciation p.a.
Depreciation p.a. = cost of asset/n (no. of years)
Depreciation = $42,000/3 = $14,000 p.a.
Step 2: Gain or Loss on Sale
Gain/loss on sale = sale price (salvage value of asset) less book value of
assett
Expenses
cash-outflow due to expenditures of production, etc.
expenses represent a tax saving (they are tax deductible, therefore they
reduce tax payable (they provide a tax-shield))
net cash-outflow after-tax equals: Exp. – (Exp. * tc ) or Exp.* ( 1 - tc)
Net Present Value
One-Step Process
Depreciation Tax-Shield
Depreciation is a non-cash expense that is an allowable tax deduction (it
provides a tax-shield). Thus it reduces the tax payable by: Depreciation * (tc)
This represents a cash-inflow (a tax-rebate).
Net Present Value
One-Step Process
Book Gain or Loss on Disposal
salvage value (SV) is the sale price (market value) received on disposal of
an asset
assets have a book value (BV), which is the purchase price less
accumulated depreciation
if SV > BV we have a book gain on disposal of the asset and a taxable
profit arises
Tax on profit = book gain * tc
This leads to a tax-liability (a cash-outflow)
The net after-tax cash-inflow from disposal will be SV less (book gain * tc)
If two projects are mutually exclusive they are competing projects and a
choice between the two projects must be made.
Evaluation of the projects is complicated if they differ in life span i.e. they are
each over a different number of years.
If two projects have different lifespans we cannot base a NPV analysis of the
two projects simply on which project has the higher NPV.
A common base is required for comparison.
Equivalent Annual Annuities
Evaluating Projects With Different Lifespans
We select the project with the lowest Equivalent Annual Cost (EAC) if the
cash-flows are based on costs (i.e. net cash-outflows)
Equivalent Annual Annuities
Evaluating Projects With Different Lifespans
To calculate the equivalent annual annuity (EAA) of a project, asset, or
investment:
1. Calculate the NPV of each project over one life - as if it were "one-off“; then
2. Convert the NPV of each project into an equivalent annuity for the life of each
project, i.e. convert the NPV into a series of annual payments or annuity
payments. To do this we must find the unknown PMT for the project using the
PV of an ordinary annuity formula.
Equivalent Annual Annuities
Evaluating Projects With Different Lifespans
Suppose our firm has to choose between two machines that differ in terms of
economic life and capacity. Our required return is 14% p.a. The after-tax net
cash-flows for each machine are as follows:
NPV2 = $1,664.01
1 (1 0.14) 6
$45,000 $12,000 $45,000 $12,0003.888 $45,000 $46,664.01 $1,664.01
0.14
Does this mean Machine 2 is better? No, the NPVs can’t be compared.
We must take the analysis one step further and calculate each project’s EAA.
Equivalent Annual Annuities
Evaluating Projects With Different Lifespans
Step 2: We assume each project can be replaced an infinite number of times
in the future, and then convert each NPV to its equivalent annuity.
The projects’ EAAs can be compared to determine which is the best project.
The EAA is the annuity amount (PMT) from the present value of an ordinary
annuity formula:
1 1 r n
PV PMT
r
EAA
Equivalent Annual Annuities
Evaluating Projects With Different Lifespans
EAA1 = $617.08
1 (1 0.14) 3 $1,432.64
$1,432.64 PMT $1,432.64 PMT 2.322 PMT $617.00
0.14 2.322
EAA2 = $427.91
1 (1 0.14) 6 $1,664.01
$1,664.01 PMT $1,664.01 PMT 3.888 PMT $427.76
0.14 3.888
We’ve reduced a problem with different time horizons to a choice between two
annuities
Choose Machine 1
Capital Budgeting And Inflation
In project evaluation not adjusting for inflation may result in errors in
capital budgeting decisions.
Depreciation p.a. on a productive asset is calculated based on historical cost, i.e. based
on the cost of the asset at the time it was bought, and not on replacement cost, i.e. not
on the cost of the asset when it has to be replaced in the future.
As depreciation is based on historical cost inflation erodes the real value of any
depreciation tax deduction and therefore discourages capital investment in an
inflationary period.
If we have inflation then the further into the future is the depreciation claim the lower is
its real present value (time value of money concept).
To get the effective write-off of an asset we work out at the inflation rate the sum of the
present value of the depreciation deductions and divide this by the cost of the asset. To
do this we use the formula:
Σ depreciation p.a.(1+r)-n
cost of asset
Note: here r is the inflation rate (and not the required rate of return/discount rate)
Capital Budgeting And Inflation
Depreciation And Inflation
Σ PV0 = $19,963.00*1
1 1 r n
PV PMT
r
So, the PV0 of the sum of the annual depreciation expenses is:
1 1.085
PV0 $5,000
0 .8
PV0 $5,0003.9927
PV0 $19,963.00
Capital Rationing
Capital Rationing – where a firm limits the total amount of funds to be
invested in projects.
Therefore, even though certain projects may have a positive NPV they could
be rejected due to capital (financing) constraints.
Hard Capital Rationing
Imposed by Capital Markets - markets will not provide sufficient finance for a
project at an acceptable cost, i.e. markets will not provide financing for the
project at a rate of interest that will give the project a positive NPV. For
example, management may base its project evaluation on a required rate of
return of 7% p.a., and using this rate the project has a positive NPV.
However, the market (e.g. banks, shareholders) believe the project is of
higher risk and will require a rate of return of, say, 10% p.a., and using 10%
p.a. as the discount rate for the project may lead to the project having a
negative NPV.
Soft Capital Rationing
Imposed by upper management to ensure subsidiaries prioritise investments.
Ensures discipline by lower level management – subsidiaries to only invest in
highest NPV projects.
Capital Rationing
Profitability Index (PI) (Benefit-Cost Ratio)
A project’s Profitability Index (PI) measures the return of the project relative
to its cost.
Profitability Index (PI) = Present Value/Cost
or
(NPV+Cost)/Cost
PI Decision Criteria
If PI > 1 = Accept the project (NPV must be positive).
If PI < 1 = Reject the project (NPV must be negative).
Capital Rationing
Profitability Index (PI) (Benefit-Cost Ratio)
Note. PI = (NPV+Cost)/Cost
Cost of Capital = 12%
Combined NPV B & C = $31.4
As compared to A alone = $23.7
Capital Rationing
Profitability Index (PI) (Benefit-Cost Ratio)
PIA = ($23.7m + $15m)/$15m = 2.583
PI Decision Rule
Maximise the total NPV subject to the capital constraint (i.e. subject to the
financing limit).
Use PI to rank projects as PI measures return relative to cost.
In the above example, we would choose both Projects B and C as they both
have a higher PI than Project A and together B and C meet the capital
constraint of $15million.