Pipeline Damage by Anchor Dragging
Pipeline Damage by Anchor Dragging
damaging a Pipeline
(15 June 2017)
• OOW and a lookout were kept on a watch for constant inspection of anchor cable.
• Weather conditions normal on 24th June night with a North Easterly 20 kts wind.
• Wind speed gradually increased next morning reaching 30 knots by afternoon.
• At 1300 on 25th June, a worried master ordered to pay out one more shackle of cable.
• Young Lady’s logbook recorded “due to the gale, anchor cable slacked 1shackle, now 8
shackles on deck’’.
• By 2000 hrs, wind went up to 40 kts, backing to North West and vessel started rolling and
pitching and yawing heavily in a swell
• Position was constantly monitored by DGPS Anchor Alarm and visual bearings.
• Positions were regularly plotted on chart to confirm that ship was not dragging.
.
Anchor Dragging
Upon reaching bridge, Master fixed the the ship and confirmed that ship was dragging anchor in Southerly direction.
Anchor Dragging
• At 2216 hrs, engine room was ordered to
keep engines ready. But by this time, Young
Lady had already dragged anchor by 8
cables at 3 knts.
• Anchor party of c/o and two seamen was
ordered to weigh port anchor.
• Chief officer reported excessive strain on
cable and heaving rate was 9 mins per
shackle as against normal rate of 3 mins per
shackle).
• At 2221 hrs, the Master reported anchor
dragging to the Tees Port Control via VHF.
• At 2223 hrs, Engines to ‘dead slow ahead’.
• The ship’s head was yawing between 068°
and 320° and ship was dragging southwards.
• At 2228 hrs, Engines put to “slow ahead”
• At 2233 hrs, rate of drift reduced.
• At 2235 hrs, engines stopped and ship began to drag.
• Engines were ordered Ahead to stop ships drift.
• By 2245 hrs, vessel dragged a distance of 1.3 Nm and was
just 2 cables north of the CATS Gas Pipeline.
• At 2250 hrs, Engines were ordered ‘half ahead’.
YOUNG LADY :
• Failure of port hydraulic windlass brakes.
• Damage to the port windlass hydraulic motor unit
• Damage to motor casing.
CATS PIPELINE :
• The pipeline was lifted 1.5m, moved laterally at the point of contact by 6m in a
south- easterly direction. The concrete protection was removed at the point of
contact, and impact damage was identified on the steel pipe.
• However, no major leakages were reported.
Consequences of Pipeline Damage
Navigation
• The anchored position allowed by the port authorities was close to the pipeline area.
• Excessive delay in slipping port anchor which could have resulted in more serious damage to pipeline.
Anchor-work
• For existing weather conditions, paying out of 7 shackles was inadequate.
• Master was not aware of the windlass’s design limitations due to unavailability of anchoring equipment data,.
• By 2000, wind had increased to 40 knots but engines started only at 2216 hrs when ship had already begun to drag.
• Inadequate and undecided use of engines to ease weight on cable.
• Attempting to weigh anchor in spite of excess load on cable which finally resulted in damage to the windlass.
•
Weather awareness
• In spite of the awareness about the deteriorating weather, the Master chose to remain at that anchorage.
• By next day morning, wind strength had increased from 20 to 30 knots, but little attention was paid to the
deteriorating wx.
Corrective Actions Taken TAKEN
BLENHEIM SHIPPING UK LTD :
• Provided training for its masters on the anchorage procedures
• Engaged an independent consultant to conduct a navigation audit within its fleet