Project Management 2022
Project Management 2022
1
PROJECT
2
PROJECT
4
PROJECT
CHARACTERISITICS
Progressive Elaboration:
Scope is high level & broadly defined in beginning
It becomes more explicit & detailed as project progresses
and develops better understanding of project objectives
and deliverables
Critical to project success
5
PROJECTS Vs OPERATIONS
6
PROJECTS Vs OPERATIONS
Commonality:
Performed by people
Limited by resource constraints
Planned, executed, monitored and controlled
Performed to achieve organizational objectives / strategic
plans
7
PROJECTS Vs OPERATIONS
PROJECTS OPERATIONS
Temporary & unique Ongoing & repetitive
Purpose is to attain Purposeis to sustain
its objectives & then the business
terminate
Concludes when its Adoptsnew set of
specified objectives objectives and the
have been achieved work continues
8
PROJECTS Vs OPERATIONS
???
10
WHY PROJECTS ??
11
PROJECTS
12
PROJECTS
Worldwide concern:
Only 34% of all projects undertaken globally succeed.
Because of poor and inefficient project management.
Project management training can address the concern.
13
PROJECT MANAGEMENT
(PM)
Application of knowledge, skills, tools
and techniques to project activities to
meet the project requirements.
Application and integration of 47
logically grouped PM processes,
comprising 5 process groups:
Initiation
Planning
Execution
Monitoring and control
closing
14
GIST OF PM
Identifying requirements.
Addressing the various needs, concerns & expectations
of the stakeholders – as the project is planned and
executed.
Balancing of competing constraints:
Scope -- Schedule
Budget -- Quality
Resources-- Risk
15
TRIPLE CONSTRAINTS
TIME COST
SCOPE
16
PM DIMENSIONS
TIME
SCOPE COST
RISK QUALITY
CUSTOMER
SATISFACTION
17
PM CONTEXT
Strategic Plan
↓
Portfolio
↓
Program
↓
Project
↓
Sub-projects
18
ORGANIZATIONAL
STRUCTURE
Functional organization
Matrix organization
Weak matrix
Balanced matrix
Strong matrix
Projectized organization
19
PROJECT MANAGER
(OWNER)
Person assigned by performing organization to
achieve project objectives.
Report to functional manager or PMO/CEO
depending on the organizational structure.
Effective project manager:
Area specific skills & knowledge
General management proficiencies
Trained
Perform by applying PM skills
Personal effectiveness, attitude, core personality
traits
20
PROJECT MANAGEMENT
OFFICE
An organizational unit to centralize
and coordinate management of
projects under its domain.
Functions:
Identify & allocating resources for various
projects
Standardized policies, procedures,
templates and other shared documents
Identify & deploy PM methodology, best
practices and standards
Training & mentoring
21
PROJECT MANAGEMENT
OFFICE
Functions (cont’d):
Central coordination of communication across
all projects
Central monitoring of all projects, time lines
and budget
Maintaining organizational projects board &
library
Authority to recommend or terminate projects
Involved in selection, management and re-
deployment of shared/dedicated project staff
Finds out opportunities to better achieve
business objectives
22
PROJECT MANAGER Vs PMO
Focuses on specified Manages objectives
project objectives for all projects in its
domain
Controls Optimizes use of
assigned
project resources shared resources
across all projects
Manages constraints Manages constraints
of the assigned of all projects at
project. organizational level.
23
ENTERPRISE ENVIRONMENTAL
FACTORS
EEF
All external and internal factors that surrounds the
project.
Enhance or constraint PM options.
Positive or negative influence on the outcome.
Org culture, structure & processes, market conditions,
govt / industry standards etc.
24
ENTERPRISE ENVIRONMENTAL
FACTORS
25
ORGANIZATIONAL PROCESS
ASSETS
Helps throughout the project
Project management policy
Standards, policies, procedures, processes
Quality consciousness
Organizational culture
Organizational ethics
Corporate knowledgebase
Historic information from previous projects
Lessons learned from previous projects
Project files, reports, library
Corporate branding
Patents, licenses, copy rights etc.
26
PM Basics
EEF
OPA (Organizational Process Assets)
ICC (CCB, CAB)
Gold Plating: giving something extra than
scope.
27
PROJECT LIFE CYCLE (PLC)
High
Amount at stake
Low
Time
Project Life Cycle
30
PLC CHARACTERISTICS
High
Cost of change
Low
Time
Project Life Cycle
31
PM LIFE CYCLE (PMLC)
32
PROJECT STAKEHOLDERS
33
PROJECT STAKEHOLDERS
34
STAKEHOLDER
MANAGEMENT
Concurrent Engineering: provides
solution to the problem of differing
stakeholder needs, perspectives and
expectations.
Get and keep them involved through
assigning them work, using them as
experts, reporting to them, involving
them in changes and the creation of
lesson learned.
Get them to sign off and obtain their
formal acceptance.
35
PM PROCESS GROUPS
37
PM KNOWLEDGE AREAS
39
TIME MANAGEMENT
40
COST MANAGEMENT
41
QUALITY MANAGEMENT
42
HR MANAGEMENT
43
COMMUNICATION
MANAGEMENT
To ensure timely and appropriate generation,
collection, dissemination, storage and disposition of the
project information
Identify stakeholders
Plan communication
Distribute information
Manage stakeholders expectations
Report performance
44
RISK MANAGEMENT
45
PROCUREMENT
MANAGEMENT
To acquire material, goods and services from outside to
meet project scope.
Plan procurement
Conduct procurement
Administer procurement
Close procurement
46
INTEGRATION MANAGEMENT
47
STAKEHOLDER MANAGEMENT
Identify Stakeholders
Plan Stakeholder Management
Management Stakeholder Engagement
Control Stakeholder Engagement
48
MAPPING
Initiating Planning Executing Controlling Closing
50
MAPPING
Initiating Planning Executing Controlling Closing
Project • Plan •Manage • Control
Communication communications Communications Communicat
Management Management ions
52
53
54
55
SCOPE MANAGEMENT
60
61
64
65
TIME MANAGEMENT
69
70
71
72
73
74
75
76
77
COST MANAGEMENT
78
79
QUALITY MANAGEMENT
80
81
82
83
84
HUMAN RESOURCE MANAGEMENT
85
86
COMMUNICATIONS MANAGEMENT
87
88
89
RISK MANAGEMENT
90
91
92
93
94
PROCUREMENT MANAGEMENT
95
96
STAKEHOLDER MANAGEMENT
97
98
Earned Value Management
99
Planned Value
Planned value. Planned value (PV) is the authorized budget assigned to
scheduled work. It is the authorized budget planned for the work to be
accomplished for an activity or work breakdown structure
component, not including management reserve.
This budget is allocated by phase over the life of the project, but at a given
moment, planned value defines the physical work that should have been
accomplished. The total of the PV is sometimes referred to as the
performance measurement baseline
(PMB).
The total planned value for the project is also known as budget at completion
(BAC).
100
Earned Value
101
Actual Cost
102
Schedule Variance:
SV = EV – PV
103
Cost Variance:
CV= EV − AC
104
Schedule performance index:
The schedule performance index (SPI) is a measure of
schedule efficiency expressed as the ratio of earned value to
planned value. It measures how efficiently the project team is
using its time.
It is sometimes used in conjunction with the cost performance
index (CPI) to forecast the final project completion estimates.
An SPI value less than 1.0 indicates less work was completed
than was planned. An SPI greater than 1.0 indicates that more
work was completed than was planned.
SPI = EV/PV
105
Cost performance index:
The cost performance index (CPI) is a measure of the
cost efficiency of budgeted
resources, expressed as a ratio of earned value to
actual cost. It is considered the most critical EVM
metric and measures the cost efficiency for the work
completed. A CPI value of less than 1.0 indicates a
cost overrun for work completed.
CPI = EV/AC
106
Schedule Variance & Cost Variance
107
Some More Derived Metrics
SPI: Schedule Performance Index SPI=EV/PV
If SPI<1 means project is behind schedule
CPI: Cost Performance Index CPI= EV/AC
If CPI<1 means project is over budget
CSI: Cost Schedule Index (CSI=CPI x SPI)
The further CSI is from 1.0, the less likely project
recovery becomes.
108
PROJECT CHARTER
109
PROJECT CHARTER
110
PROJECT CHARTER
111
PROJECT CHARTER
Process overview:
INPUTS TOOLS & OUTPUTS
TECHNIQUES
• Project Statement of work • Project Charter
• Business case •Expert judgment
•Agreements •Facilitation
• EEF techniques
• OPA
112
113
PROJECT STATEMENT OF
WORK
Describes product/services to be provided by the
project.
For internal projects, it is given by project sponsor.
For external projects, it is given by customer.
It indicates business need, service scope description &
strategic plan.
114
BUSINESS CASE
115
EXPERT JUDGMENT
116
PROJECT CHARTER
Process overview:
INPUTS TOOLS & OUTPUTS
TECHNIQUES
• Project Statement of work • Project Charter
• Business case • Expert judgment
• Contract (if applicable)
• EEF
• OPA
118
IDENTIFY STAKEHOLDERS
119
IDENTIFY STAKEHOLDERS
Process overview:
120
STAKEHOLDER ANALYSIS
121
STAKEHOLDER ANALYSIS
Power
Monitor
(minimum Keep informed
Low effort)
123
IDENTIFY STAKEHOLDERS
Process overview:
124
PLANNING
125
PLANNING
127
COLLECT REQUIREMENTS
128
COLLECT REQUIREMENTS
130
DEFINE SCOPE
Process overview:
131
WBS
132
WBS
Project
1 2 3 4 5
1.1.1 1.2.1
1.1.1.1 1.2.1.1
1.2.2
1.2.3
1.2.3.1
1.2.3.2
133
WBS
134
WBS
135
WBS
136
WBS DICTIONARY
137
SCOPE BASELINE
138
CREATE WBS
Process overview:
139
DEFINE ACTIVITIES
140
DEFINE ACTIVITIES
Process overview:
141
SEQUENCE ACTIVITIES
142
SEQUENCE ACTIVITIES
Process overview:
143
PRECEDENCE
DIAGRAMMING
Shows activities in rectangle boxes linked by arrows
showing dependencies.
Boxes are called nodes.
Hence, it is known as activity-on-node (AON)
144
PRECEDENCE
DIAGRAMMING
Activity Dependency G
E H
D Start
A Start D
C
F D,A
Start
E D End
G F,E
A B
B F F
H G
C H
End C,B 145
PRECEDENCE
DIAGRAMMING
Four types of dependencies/precedence relationships:
Finish to start (FS) {tiles fitting & carpet laying)
Finish to finish (FF) {wiring & inspection}
Start to finish (SF) {commissioning new IT system}
Start to start (SS) {furniture making & shifting house}
146
DEPENDENCY
DETERMINATION
Mandatory dependency (hard logic):
Discretionary dependency (soft logic):
Determined by project team
It allows the activity to happen in a preferred order
External dependency:
External to the project like govt, vendors, external
resources etc.
147
LEAD
148
LAG
149
PROJECT NETWORK
DIAGRAM
Summary description of sequencing approach
Schematically show project activities along with their
dependencies.
Drawn manually or on computer using PDM.
Unusual sequences, if any are properly narrated.
Traditionally known as PERT chart.
150
ESTIMATE ACTIVITY
RESOURCES
Process of determining:
what physical resources (people, equipment, material)
what quantity of each resource
When they would be required to complete project
activities.
Resources – most imp assets of a project.
151
ESTIMATE ACTIVITY
RESOURCES
Process overview:
152
RESOURCE CALENDARS
153
ALTERNATIVE ANALYSIS
154
BOTTOM UP ESTIMATING
155
RBS
156
ESTIMATE ACTIVITY
DURATIONS
Process overview:
157
ANALOGOUS ESTIMATION
Order of magnitude
Gross value estimation approach.
Actual duration of a similar activity
completed on a previous project to
determine the duration of same type of
activity on the current project.
Used only in early phases of the project
when there is no detailed information.
Less costly and time consuming, less
accurate
158
DEFINITIVE ESTIMATION
Bottom up approach
Accurate
159
PARAMATRIC ESTIMATION
160
THREE POINT ESTIMATION
Most likely estimate (tM)
Optimistic estimate (tO)
Pessimistic estimate (tP)
Expected activity duration:
tO + 4 tM + tP
tE = -------------------
6
Concept originated with PERT
161
RESERVE ANALYSIS
162
RESERVE ANALYSIS
Using reserve too freely and too early and you have
nothing left for later when reserves might be critical.
Set hard limits as to how much to release in each period
of the project.
163
DEVELOP SCHEDULE
164
DEVELOP SCHEDULE
Process overview:
165
SCHEDULE NETWORK
ANALYSIS
A technique to generate project schedule.
Various analytical techniques like CPM, CCM, what if
analysis, resource leveling etc.
166
CRITICAL PATH METHOD
167
SCHEDULE COMPRESSION
168
SCHEDULE COMPRESSION
Fast tracking:
Performing critical path activities in parallel.
More risky
Rework, needs more attention to communication
169
WHAT IF SCENARIO
ANALYSIS
Calculating multiple project durations with different set
of activity assumptions with the use of simulation
techniques.
Monte Carlo Analysis
Used primarily to understand the feasibility of schedule
under unfavorable conditions.
Helps in making contingency or response plans to tackle
or lessen the effect of adverse situations.
170
RESOURCE LEVELING
171
DEVELOP SCHEDULE
Process overview:
172
PLAN QUALITY
173
PLAN QUALITY
Process overview:
Costs:
Training
Surveys
Studies
Appraisal
Design review
Benefits:
Less rework
Higher productivity
Lower costs
Increased stakeholder satisfaction
175
BENCHMARKING
176
DESIGN OF EXPERIEMENTS
DOE
Analytical technique that identifies the elements or
variables that will have impact on overall project
outcomes.
Designs and sets up experiments to determine the ideal
solution for a problem utilizing a limited number of
sample cases.
177
COST OF QUALITY
179
CONTROL CHARTS
180
STATISTICAL SAMPLING
181
QUALITY PLANNING TOOLS
Brain storming
Force field analysis
Matrix diagram
Nominal group techniques
Affinity diagrams
Prioritization techniques
182
QUALITY MANAGEMENT
METHODOLOGIES
Six sigma
Lean six sigma
Quality function deployment
CMMI (capability maturity model integration)
TQM
FMEA
Kaizen
183
PLAN QUALITY
Process overview:
185
QUALITY METRICS
Examples:
On time performance
Budget control
Defect frequency
Failure rate
186
QUALITY CHECKLISTS
187
DEVELOP HR PLAN
Process of :
Defining project roles and responsibilities
Required skills
Project organization chart
Reporting relationships
Staffing management plan (time table for staff
acquisition & release, training needs, team
building strategies, rewards & recognition,
compliance, safety issues etc).
OBS
Responsibility assignment matrix (RAM): RACI
Networking
188
PLAN COMMUNICATION
189
COMMUNICATION
Customer
Sponsor
Senior management
Functional managers
Team members
Other project managers
Regulatory authorities
Media
Society
Interest specific groups/organization
Stakeholders
190
COMMUNICATION
Status
Performance baselines
Achievements & major milestones
Problems
Changes to scope, schedule, cost etc
Adherence to standards & regulations
New risk uncovered
Team members performance
Project phase deliverable’s acceptance
191
COMMUNICATION
Status report
Progress report
Trend report
Forecasting report
Variance report
EV analysis report
192
COMMUNICATION
Methods:
Interactive communication
Push communication
Pull communication
193
SENDER RECEIVER MODEL
194
COMMUNICATION BARRIERS
Personal:
Human emotions
Values
Poor listening habits
Difference in education, culture, sex,
socioeconomic status
Physical:
Distance
Noise
Walls
Static that interferes with electronic messages
195