Turnkey CMP Modality (For Developer)
Turnkey CMP Modality (For Developer)
MODALITY
AGENDA
I. ABOUT TURNKEY CMP MODALITY
II. STAKEHOLDER ELIGIBILITY
III. PROJECT VALUATION AND APPROVAL PHASE
IV. PILOT PHASE AND APPROVAL
V. PROJECT TURNOVER AND CLOSURE
I. TURNKEY CMP MODALITY
• Approved through Board Resolution Nos. 767 and 898 dated
________.
• It was created to accelerate the delivery of housing services to
low-income families from the formal and informal sectors of
Philippine society.
• Utilizes the People’s Plan approach wherein the Community
Association (CA) chooses the site where they intend to
relocate, partners with the developer to build and develop its
housing project, applies for a CMP loan to finance the project,
and monitors the project’s development and construction.
Overview of the Process
• CA and the developer negotiate and agree on a housing project under
1 the ambit of a People’s Plan Approach;
• SHFC and CA inspect and approve the Pilot Phase of the Turnkey
7 CMP project;
Once accredited, developers who intend to work with SHFC again shall be required to
update their accreditation requirements with PRD for subsequent projects.
Summary of Requirements
Cancellation of Accreditation of
the Developer
• Cases of abandonment of CA without formal termination of
contract;
• Submission of spurious documents/statements;
• Deviation from approved plans and specifications, or providing
downgraded/substandard specifications without approval from the
CA, SHFC and/or LGU;
• Misrepresentation during pre-qualifications or accreditation;
• Sub-contracting work outside of the exceptions without CA and
SHFC approval;
• Lending of PCAB license to another contractor; and,
• Refusal to rectify the non-compliance of specifications of building
design.
Permits and Licenses Secured
by the SHFC-Accredited
Developer (Project Inclusions)
• The SHFC-Accredited Developer shall be responsible for securing
and paying the necessary costs associated with permits and
licenses, which shall include but not be limited to the following:
the conduct of relocation surveys, subdivision survey, approval
with the land management, land reclassification, land conversion,
Preliminary Approval and Locational Clearance (PALC),
Development Permit, building permits, electrical permits,
occupancy permits, and Fire Safety Inspection Certificate, unless
granted exemption by the local government. It is understood that
work on the project shall not start without the above enumerated
permits and licenses.
III. PROJECT VALUATION AND
APPROVAL PHASE
Endorsement for
Loan Examination Project Approval Multi-Stakeholder
and Mortgage Agreement
Examination
• have been satisfactorily
assessed and valuated by
• Final Design SHFC RED and Pre-Credit • Community
• Project Collateral Committee Level Associations
• endorsed to the SHFC
• Documentary Credit Committee,
• SHFC-Accredited
Requirements Management Committee, Developer
Executive Committee and • Social Housing
SHFC Board of Directors
for approval, subject to the Finance
approved Delegation of Corporation
Authority • LGU (if it’s LGU-
• A Letter of Guaranty shall
be issued for the Pilot
initiated project )
Phase which is equivalent
to a minimum of 10% of
the total number of units.
The succeeding phases
shall be covered by a
separate LOG, subject to
the evaluation and
acceptance of the
constructed units and
another approval of the
Board.
PROJECT VALUATION AND
APPROVAL PHASE
1. Loan Examination and Mortgage Examination
Upon successful negotiation and agreement between the CA and its
chosen developer, the concerned SHFC branch shall conduct the
loan examination and mortgage examination undertakings.
For loan examination, the guidelines embodied in Board Resolution
No. 877 for the conduct and parameters of the Community Needs
Assessment Tool and Process shall prevail. While activities for
mortgage examination shall be consistent with the pre-requirements
and technical due diligence of loans with Accommodation
Mortgage.
• Final Design
- The final design of the proposed housing project,
including the total cost for each beneficiary shall have the
conformity of all the members of the CA. This shall
likewise include provision for open spaces. For projects
involving at least 1,000 members, the SHFC-Accredited
Developer shall construct, at its own cost, infrastructure or
building facilities, such as, but not limited to, commercial
spaces, multi-purpose buildings, health center, livelihood
center, and/or community center.
• Project Collateral
The land on which the housing units are constructed,
including the improvements thereof, shall be the collateral
to the loan. All applicable taxes shall be shouldered by the
developer. Costs for the mortgage fees, transfer fees, and
annotations in the Registry of Deeds (RD) shall be
shouldered by the CA.
• Documentary Requirements
1. Topographic Map, if sloping terrain;
2. Vicinity Map/Site Structure Plan showing the socio-economic
facilities/establishments within 2 to 5-km radius and distance from the
proposed Turnkey CMP site;
3. Data on other Housing Projects (SHFC [CMP/HDH]/Private
Subdivision/Lots) within 2 to 5-km radius;
4. Disaster Risk Reduction Management Plan signed by the authorized
Homeowners Association and Barangay City Official/s.
5. Certified photocopies of the Transfer Certificate of Title (TCTs) (present,
1st back and 2nd back) covering the property to be posted as loan collateral;
6. Copy of tax declaration and tax map;
7. Zoning Certification issued by the concerned LGU citing that the land
use classification of the property is suited for socialized housing or its
equivalent;
8. Lot Plan/Subdivision Plan approved by the local government unit;
9. Complete set of approved plans, Bill of Quantities, and specifications;
Continuation…
SHFC RED shall review and ensure the completeness and acceptability
of the above listed documents within ten (10) working days from receipt.
2. Endorsement for Project Approval
• Turnkey CMP projects that have been satisfactorily assessed and
valuated by SHFC RED and Pre-Credit Committee Level shall be
endorsed to the SHFC Credit Committee, Management
Committee, Executive Committee and SHFC Board of Directors
for approval, subject to the approved Delegation of Authority
(Section 1.4).
• A Letter of Guaranty shall be issued for the Pilot Phase which is
equivalent to a minimum of 10% of the total number of units. The
succeeding phases shall be covered by a separate LOG, subject to
the evaluation and acceptance of the constructed units and another
approval of the Board.
Approving Committee:
3. Multi-Stakeholder Agreement
A Multi-Stakeholder Agreement shall be forged among the relevant stakeholders
and parties of the Turnkey CMP project, such as, but not limited to, the CA, the
SHFC-Accredited Developer, and SHFC. This agreement shall state the obligations
and responsibilities of the parties involved:
1. Community Associations – are the Turnkey CMP housing loan beneficiaries.
They shall be the primary decision-maker in terms of the location and the housing
unit’s design, utilizing the People’s Plan approach in engaging the developer and
SHFC.
2. SHFC-Accredited Developer – is the entity that primarily assists the CAs in
developing and constructing their technical shelter plan in accordance with the
latter’s preference.
3. Social Housing Finance Corporation – is the financing entity that oversees
approving and supervising the credit for the community’s housing loan through a
People’s Plan Approach. SHFC shall also ensure that the housing loan will have a
cumulative effect of creating resilient and sustainable communities.
Controlled Supervision by the LGU
The receiving local government unit shall also be part of the
agreement, provided that the project is an LGU-initiated project and
shall be given controlled supervision over all stages of the project.
It shall, among others, perform the following functions:
1. Assist in fast-tracking the issuance of necessary permits and
certifications;
2. Coordinate among the project stakeholders (CA and SHFC-
Accredited Developer) their respective project responsibility and
accountability; 10
3. Prepare and submit to SHFC the project status and/or progress
reports, including all project issues and actions taken, if any.
IV. PILOT PHASE AND
APPRAISAL
• What is a Pilot Phase?
-refers to the construction of a minimum of 10% of the total number of
the housing units to be constructed as agreed by the CA and Developer
for Turnkey CMP, where 80% to 90% of the project’s site development is
completed with provision of basic services that have been tested and
approved by the utility provider with respect to its specification and
requirements.
The basic services shall be those stated under Section 21 of the Urban
Development and Housing Act (RA 7279).