Chapter Four Evaluation (Appraisal) of Transport Projects: 2014E.C. Oda Bultum University
Chapter Four Evaluation (Appraisal) of Transport Projects: 2014E.C. Oda Bultum University
Evaluation(Appraisal) of
transport projects
2014E.C.
ODA BULTUM UNIVERSITY
Evaluation(Appraisal) of transport projects
The aim of the highway appraisal process is to determine the
economic, societal and environmental feasibility of the project or
group of projects under examination.
The process enables highway planners to decide whether a project
is desirable in absolute terms and also provides a means of
choosing between different competing project options, all of
which have the ability to meet the stated goals and objectives of
the project sponsors.
Evaluation of transport projects (cont’d)
Appraisal - Assessing whether an alternative solution is
worthwhile clearly involves forecasting the effect it will
have on policy indicators and weighing them up to decide
whether overall the proposal is beneficial.
Economic efficiency - Projects could be found and
undertaken which would make everyone better off, those
projects would serve to promote economic efficiency.
A project is economically efficient if the benefits measured
in money terms exceed the costs; the most efficient project is
that for which the difference is greatest.
Evaluation of transport projects (cont’d)
Transport project expenditures can be readily valued using
monitory terms and maintenance can be computed using the
market price of the nation. Operating cost usually takes the form:
𝐺=𝑀+𝛾 𝑇
where is the generalized cost,
is the monitory cost,
T is the journey time and
is the value of time.
Costs of transport projects- pain and grief resulting from
accidents, environmental effects- do not have a market price.
Evaluation of transport projects (cont’d)
Accidents
Damage to property and vehicles,
Health service, ambulance and police costs, and
Loss of production due to victims being unable to work
Difficult is to place a money value on the pain, grief and suffering caused by death or injury
in an accident.
Environmental
Property demolition,
Noise nuisance,
Visual intrusion and air pollution.
Consumption of scarce and non-renewable resources such as oil.
Benefits
Reduction of congestion and travel time,
Provision of accessibility,
Enhancement of environment
Evaluation of transport projects (cont’d)
The time saving can be generally indicated by the change in the operating
cost after the opening of the transport project.
Δ𝐺=𝐺𝑖−𝐺𝑓
Where Δ𝐺 is the saving in operating cost,
𝐺𝑖 is the initial cost before the project and
𝐺𝑓 is the current cost after the construction of the project.
The total saving in operating cost is given by
(NPV) ≥0
CFt
n
• Using the formula: NPV t
t 0 (1 R )
Step 1 Step 2 Step 3 Step 4
0 250 0 -250 1.00 -250
1
250 290 40 0.893 35.7
2
250 290 40 0.797 31.9
3
255 300 45 0.712 32
4
260 335 75 0.636 47.7
5
260 335 75 0.567 42.5
6
260 335 75 0.507 38.0
1,185 1,295 -22.2
Step 5
NPV=-22.2 <0 thus, The project, cannot be accepted
Example 2
Benefits-Costs (Net Cash Values of 1 at 8% Discounted Net
Year Flows) Discount Rate Cash Flows
Step 2 Step 3 Step 4
0 -250 1.00 -250
1 40 0.93 37.2
2 40 0.86 34.4
3 55 0.79 43.5
4 75 0.74 54.8
5 75 0.68 51.0
6 75 0.63 47.2
NPV=18.1
Rules are:
BCR>1 = Accept
BCR<1 = Reject
BCR =1 Indifferent
Evaluation of transport projects (cont’d)
Steps for calculating the benefit-cost ratio are:
Step 1. Estimate the cash inflows and outflows on a year-to-year
basis
Step 2. Find out for individual years the discount value of 1 at
the given
discount rate.
Step 3. Multiply the cash inflows and cash outflows for each
year by the corresponding discount factor.
Step 4 .Add up the discounted values of cash inflows and
outflows separately.
Step 5. Divide the discounted values of cash inflows by cash
outflows to obtain the benefit-cost ratio.
example 3
Ye a Costs Discount Discounted Values
r
(outfl ows) Benefits Factor at
(inflows) 8% Costs Benefits
Step 1 Step 2 Steps 3 and 4
0
250 0 1 250 0
1
250 290 0.93 232.5 269.7
2
250 290 0.86 215 249.4
3
255 300 0.76 193.8 228
4
260 335 0.73 189.8 244.55
5
260 335 0.68 176.8 227.8
6
260 335 0.63 163.8 211.05
1421.7
1430.5
Total
t 0 (1 IRR )
t
0
8-18
Evaluation of transport projects (cont’d)
NPV > 0 at 15% required return, so you should
Accept
IRR =10.11% (using a financial calculator), which
would tell you to Reject
Recognize the non-conventional cash flows and
look at the NPV profile
I= 15%
YR CF
0 -$90,000
1 $132,000
2 $100,000
3 -$150,000
NPV $1,769.54 >0
IRR-1 10.11% < 15%
IRR-2 42.66% > 15%
8-19
Evaluation of transport projects (cont’d)
Evaluation of transport projects (cont’d)
Independent
The cash flows of one project are
unaffected by the acceptance of the
other.
Mutually Exclusive
The acceptance of one project
precludes accepting the other.
Evaluation of transport projects (cont’d)
The calculation of the internal rate of return involves the
following steps for mutually exclusive project.
Step 1. Estimate the cash inflows and cash outflows on a year-to-
year basis
Step 2. Work out the net cash flows for individual years.
Step 3. Select any random discount rate and compute the net
present values.
Step 4. If the NPV thus arrived at is positive, then select a higher
discount rate at which the NPV may come close to zero.
If, however, the NPV is negative, then select a lower discount
rate at which the NPV may come close to zero.
Step 5. Repeat the exercise until a discount rate that reduces the
net present values to zero is found.
Example (mutually exclusive project)
Costs
(Cash
Benefits
Year Net Cash Net Present Values
outflow s) (Cash
Flows Discounted
inflows)
Step 1 Step 2 Step 3(A) Step 4(B)
8% 12%
0
250 0 -250 -250 -250
1
250 290 40 37.2 35.7
2
250 290 40 34.4 31.9
3
255 300 45 43.5 32.0
4
260 335 75 54.8 47.6
5
260 335 75 51.0 42.5
6
260 335 75 47.2 38.0
Total
NPV=18.1 NPV=-22.2
Cont’d
In this example, the initial discounting of the net cash flows (Step
3) has been done at 8 percent, which gives a positive net present
value of 18.1.
Step 4, that is, discounting at 12 percent, turns the net values to a
negative figure of 22.2, suggesting that the rate at which the
discounted net values would turn zero must lie somewhere between
8 and 12 percent.
An alternative to the use of repetitive computations is
“interpolation”, which is a technique of finding the intermediate
values between any two figures, or any two discount rates in the
present context.
Project A is selected based on NPV & Project B is rejected.
Cont’d
IRR=Lower Dis. rate+ X
Internal rate of return = 8+ (12 – 8) X 18.1
(18.1)-(-15.1)
= 8+ (4) x 18.1
40.3
= 8 + (4) (0.45)
= 8 + 1.8
= 9.8 % rate of discount
Evaluation of transport projects (cont’d)
Example of Mutually Exclusive
Projects
Period Project A Project B The required
0 -500 -400 return for both
projects is 10%.
1 325 325
2 325 200
Which project
IRR 19.43% 22.17% should you accept
NPV 64.05 60.74 and why?
Thank you!!!!
Any Questions????