Case Study Pert Mustang Updated
Case Study Pert Mustang Updated
STUDY
2 QUESTION 1
3 QUESTION 2
4 QUESTION 3
5 QUESTION 4
INTRODUCTION
NEW VENTURE
Approach
1. Assemble a library
1. Serving as a part
of parts and body
brokers for NOS
manuals for old cars
for customization
2. Machine new parts to
purposes
replicate those which
are rare
2. Offers help in
compiling part list
3. Take charge of the
and RASAS could
entire if restoration
acquire the parts for
them
BASIC RESTORATION
Competitive priorities
CONTENT
OF
THE Aspects of proposed business
REPORT
Project Duration and Budget
Productivity cost
LEARNING ISSUES
AND
CONCEPT
PROJECT MANAGEMENT
Work Network
breakdown planning (PERT
schedule or CPM)
Schedule of
project activities
Develop a risk
Analyze cost
management
time trade off
plan
Steps in PERT
www.themegallery.com
Competitive Priorities
QUALITY
www.themegallery.com
Competitive Priorities
Flexibility
restore
Accept the
any
Restoring oldkind
car
vintage
for customer
automobile who
does fit the
of
are
restoration
really
demand of keen on
current a
customer
market
vintage wants
cars.
www.themegallery.com
Competitive Priorities Customer services
www.themegallery.com
QUESTION
2
Construct a table containing the
project activities using the letter
assigned to each activity, the time
estimates and the precedence
relationship.
TABLE OF PROJECT ACTIVITIES
Activity Detail Predecessor Time
U Put chrome parts back on. Car must have been S,M 1
painted and chrome parts rechromed first
V Put car to the Detroit Auto Show. Must have T,U 2
completed reupholstery of interior and have put
the chrome parts back on
QUESTION
3
Draw a network diagram of the project
similar to figure 2.4.Determine the
activities on the critical path and the
estimated slack for each activity
S= 0 S= 0 S= 0
A 0 2 B 2 32 T 32 39
2 0 2 30 2 32 7 32 39
S=27
36
S=30
1 36
S=28
37 4 37 41
S
I 2 3 J 3 6 O 8 9 H
1 29 31 3 33 36 1 36 37
S=28
K 3 8
5 31 36 41
days
$100 $2100 $2400
A 0 2 B 2 32 T 32 39
2 0 2 30 2 32 7 32 39
$200
36
$900
1 36
$240
37 4 37 41
S
I 2 3 J 3 6 O 8 9 H
1 29 31 3 33 36 1 36 37
$1000
K 3 8
5 31 36
Critical path
A – B – T – V = 41 days
QUESTION
4
Prepare a project budget showing the cost
of each activity and the total for the
project.
Can the project be completed within the
budget?
ACTIVITIES COST ($)
A 100
B 2100
C 800
D 1750
E 200
F 300
G 1000
H 1500
I 200
J 900
K 1000
L 200
M 210
N 200
O 240
P 20 00
Q 100
R 100
S 1 700
T 2 400
U 100
V 1 000
TOTAL COST 18 100
Total project cost
= $ 50 000 + $ 18 100
= $ 68 100
Assumptions
*Activities B,C and D must be paid for when the item is
received
*The costs of all activities that spam more than one week
can be prorated
*Each week contains five work days
GANTT CHART
F:\gantt chart mustang.doc