0% found this document useful (0 votes)
255 views39 pages

Project Management: A Managerial Approach: Chapter 9 - Resource Allocation

Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPT, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
255 views39 pages

Project Management: A Managerial Approach: Chapter 9 - Resource Allocation

Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPT, PDF, TXT or read online on Scribd
You are on page 1/ 39

Project Management: A

Managerial Approach

Chapter 9 – Resource Allocation

© 2006 John Wiley and Sons, Inc.


Overview

• Critical Path Crashing


• Resource Leveling
• Resource Constrained Schedules
• Multiproject Resource Management
• Critical Chain

© 2006 John Wiley and Sons, Inc.


Critical Path Method - Crashing a Project
• CPM includes a way of relating the project
schedule to the level of physical resources
allocated to the project
• This allows the project manager to trade
time for cost, or vice versa
• In CPM, two activity times and two costs
are specified, if appropriate for each
activity

© 2006 John Wiley and Sons, Inc.


Chapter 9-1
Critical Path Method - Crashing a Project
• The first time/cost combination is called
normal, and the second set is referred to as
crash
• Normal times are “normal” in the same sense
as the ‘m’ time estimate of the three times
used in PERT
• Crash times result from an attempt to expedite
the activity by the application of additional
resources
© 2006 John Wiley and Sons, Inc.
Chapter 9-2
Critical Path Method - Crashing a Project

• Careful planning is critical when attempting


to expedite (crash) a project
• Expediting tends to create problems; and the
solution to one problem often creates
several more problems that require solutions
• Some organizations have more than one
level of crashing

© 2006 John Wiley and Sons, Inc.


Chapter 9-3
Crashing – Sample Network

3 8
6 6 6

3 2 10 7
1 4 0
11 5 5

Critical Path = 3 + 6 + 8 + 6 = 23 Time Units


© 2006 John Wiley and Sons, Inc.
Crashing – An Example
Activity Normal Normal Crash Crash Max
Time Cost Time Cost Slope Crsh Tm

1-2 3 $50 2 $70


2-3 6 $80 4 $160
2-4 10 $60 9 $90
2-5 11 $50 7 $150
3-6 8 $100 6 $160
5-7 5 $40 4 $70
6-7 6 $70 6 $70
© 2006 John Wiley and Sons, Inc.
Crashing – Sample Network

3 $100
$80 6 $70

$50 2 7
1 4

“Normal” Project Total Cost = $50 + $80 + $100 + $70 +


$60 + $50 + $40 = $450
© 2006 John Wiley and Sons, Inc.
Crashing – An Example
Activity Normal Normal Crash Crash Max
Time Cost Time Cost Slope Crsh Tm

1-2 3 $50 2 $70 20 1


2-3 6 $80 4 $160 40 2
2-4 10 $60 9 $90 30 1
2-5 11 $50 7 $150 25 4
3-6 8 $100 6 $160 30 2
5-7 5 $40 4 $70 30 1
6-7 6 $70 6 $70 0 0
© 2006 John Wiley and Sons, Inc.
Crashing – Sample Network
Critical Path = 23 Days
3 8
6 $100 6
$80 6 $70
3
10
$50 2 $60 7
1 4

$50 5 $40
11 5
“Normal” Project Total Cost = $50 + $80 + $100 + $70 +
$60 + $50 + $40 = $450
© 2006 John Wiley and Sons, Inc.
Crashing – Sample Network
Critical Path = 23 Days “Crashed”Path = 20 Days
3 6
6 $160 6
$80 6 $70
2
10
$70 2 $60 7
1 4

$50 5 $40
11 5
“Crashed” Project Total Cost = $70+ $80 + $160 + $70 +
$60 + $50 + $40 = $530
© 2006 John Wiley and Sons, Inc.
Fast-Tracking
• Another way to expedite a project is known
as “fast-tracking”
• It refers to overlapping the design and build
phases of a project
• Because design is usually completed before
construction starts, overlapping the two
activities will result in shortening the project
duration
© 2006 John Wiley and Sons, Inc.
Chapter 9-4
The Resource Allocation Problem

• A shortcoming of most scheduling procedures is


that they do not address the issues of resource
utilization and availability
• Scheduling procedures tend to focus on time
rather than physical resources
• Time itself is always a critical resource in
project management, one that is unique because
it can neither be inventoried nor renewed
© 2006 John Wiley and Sons, Inc.
Chapter 9-5
The Resource Allocation Problem

• Schedules should be evaluated not merely in


terms of meeting project milestones, but also in
terms of the timing and use of scarce resources
• A fundamental measure of the project
manager’s success in project management is the
skill with which the trade-offs among
performance, time, and cost are managed

© 2006 John Wiley and Sons, Inc.


Chapter 9-6
The Resource Allocation Problem

• The extreme points of the relationship between


time use and resource use are these:
– Time Limited: The project must be finished by a
certain time, using as few resources as possible. But it
is time, not resource usage, that is critical
– Resource Limited:The project must be finished as
soon as possible, but without exceeding some specific
level of resource usage or some general resource
constraint

© 2006 John Wiley and Sons, Inc.


Chapter 9-7
The Resource Allocation Problem
• If all three variables - time, cost, specifications -
are fixed, the system is “overdetermined”
• In this case, the project manager has lost all
flexibility to perform the trade-offs that are so
necessary to the successful completion of projects
• A system-constrained task requires a fixed amount
of time and known quantities of resources

© 2006 John Wiley and Sons, Inc.


Chapter 9-8
Resource Loading

• Resource loading describes the amounts of


individual resources an existing schedule requires
during specific time periods
• The loads (requirements) of each resource type are
listed as a function of time period
• Resource loading gives a general understanding of
the demands a project or set of projects will make
on a firm’s resources

© 2006 John Wiley and Sons, Inc.


Chapter 9-9
Resource Loading

• An excellent guide for early, rough project


planning
• Because the project action plan is the source of
information on activity precedences, durations, and
resources requirements, it is the primary input for
both the project schedule and its budget
• The action plan links the schedule directly to
specific demands for resources

© 2006 John Wiley and Sons, Inc.


Chapter 9-10
Resource Loading

• The PERT/CPM network technique can be


modified to generate time-phased resource
requirements
• The project manager must be aware of the ebbs and
flows of usage for each input resource throughout
the life of the project
• It is the project manager’s responsibility to ensure
that the required resources, in the required amounts,
are available when and where they are needed

© 2006 John Wiley and Sons, Inc.


Chapter 9-11
Resource Leveling

• Resource leveling aims to minimize the period-by-


period variations in resource loading by shifting tasks
within their slack allowances
• The purpose is to create a smoother distribution of
resource usage
• Several advantages include:
– Less hands-on management is required
– May be able to use a “just-in-time” inventory policy

© 2006 John Wiley and Sons, Inc.


Chapter 9-12
Resource Leveling

• When resources are leveled, the associated costs


also tend to be leveled
• The project manager must be aware of the cash
flows associated with the project and of the means
of shifting them in ways that are useful to the
parent firm
• Resource leveling is a procedure that can be used
for almost all projects, whether or not resources are
constrained
© 2006 John Wiley and Sons, Inc.
Chapter 9-13
Resource Leveling - Example

© 2006 John Wiley and Sons, Inc.


Constrained Resource Scheduling
• There are two fundamental approaches to constrained
allocation problems:
– Heuristic Methods
– Optimization Models
• Heuristic approaches employ rules of thumb that have
been found to work reasonably well in similar situations
• Optimization approaches seek the best solutions but are
far more limited in their ability to handle complex
situations and large problems

© 2006 John Wiley and Sons, Inc.


Chapter 9-14
Heuristic Methods

• Heuristic approaches to constrained resource


scheduling problems are in wide, general use for a
number of reasons:
– 1. They are the only feasible methods of attacking the
large, nonlinear, complex problems that tend to occur in
the real world of project management
– 2. While the schedules that heuristics generate may not be
optimal, they are usually quite good- certainly good
enough for most purposes

© 2006 John Wiley and Sons, Inc.


Chapter 9-15
Heuristic Methods

• Most heuristic solution methods start with the


PERT/CPM schedule and analyze resource usage
period by period, resource by resource
• In a period when the available supply of a resource
is exceeded, the heuristic examines the tasks in that
period and allocates the scarce resource to them
sequentially, according to some priority rule
• Technological necessities always take precedence

© 2006 John Wiley and Sons, Inc.


Chapter 9-16
Heuristic Methods
• Common priority rules:
– As soon as possible
– As late as possible
– Shortest task first
– Most resources first
– Minimum slack first
– Most critical followers
– Most successors
– Arbitrary
© 2006 John Wiley and Sons, Inc.
Chapter 9-17
Heuristic Methods

• Most priority rules are simple adaptations of the heuristics used


for the traditional “job shop scheduling” problem of
production/operations management
• Most heuristics use a combination of rules: a primary rule, and
a secondary rule to break ties
• As the scheduling heuristic operates, one of two events will
result:
– The routine runs out of activities before it runs out of resources
– The routine runs out of resources before all activities have been
scheduled

© 2006 John Wiley and Sons, Inc.


Chapter 9-18
Optimizing Methods
• The methods to find an optimal solution to the
constrained resource scheduling problem fall
into two categories:
– Mathematical programming
– Enumeration
• Mathematical programming can be thought of
as liner programming (LP) for the most part

© 2006 John Wiley and Sons, Inc.


Chapter 9-19
Optimizing Methods

• Linear programming is usually not feasible for


reasonably large projects where there may be a
dozen resources and thousands of activities
• In the late 1960s and early 1970s, limited
enumeration techniques were applied to the
constrained resource problem
• Tree search, and branch and bound methods were
devised to handle up to five resources and 200
activities
© 2006 John Wiley and Sons, Inc.
Chapter 9-20
Multiproject Scheduling and Resource Allocation

• The most common approach to scheduling and


allocating resources to multiple projects is to treat the
several projects as if they were each elements of a
single large project
• Another way of attacking the problem is to consider all
projects as completely independent
• To describe such a system properly, standards are
needed by which to measure scheduling effectiveness

© 2006 John Wiley and Sons, Inc.


Chapter 9-21
Multiproject Scheduling and Resource Allocation
• Three important parameters affected by project scheduling
are:
– Schedule slippage
– Resource utilization
– In-process inventory
• The organization (or the project manager) must select the
criterion most appropriate for its situation

© 2006 John Wiley and Sons, Inc.


Chapter 9-22
Multiproject Scheduling and Resource Allocation

• Schedule slippage, often considered the most important


of the criteria, is the time past a project’s due date or
delivery date when the project is completed
• Resource utilization is of particular concern to
industrial firms because of the high cost of making
resources available
• The amount of in-process inventory concerns the
amount of work waiting to be processed because there
is a shortage of some resource

© 2006 John Wiley and Sons, Inc.


Chapter 9-23
Multiproject Scheduling and Resource Allocation

• All criteria cannot be optimized at the same


time
• As usual, the project manager will have to
make trade-offs among the criteria
• A firm must decide which criterion to evaluate
its various scheduling and resource allocation
options
© 2006 John Wiley and Sons, Inc.
Chapter 9-24
Mathematical Programming

• Mathematical programming can be used to obtain


solutions to certain types of multiproject scheduling
problems
• These procedures determine when an activity should
be scheduled, given resource constraints
• Mathematical programming, however, is rarely used
in project management to handle the multiproject
problem (mostly, heuristics are used)

© 2006 John Wiley and Sons, Inc.


Chapter 9-25
Mathematical Programming

• The three most common objectives of mathematical


programming are:
– 1. Minimum total throughput time (time in the shop) for all
projects
– 2. Minimum total completion time for all projects
– 3. Minimum total lateness or lateness penalty for all projects

• These objectives are most appropriate for ‘job shop’


type solutions to resource constraints

© 2006 John Wiley and Sons, Inc.


Chapter 9-26
Heuristic Techniques

• There are scores of different heuristic-based


procedures in existence
• They represent rather simple extensions of well-
known approaches to job-shop scheduling:
– Resource Scheduling Method
– Minimum late finish time
– Greatest resource demand
– Greatest resource utilization
– Most possible jobs

© 2006 John Wiley and Sons, Inc.


Chapter 9-27
Critical Chain
• Eliyahu M. Goldratt’s “Theory of Constraints”
• Traditional Project Estimation Techniques
Ineffective
– Time and Resource Constraints Usually Violated
– PMs Rely on “Padding” of Schedules and Budgets
– Unknown Nature of Event Interaction
• Fear, Uncertainty, Doubt
• Psychological, Organizational, and Physical

© 2006 John Wiley and Sons, Inc.


Critical Chain - Approach
• Bottleneck Management
– Activities with Several Predecessors and/or
Successors
– Add “Time Buffers” at Bottleneck Events
• “Safety Stock” Equivalent in Manufacturing
• Just-in-Time with “Just-in-Case”
• Statistically-derived “Path Buffers”
– Establish the Critical Chain for Scarce Resources
– Prioritization of Resources in Chain Events
• Communication of “Walt” Needs is Critical to Success

© 2006 John Wiley and Sons, Inc.


Copyright 2006 John Wiley & Sons, Inc.
All rights reserved. Reproduction or translation of this work beyond that permitted in section 117
of the 1976 United States Copyright Act without express permission of the copyright owner is
unlawful. Request for further information should be addressed to the Permissions Department,
John Wiley & Sons, Inc. The Publisher assumes no responsibility for errors, omissions, or
damages caused by the use of these programs or from the use of the information herein.

© 2006 John Wiley and Sons, Inc.

You might also like