Project Management: A Managerial Approach: Chapter 9 - Resource Allocation
Project Management: A Managerial Approach: Chapter 9 - Resource Allocation
Managerial Approach
3 8
6 6 6
3 2 10 7
1 4 0
11 5 5
3 $100
$80 6 $70
$50 2 7
1 4
$50 5 $40
11 5
“Normal” Project Total Cost = $50 + $80 + $100 + $70 +
$60 + $50 + $40 = $450
© 2006 John Wiley and Sons, Inc.
Crashing – Sample Network
Critical Path = 23 Days “Crashed”Path = 20 Days
3 6
6 $160 6
$80 6 $70
2
10
$70 2 $60 7
1 4
$50 5 $40
11 5
“Crashed” Project Total Cost = $70+ $80 + $160 + $70 +
$60 + $50 + $40 = $530
© 2006 John Wiley and Sons, Inc.
Fast-Tracking
• Another way to expedite a project is known
as “fast-tracking”
• It refers to overlapping the design and build
phases of a project
• Because design is usually completed before
construction starts, overlapping the two
activities will result in shortening the project
duration
© 2006 John Wiley and Sons, Inc.
Chapter 9-4
The Resource Allocation Problem