Event Chain Methodology
Event Chain Methodology
????
Risks Affecting Project Schedule
Event 1
Event 2
Event 3
Principle 1: Single Events
Statistical distribution for
moment of event
Event 1 Event 2
Event 2
Event 3
Event Chain: Event 1 triggered a response event after some time
Event
Structural Event: Execute
defect is Response Plan
discovered
Risk Response
Is completed
Entry point
Exit
Point
Execution of
Response Plan
Risk Response Plan
“Repair”
Risk Transfer
Event 1
Event 1
Transferred
Principle 3: Event Chain Diagrams
Closed or Closed
transferred issue
Issue risk
Threat
Opportunity
State: New Requirements
Risk Probability and Impacts
Low impact
Event 2
0.5
Event 4
Event Chain Executes an Activity
Event 1
Event Chain:
Event triggers
activity
Event Chain Executes a Group Activities
Event 1
Event Chain:
Event triggers
group of
activities
State Table
Task: Software Development
Event 2:
Event 1: Event 3:
Problem with
Architectural Minor
development
changes requirement change
tool
Probability: 20% Probability: 10%
Moment of event: any time Moment of event: any time
Ground State Excited state: refactoring Excited state: refactoring
Impact: delay 2 weeks Impact: delay 1 week
Probability: 10%
Excited state: Moment of event: start of the state
Excited state: minor code change
refactoring Impact: delay 2 days
Excited state:
minor code change
Principle 4: Monte Carlo Simulations
Duration Cost
53% chance that Duration w ill be less than 121.03 (day) 52% chance that Cost w ill be less than 95,977.01 ($)
Determ. Determ.
18%
100% 25% 100%
6%
30% 8% 30%
4%
20% 5% 20%
2% 10% 3% 10%
109.49 90514.93
0% 0% 0% 0%
25.00 50.00 75.00 100.00 125.00 150.00 175.00 25,000.00 50,000.00 75,000.00 100,000.00 125,000.00 150,000.00
Duration (day) Cost ($)
Schedule and Non-Schedule Risk Categories
Event 1 Impact:
Schedule – 20% Schedule related
Cost – 30% categories
Performance – 50%
Quality – 45% Non-schedule
Litigation – 25% categories
Safety – 40%
Security – 30
Integrated Impact – 50%
Principle 5: Critical Event Chains
Critical Event
Chain
Principle 6: Project control with events
Low estimate of High estimate of
project duration project duration
100%
% Complete
Project Duration
Risks Risk response increases a chance of
Chance of 100% the project meeting the deadline
project meeting
a deadline
80%
(Project Success
Rate)
60%
Chance of meeting the
deadline is reduced as a result
40% of events
Risk response plan
20%
0%
0 2 4 6 8 10 12
Project Duration, Weeks
Project Risk Analysis Made Ridiculously Simple
A Step by Step Guide to Project Risk Analysis
by Lev Virine and Michael Trumper