Pengenalan Uji Sumur (Introduction To Well Testing)
Pengenalan Uji Sumur (Introduction To Well Testing)
• Deliverability tests
To measure the productivity of the well and
reservoir performance based on pressure
changes with flowrate
WELL TEST OBJECTIVES
Pressure Transient Test:
• Reservoir properties (permeability, skin
factor, fracture-matrix Parameter, etc).
• Define drainage area limits
• Estimate average pressure
• Reservoir pore volume (estimated at pseudo steady
state period).
• Communication between two adjacent wells
• Evaluate stimulation treatment effectiveness
WELL TEST OBJECTIVES
Deliverability tests:
• Estimate well productivity
• Characterize reservoir
• Diagnose productivity problems
• Estimated ultimate recovery (EUR) or
movable fluid volumes (estimated using
long-term production performance).
HOW IS A WELL TEST CONDUCTED?
HOW IS A WELL TEST CONDUCTED?
Pressure Transient Test :
Single Production Well Test
• Pressure Buildup (PBU) test
- shut in after controlled production
• Injectivity test
- Inject into the well at measured rate and
measure pressure as it increases with time
analogous to pressure drawdown testing.
Pressure Transient Test :
Multi Well Test
• Interference tests
- The active well is produced at a measured,
constant rate throughout the test
- Other wells in the field must be shut in so that
any observed pressure response can be
attributed to the active well only.
-wells which usually can be interpreted
unambiguously (even when other wells in the
field continue to produce)
Pressure Transient Test :
Multi Well Test
• Pulse tests
The active well produces and then, is shut in,
returned to production and shut in again
Repeated but with production or shut-in periods
rarely exceeding more than a few hours
Produces a pressure response in the observation
wells which usually can be interpreted
unambiguously (even when other wells in the
field continue to produce)
DELIVERABILITY TESTS (DT)
Dimana:
Co = kompresibilitas cairan
Vw = volume lubang sumur, bbl
Atau oleh Earlougher, 1977:
Dua karakteristik rezim aliran dapat hadir dalam respon sumur dengan wellbore storage dan skin dalam
reservoir homogen:
1. Pada early time, selama rezim murni dipengaruhi lubang sumur,
Wellbore Storage
• Selama rezim aliran murni, wellbore storage coeficient
dapat diperkirakan dari plot p vs t pada skala linier
(van Everdingen dan Hurst, 1949):
(1)
Batasan-batasan:
Pada sumur: Jari-jari sumur terbatas, laju injeksi
tetap
Pada reservoir: Infinite acting, tekanan awal dan
sifat reservoir seragam.
Jika reservoir satu lapisan, homogen dan isotropic.
Fluida reservoir slightly compressible.
Sumur-sumur memproduksi fluida dari seluruh
ketebalan.
Periode Infinite Acting
Penyelesaian PDE untuk aliran radial
Dimana:
Dimana:
Periode Infinite Acting
• Persamaan di atas dapat ditulis sebagai:
rD = r/rw = rw/rw = 1
dimana:
Uji pada Reservoir Terbatas
• Setelah sesaat encapai periode pss, laju penurunan tekanan akan konstan dan seragam diseluruh daerah pengurasan.
• Volume pori:
Shape Factors untuk berbagai daerah pengurasan sumur