Method Statement of Substation - Sample

The document provides details on the electrical work method for the substation press/body shop, including installing cable trays, lighting, and grounding systems on the 1st and 2nd floors. The scope of work involves main feeder installation, lighting installation, and grounding installation. Safety and quality control measures are outlined for each step, such as using safety harnesses and checking that installations meet drawings.

Uploaded by

Nimas Afina
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
275 views17 pages

Method Statement of Substation - Sample

The document provides details on the electrical work method for the substation press/body shop, including installing cable trays, lighting, and grounding systems on the 1st and 2nd floors. The scope of work involves main feeder installation, lighting installation, and grounding installation. Safety and quality control measures are outlined for each step, such as using safety harnesses and checking that installations meet drawings.

Uploaded by

Nimas Afina
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
You are on page 1/ 17

WORK METHOD ELECTRICAL

SUBSTATION PRESS/BODY SHOP


- Supporting work
- Installation tray and lighting
- Grounding system

2020. June . 17 Rev.0


Approved by
HMMI Project In Indonesia Proposed by
GIIC Real Estate Row 32, Blok BG
Construction Schedule at Substation Press/Body Shop
■ Outline/Scope of Work
 Cable tray 1st Floor  Lighting 1st Floor

Scope of Work :

 Main feeder installation


(Supporting work, cable
tray, MV-LV cable
installation, grounding
installation)
 Lighting installation
 Cable tray 2nd Floor  Lighting 2nd Floor (Supporting work, cable
and lighting installation)

Work location :

 Substation 1st Floor


 Substation 2nd Floor
■ Outline/Scope of Work
 Grounding System

Grounding rod included with box


Scope of Work :

 Main feeder installation


(Supporting work, cable
tray, MV-LV cable
installation, grounding
installation)

Work location :

 Substation 1st Floor


 Substation 2nd Floor
 Outdoor/outside
■ Sequence of Working Group

Working
2nd FL
Group-2

Working
1st FL
Group-1
■ STEP OF WORK Cable Tray Installation
 STEP-1 INSTALL HANGER & SUPPORT CABLE TRAY

0 mm
50 Hanger Gap
ax2
m

= Anchor bolt/clamp, hanger & support tray

= Hanger & supprt


Substation 1 FL & 2 FL
■ Squence of Work Cable Tray Installation
Substation 2 FL

 HANGER & SUPPORT


1 1. Step-1 Install clamp & UNP support
2 2. Step-2 Install hanger
 CABLE TRAY
3. Step-3 Install cable tray

3 3
■ Squence of Work Cable Tray Installation
Substation 1 FL

1
 HANGER& SUPPORT
2 1. Step-1 Install clamp & UNP support
2. Step-2 Install hanger
 CABLE TRAY
3. Step-3 Install cable tray

3
3
■ STEP OF WORK Lighting Installation
 STEP-1 INSTALL HANGER & SUPPORT LIGHTING

Hanger Gap

Max 2500 mm

= Anchor bolt/clamp, hanger rod & support lighting

= Hanger rod
Substation 1 FL & 2 FL
■ STEP OF WORK Lighting Installation
 STEP-2 INSTALL CABLE LIGHTING

= Cable Lighting

Substation 1 FL & 2 FL
■ STEP OF WORK Lighting Installation
 STEP-3 INSTALL LIGHTING

= Lighting Fixture

Substation 1 FL & 2 FL
■ Sequence of Work Lighting Installation

1 2

 HANGER & SUPPORT  CABLE & LIGHTING


1. Step-1 Install clamp & support Substation 1 FL & 2 FL
3. Step-3 Install Cable
2. Step-2 Install hanger rod & C-Channel 4. Step-4 Install Lighting

(Type B)

3 4
■ STEP OF WORK Grounding Installation
 STEP-1 Excavation

= Excavation area for slevee grounding = Location for grounding rod

Inside Substation 1 FL Outdoor Electrical Room


■ Sequence of Work Grounding Installation

 STEP – 1 Boring for make hole  STEP – 2 Install grounding rod (Inside hole)

3000 Grounding rod

 STEP – 3 Megger test (Max 5ohm)  STEP – 4 Excv. cabling, backfill and install
grounding box
Grounding box
(Follow sample mockup)

Excavation, cabling, backfill


Grounding rod
Grounding rod
■ Sequence of Work Grounding Installation
Inside Electrical
Room

1
2

 EXCAVATION
1. Step-1 Soil excavation
2. Step-2 Install sleeve for grounding
3. Step-3 Concrete protection
4. Step-4 Backfill

3
■ C. Tray, Lighting & Grounding Work _JSQA (Job Safety Quality Analysis)
No. Name of Work Dangerous/risk point Safety Control Quality Control

1. Install clamp and support for c. tray & - Falling from height - Safety Harness and handrail - Tool box meeting
lighting - Falling object - Scaffolding must be follow the standard - Make sure that location of clamp for c. tray & lighting
- Hand pinched - Safety helmet and shoes based on drawing
- Slip, trip, fall - Check ground condition - Make sure the clamp and support was tighten and
- Mask tough

2. Install hanger rod for c. tray & lighting - Falling from height - Safety Harness and handrail - Tool box meeting
- Falling object - Scaffolding must be follow the standard - Make sure that location of hanger rod for c. tray &
- Hand pinched - Safety helmet and shoes lighting based on drawing
- Slip, trip, fall - Check ground condition - Make sure the hanger rod was tough
- Mask

3. Install cable tray & lighting - Falling from height - Safety Harness and handrail - Tool box meeting
- Falling object - Scaffolding must be follow the standard - Make sure that location of cable tray & lighting based
- Hand pinched - Safety helmet and shoes on drawing
- Slip, trip, fall - Check ground condition
- Mask

4. Install Rod and BC cable - Slip and trip - Put base for work on soil - Tool box meeting
- Get stabbed by steel bar - Check ground condition - Make sure that location of rod based on drawing
- Hand pinched - To improve coordination for worker - Make sure connection of BC cable to steel bar was
- Use glove tighten
- Mask
5. Check resistance grounding rod - DC electric shock - Use earth tester follow instruction - Maximum value is 5ohm

6. - Install mesh earth - Hand pinched - To check crane rope before use. - Don’t add water into concrete
Cabling NYA cable & connection - Slip and trip - Set strong support on gutter - Compacting must use vibrator
- Install steel conduit for cable sleeve - Worker is not allow hang up in bucket - Don’t put vibrator into concrete too long, for time limit is
mesh grounding 10 sec.

7. Check resistance grounding cable DC electric shock - Use earth tester follow instruction - Maximum value is 5ohm
■ Flow Chart Scaffolding Inspection
STEP 1 START 2 1

Based on standard of Preparation No


scaffolding material
STEP 4 Inspection HEIN’ Safety

Install Scaffolding Yes

Scaffolding ready to use

No
STEP 2 Inspection Kinden’ Safety

FINISH
Yes

Scaffolding installed

STEP 3 Inspection Takenaka’ Safety

No
Yes

2
Scaffolding installed