Pile Foundations 2021
Pile Foundations 2021
Pile Foundations 2021
By –
C.M.GUPTA
Sr.Prof/Br.2
IRICEN
1
TYPE OF FOUNDATIONS
• SHALLOW
– SINGLE FOOTING
– COMBINED FOOTING
– RAFT
– STRIP
• DEEP
– PILE
– WELL
2
DEEP FOUNDATIONS
• ADEQUATE GRIP- BELOW DEEPEST
ANTICIPATED SCOUR
• DEPTH OF FOUNDATION BELOW WATER LEVEL
FOR Qf –
• NOT LESS THAN 1.33 X MAX DEPTH OF SCOUR
• SHALL NOT REST ON SLOPING ROCK STRATA
• DYNAMIC AUGMENT NEED NOT BE
CONSIDERED
3
CLASSIFICATION OF PILES
• BROAD CALSSIFICATION
– DRIVEN (DISPLACEMENT PILES)
– BORED (REPLACEMENT PILE)
• ON THE BASIS OF MATERIAL
– TIMBER
– STEEL
– PCC
– RCC
– PSC
– COMPOSITE
4
CLASSIFICATION OF PILES
• Method of construction
– Driven precast piles
– Driven cast in situ piles
– Bored precast piles
– Bored cast in situ piles
• Mode of load transmission
– End bearing piles
– Friction piles
– Friction cum end bearing piles
5
CLASSIFICATION OF PILES
• Sectional area
– Circular
– Square
– Tubular
– Octagonal
– H-section
• Size
– Micro (mini) piles (<150 mm)
– Small diameter pile (>150 mm < 600 mm)
– Large diameter pile (>600 mm)
6
CLASSIFICATION OF PILES
• INCLINATION
– VERTICAL PILES
7
8
9
END BEARING PILE
10
FRICTION PILES
11
DRIVEN PILING
12
BORED PILING
13
CONSTRUCTION OF PILE FOUNDATION
• Driven precast piles
– Drop hammer
– Single/ double acting hammer
– Diesel hammer
– Vibratory hammer
• Driven cast in situ piles
– Steel casing pipe with shoe at bottom driven to reqd depth
– Casting after placing reinforcement cage
• Bored cast in situ piles
– Guide casing of 3-4 m at top of bore hole
– Bailer – chiesel
– Bentonite slurry for stabilisation
– Flushing
– Concreting after placing rein. Cage
– Tremie method of concreting
– Concrete grade m 20 or higher
– High slump concrete 14
DRIVING OF PILE
15
DRIVEN CAST IN SITU
• Driving a permanent
or temporary casing
and filling with plain
or reinforced
concrete
16
INSTALLATION OF BORED CAST IN SITU
PILES
17
BAILER AND CHISEL METHOD
18
AUGAR
BORING
19
UNDER REAMING RIG
20
BORED CAST IN SITU PILES
• Stabilization of bore
–Drilling Mud Circulation
(Bentonite Slurry)
Bentonite is impure clay
consisting of Montmorillonite.
Na cation responsible for support
21
MUD CIRCULATION
22
TREMIE CONCRETING
• concrete to be rich in cement (min 370 kg/ m3), slump –
150 -180 mm
• casing- temp/permanent
• sliding plug/steel plate flushed ahead of first charge – to
prevent mixing of water
• hopper and tremie should be closed system
• dia of tremie pipe – 200mm for 20mm aggregare
• concreting to be uninterrupted
• top of concrete in pile – above cutoff level
• min embedment in pile cap – 50 mm
23
TREMIE CONCRETING
24
TREMIE CONCRETING
25
Method statements for casting of piles
26
Method statements for casting of piles
27
Method statements for casting of piles
28
Method statements for pile cap casting
29
Method statements for pile cap casting
30
Method statements for pile cap casting
31
SELECTION OF TYPE OF PILES
32
SOCKETTING IN ROCK
• For the end bearing piles
– Sound relatively homogenous rock including
granite and gneiss -- 1 to 2D
– Moderately weathered closely formed
including schist & slate ---- 2 to 3D
– Soft rock --- 3 to 4D
33
SEQUENCING OF PILING
• Normally from centre to periphery or from one
side to other
• Possibility of harm to adjacent piles be considered.
More damage in compact soils
• Order of installation should avoid creating a
compacted block of ground
• In stiff clay or compacted sand layers – from center
to outward or from one edge to across the group
• In very soft soils – from outside to inside
34
SPACING OF PILES
• Determined based on the
– Type of soil
– Empirical approach
• Practical aspects of installing a pile
• Nature of load transfer
• Possible reduction in bearing capacity of a
group of piles
35
SPACING OF PILES
• For end bearing piles
– Governed by competency of bearing strata
– Not less than 2.5 D
• For friction piles
– Sufficiently apart to avoid overlapping zones
– Not less than 3 D
• Closure spacing possible in loose sand or fillings
for driven piles only
• Max spacing 4 D
36
LOAD CARRYING CAPACITY OF PILE
• In context of foundation engineering
• Load that a pile can carry without undergoing
continuous settlement for insignificant load
increments – by virtue of its boundary
conditions
• Failure of surrounding soil occurs before
failure of pile material
37
FACTORS INFLUENCING PILE CAPACITY
• Surrounding soil
• Installation technique
• Spacing of piles
• Symmetry of the group
• Location of pile cap
• Shape of pile cap
• Location of pile in a group
• Drainage conditions in soil
38
LOAD CARRYING CAPACITY OF SINGLE PILE
• Dynamic pile formula – by using the data obtained during
piling ( conservation of energy)
– Hiley’s Formula
• More reliable for non-cohesive soils
• Not reliable for cohesive soils
• Static formula – using soil test results
39
Engineering news formula
40
Hileys formula
41
SE
E
fig
1
An of
d ap
Ar
e
IS pe
a
64 n d
of
03 ix
pi
fo B f
le
r N or
r ( Nq
to
Di
e
sl
a
id
e
of
22
)
pi
le
De
cm
Be ns
a rin ity
Ef
fe g of
c tiv ca so
e pa il
ov c ity
er fa
bu
rd c to
en rs
pr
e ss
ur
Ef Co e
fe at
c tiv
ef
fic t oe
e i en
ov t of
er
b ur e ar
de th
n pr
pr es
e ss su
u re
re
An at
gl ith
e la
of y
w er
al
lf
ric
tio
Su n
rfa =
ce ph
i
•Similar formula for clayey soil is also given in Annex B-2
ar
ea
of
i th
la
ye
r
LOAD CARRYING CAPACITY
• Annex B-1 of IS:2911 Part 1, Sec.2:2010 - For Granular soil
42
43
Bearing capacity factor Nγ
44
Bearing capacity factor Nq
45
46
47
48
49
FACTOR OF SAFETY
50
BEARING CAPACITY OF A PILE GROUP
• MAY BE
– EQUAL TO THE BC OF SINGLE PILE X NO. OF PILES
– LESS THAN THE ABOVE
• FRICTION PILES, CAST OR DRIVEN INTO
PROGRESSIVELY STIFFER MATERIALS & END BEARING
PILES – EQUAL
• FRICTION PILES INSTALLED IN SOFT AND CLAYEY SOILS
– LESS
• DRIVEN PILES IN LOOSE SANDY SOILS – MORE DUE TO
EFFECT OF COMPACTION
51
BEARING CAPACITY OF A PILE GROUP
STRATA TYPE OF PILE BC PF PILE GROUP
1. DENSE SAND NOT DRIVEN NO. OF PILES X SPC
UNDERLAIN BY WEAK
DEPOSITS
2. LOOSE SANDY SOILS ½ (NO. OF PILES X SPC)
53
OVERLOADING OF PILES
• 10% OF THE PILE CAPACITY MAY BE ALLOWED
ON EACH PILE
• MAX OVERLOADING ON A GROUP SHALL BE
RESTRICTED TO 40% OF THE ALLOWABLE
LOAD ON A SINGLE PILE
• SHALL NOT BE ALLOWED AT INITIAL DESIGN
STAGE
54
LOAD TEST
• STRESS TEST
– MAINTAINED LOAD TEST
– CONSTANT RATE OF PENETRATION TEST
– LATERAL LOAD TEST
– DYNAMIC LOAD TEST
– CYCLIC LOAD TEST
• STRAIN TEST
– LOW STRAIN INTEGRITY TEST
– HIGH STRAIN INTEGRITY TEST
55
PILE LOAD TESTING
(IS-2911 PART-IV)
• Initial Test
– On one or more piles
– Min. 2 tests if past experience of piles in that
area is not available
• Purpose
– To check safe load calculated by static or
dynamic formulae
– Arrive at safe load
56
PILE LOAD TESTING
(IS-2911 PART-IV)
• Routine Test
– On ½ percent of piles, can be increased
to 2% depending on strata
• Purpose
– To check safety of piles against safe
load
57
PILE LOAD TESTING
(IS-2911 PART-IV)
58
LOAD TEST-INITIAL TEST
• THE SAFE LOAD ON A SINGLE PILE WILL BE
LEAST OF THE FOLLOWING
60
LOAD SETTLEMENT CURVE
SAFE LOAD
Least of 2/3
P1 or ½ P2
FOR GROUP
Least of Load
corrp. to 25 mm
sett or 2/3
corrp. to 40 mm
sett.
LOAD IN
INCREMENTS
OF 20%
Final load
maintained for
24h
61
LOAD TEST – ROUTINE TEST
• TEST LOAD WILL BE ATLEAST 1.5
TIMES THE WORKING LOAD
63
PILE LOAD TEST
(KENTELEDGE ARRANGEMENT)
64
PILE LOAD TEST
(WITH ANCHOR PILES)
65
DYNAMIC PILE TESTING
• SUPPLEMENTS STATIC TESTING
• HIGH STRAIN TESTING
– PROVIDES DATA ON FORCE & ACCELERATION OF PILE
– EVALUATION OF BEARING CAPACITY
– FACILITATE IMMEDIATE DECISION ABOUT ACCEPTANCE
OR REJECTION OF PILE
• LOW STRAIN TESTING
– FOR TESTING CONTINUITY OF PILE
– INFORMATION ABOUT DIMENSIONS AND CONSISTANCY
OF MATERIAL
ASTM D 4945
66
DEFECTS IN CAST IN SITU PILES
• HONEY COMBING DUE TO INADEQUATE VIBRATIONS
• SEGREGATION DUE TO IMPROPER CONCRETE
PLACEMENT METHODS
• WASHOUT OF CEMENT DUE TO GROUNDWATER
FLOW
• CRACKS IN PILE SHAFT DUE TO SHRINKAGE
• INCLUSION OF FOREIGN MATERIAL
• NECKING DUE TO COLLAPSE OF SIDE WALLS DURING
WITHDRAWAL OF TEMPORARY CASING
67
NECKING IN PILE
68
NECKING IN PILE
69
O U
K Y
A N
T H
70
DESIGN OF PILES
71
RELEVENT STANDARDS
• Manual on the Design and
Construction of well and pile
Foundations issued by RDSO
• IS 2911- Part I
– Section I – Driven cast in situ piles
– Section II- Bored cast in situ piles
– Section III- Driven precast concrete
piles
• IS 2911- Part IV- Load test
72
RELEVENT STANDARDS
73
STEPS OF DESIGN
1. From soil data, depth of scour – fix length
of pile
2. Based on thumb rules, fix dia of pile
3. Calculate load carrying capacity of single
pile using static formulae
4. Do rough design for selected group of piles.
Spacing to be based on thumb rules
5. Check design for load carrying capacity,
settlement, depth etc.
6. Revise design if required
7. Conduct load test to confirm capacity of
pile
8. Do structural design
74
IMP. CODAL PROVISIONS
• DIA. OF PILE
– Bridge Manual- > normally 1 m
– IRC-78
» Bored piles on land- min. 1 m
» Bored pile in river bridge- min. 1.2 m
– IS 2911- Part I, Section 2
» Provisions are for max. dia of 2.5 m
• For Railway bridges dia. Of 1 m to 1.5
m be normally adopted
75
IMP. CODAL PROVISIONS
• SPACING OF PILE
– IRC-78
» Friction- min. 3 D
» End bearing- Can be reduced to clear distance= D
that is c/c 2D
– IS 2911- Part I, Section 2
» End bearing- hard soil- Min. 2.5 D
» End bearing- hard rock- Min. 2.0 D
» Friction- Min 3.0 D
– RDSO Manual
» Friction – min. 3 D
» End bearing- Min. 2.5 D
» Max. 4 D
79
IMP. CODAL PROVISIONS
• FOS
– IRC-78
» 2.5 if derived from static formulae for
soil. 5 for end bearing on rock and 10 for
socket resistance.
– IS 2911- Part I, Section 2
» Appendix given for calculating strength
with static formulae
– RDSO Manual
» 3 if derived from static formulae.
» 2 if derived from load test
80
LAYOUT
Accuracy of prime
importance
Should always be
cross checked by at
least two
independent surveys
Permanent theodolite
stations with the base
line on the bank will
be established to
mark reference points
81
Well v/s Pile
83
NORMAL SCOUR
LACEY’s FORMULA- D = 0.473 (Qf/f)1/3
IF
(a)Design flood continues for sufficient time
(b)River is flowing straight through
incoherent alluvium and are free to adjust
their width of flow and their depth
(c)The width of the river is not less than the
Lacey’s regime width i.e. L= 4.85 Qf.
• f is the silt factor = 1.76m
• Where the width is less than Lacey’s
regime width
dc/d = (w/wc)0.61 84
LOCAL SCOUR
• The depth calculated shall be increased as under-
Qu = Rs + Rt
Qu = fs As + qt At
TRANSFER
vs Depth vs Depth
Rs = 0
Rs
Rt
Rt
Uniform
Rt Rs
Triangular
Rt Rs
87