Project Plan Development Approach
Setting Up Tasks
Planning the Transition from the Project Team to
a Line Organization
Project Documentation
Project Plan Evaluation
Some Guidelines
Introduction
Why plan?
To eliminate or reduce uncertainty
To improve efficiency of the operation
To obtain a better understanding of the objectives
To provide a basis for monitoring and controlling
work
To pre-think future actions for the project
Verify target achievability of all set project targets
Identify problems and risks that may affect the project
Resource planning for project activities
Communication to project stakeholders
Gaining commitment from project stakeholders
Providing people involved in the project with objectives
Basis for controlling the project
What are the consequences of not planning
Objectives
a goal, target or quota to be achieved
Programme
strategy and major action to achieve objectives
Schedule
a plan to show when milestones will be reached
Budget
planned expenditure for the project
Forecast
a projection of what will/may happen when
Organisation
the projects management and personnel structure
Policy
a general guide to decision making and individual
actions
Procedures
a detailed method for carrying out policy
Standards
a level performance defined as adequate and/or
acceptable
Considering what you already know about project
management.
Why is project planning so important?
Discuss in small groups
What is the purpose of the project?
Management
Technology
Business Process
Customers
Suppliers
What is the scope of the project?
What are the tangible benefits from completing
the project? “If the project were not done or if it failed, what would be
the impact?”
Step 1: Determine the project concept
Step 2: Assess the project
Step 3: Develop a strategy for the project
Step 4: Identify major milestones and initial schedule
Step 5: Define initial budget – using milestones.
Step 6: Identify groups/organizations will be involved
Step 7: Determine the methods/tools to be employed in the project
Step 8: Identify the areas of risk and association them with milestones and tasks
Step 9: Refine the schedule and budget
Step 10: Identify project manager/leader
Step 11: Identify and establish the project team
Step 12: Develop the detailed project plan
Project Concept:
Purpose of the project
Scope of the project
Benefits of the project
General roles of the project – which organizations are going to
do what
Basic issues that the project may face
Evaluation of Specific Objectives & Scope
Do the objectives and scope fit with the organization?
Are the objectives too broad or too focused?
Are potential resources available?
What are the areas of risks?
Are the benefits reasonable given the purpose and scope?
Perspectives:
Technology
Competition
Government Regulations
Politics
Cross-impacts examples
First, determine which items can be employed in the project
Second, determine where risks lie up front, before the project is
started.
Third, use the list to validate your objectives and scope.
What should your strategy address?
How will you organize the project?
How will you select the project leader/team?
What will be the role of the team in project management?
How will you manage risk and address issues?
First – define your approach for each of the above items
(including alternatives)
Second – refine your approach by considering political,
organizational, and technological factors
Third – evaluate each alternative
Milestones:
Draw up at least 10 to 20 milestones for each
subprojects.
Logically relate the milestones between the
subprojects in terms of dependences.
Take a piece of paper and lay it out sideways.
List 4 or 5 key resources for each milestone
Next, develop an initial budget by milestones for
each subprojects (always develop your initial budget buttom-up).
Estimate overhead and other resources as a group
(including facilities, supplies, and equipments as well as personnel).
Organization Role Impt. of Involvement
Create an table as above.
First, determine the set of methods/tools for the
actual work.
Another set of methods and tools for the project
management.
Refine and label more detailed milestones which involve risks
(smaller milestones).
Use the list of issues that may impact the project as defined in the
project concept.
Identify any tasks (milestones) to which an issue pertains.
Refine the estimates of budgets and schedule
based upon the “risks” identified in the tasks.
Identify several alternative project managers
Need a backup plan for a project leader when
leaves a project before completion.
Identify and establish a few key people as the
core of the project team.
For each subproject enter the milestones and the resources
that you identified.
New define the tasks that lead up to each milestone (you
now have a work breakdown structure with a list of tasks).
Establish dependencies between tasks.
Assign up 4 to 5 resources per task.
Estimate the duration of each task and set the start date of
the project.
Assign the quantity of each resource for the tasks.
Analyze the schedule and make changes by changing
duration, dependencies, resources, and starting dates.
Keep the task description simple – less than 30
characteristics
If the task name is compound or complex, split the task.
Start each task with an action verb.
Use a field in the project database for responsibility for
the task.
Each detailed task should be from 2 to 10 days long.
Use standard abbreviations wherever possible.
Number all tasks in an outline form.
Establish categories of resources (e.g., personnel,
equipment, facilities, etc).
Try to avoid using the individual names of people (Put a job little
abbreviated form instead).
Keep resource names to less than 10 characteristics.
Use a field in the software to indicate which tasks have substantial
risk.
Use task outlining and indenting.
Group the task with appropriate milestones.
Label milestones as such (e.g., M: Foundation completed).
Use a field to put in the name of the person (or organization
accountable for the tasks).
Identify the organization that will be responsible
for the results of the project.
Work with the organization to determine several
people who will be responsible for day-to-day
operation.
Plan a limited role for these individuals in the
project before the transition to get them
committed and involved in the project.
Depends on the size and complexity of the project
Justify the time spent on documentation on the grounds of
managing risks and for marketing.
Recommended Items:
A project plan for the overall project.
Detailed project plans for each subproject
A list of initial known issues for the project
A description of interfaces between subprojects.
A description of the roles of organizations involved in the project.
Are the objectives and scope consistent?
Is the scope reflected in the range of tasks?
Is the strategy borne out in the tasks?
Have you identified the areas of risks?
Have you defined the key resources?
Have you associated tasks that carry risk with the list
of issues?
If you were assigned the job of attacking the plan,
what would you see as the major weakness?
Build a plan with great detail on the near-term tasks but less detail
for tasks that are further out in the future.
Take a project and divide it into phases.
Remain sensitive to the environment
Understand what Not to do in a project
Hold one person accountable for each detailed task
Minimize documentation
Analyze risks at the start of a project
Use a chart to create a picture of the project
Does your firm follow an established
sequence of steps in developing project
plans?
How are small projects handled differently
from large projects in your company?
If you were to develop a new project plan,
what guideline, templates, and other support
are offered in your organization?
1. Project Plan (outlining the activities, tasks,
dependencies and timeframes)
2. Resource Plan (listing the labor, equipment and
materials required)
3. Financial Plan (identifying the labor, equipment and
materials costs)
4. Quality Plan (providing quality targets, assurance and
control measures)
5. Risk Plan (highlighting potential risks and actions
taken to mitigate them)
6. Acceptance Plan (listing the criteria to be met to gain
customer acceptance)
7. Communications Plan (listing the information needed
to inform stakeholders)
8. Procurement Plan (identifying products to be sourced
from external suppliers).
If time allows consider the following
Why do you suppose that the coordination of
various elements of the project is considered the
most difficult aspect of project implementation?
Discuss the above in small groups
1. Introduction and status of the plan
2. The authorization procedures
3. Statement of project objectives
4. Statement of requirement and Technical approach
5. Deliverables in the project
6. A Work Breakdown Structure
7. The project milestones
8. The resource requirements
9. Interdependencies of work
10. The timetable of events
11. Staffing, organization and responsibilities
12. Development methods and toolsets to be used
13. Source documentation
14. Resource and financial summary
Project Planning Tools
Introduction to project scheduling