Lesson 11 - PMP Prep Risk V3
Lesson 11 - PMP Prep Risk V3
This course is based on PMBOK® Guide – Fifth Edition Copyright 2014, Simplilearn, All rights reserved.
PMP, PMI, PMBOK is a registered mark of PROJECT MANAGEMENT INSTITUTE®
Risk is an uncertain event or condition that, if it occurs, has a positive or negative effect on a
project’s objectives.[1]
You are currently using a software for managing the team’s time sheet. Due to a budget constraint, you are
expected to use a new software. You are apprehensive on using the new software, but on using it, you
realize that the new software is more efficient and has better reporting structure. This is a case of risk
having a positive outcome.
If the Government declares a mandatory holiday to check flu spread, the project timelines may get
hampered and this is an example of risk affecting the project negatively.
Positive risks are known as opportunities and negative risks are known as threats. A risk that can have
a positive or negative risk is called business risk. A risk that can only have a negative consequence is
called pure risk. Given below are other risk related terms:
Risk averse
One who does not take risks.
Risk tolerance
The level of risk that can be tolerated.
Risk threshold
Amount of risk that is acceptable.
Understanding the key terms of project risk management may be useful while answering the exam.
Exam Tips
Where, risk probability is the likelihood that a risk event could happen
and risk impact is the effect on the project objectives if a risk event
happens.
Q Calculate the expected monetary value for the given work packages.
Internal Risks Arise within the project. E.g., funding, resources, and prioritization.
Technical Risks Arise out of the technology being used. E.g., requirements, technology, and quality.
Project Arise out of project management activities. E.g., estimating, planning, schedule, and
Management Risks communication.
Risks can also be classified on the basis of their origin; scope risks, resource risks, schedule risks, cost
risks, and quality risks.
7 Copyright 2014, Simplilearn, All rights reserved.
Decision Tree
A decision tree is used to analyze risk and its impact on decisions, in the face of uncertainties.
Failure : Probability=10%
Impact= $15,000
Initial cost of buying the new car
= $20,000 Pass : Probability=90%
Impact= $000
Decision: Which car would you
buy? A new one or a used one.
Failure : Probability=70%
Initial cost of buying the old car= Impact= $10,000
$15,000
Pass : Probability=30%
Impact= $000
Q If you need to buy a car, which one would you buy? Which option has a risk over a period of 5 years?
A
Risk = Probability * Impact
Risk associated with the new car is $20,000 + ($15,000 * 10%) + ($000*90%) = $21,500
Risk associated with the old car is $15,000 + ($10,000*70%) + ($000*30%) = $22,000
8 Copyright 2014, Simplilearn, All rights reserved.
Risk Reserve
Project cost should include both the known and unknown risks. The various risk reserves are
calculated in the order given below:
Management
Reserve
Cost
Baseline
Contingency
Reserve
Project
Control
Work Account
Packages
Activities
Small, Work packages Set of Reserve for Project cost Reserve for
Lowest level
assigned clubbed to control known for unknown
of WBS
project tasks manage cost accounts uncertainties budgeting uncertainties
9 Copyright 2014, Simplilearn, All rights reserved.
Project Risk Management
Project Risk Management includes the processes of conducting risk management planning,
identification, analysis, response planning, and controlling risk on a project.[2]
The key objective of risk management is to increase the probability and or impact of positive events
and decrease the probability and or impact of negative events.
Q Cynthia is a subject matter expert and the Director of New Store Construction in Small Markets.
Because of her expertise and experience in managing complex store build out for the corporation, she
has been appointed as the manager of a new, large, and complex construction project involving a gas
station. None of the previous construction projects included a gas station and convenience store
component. Since this is a new initiative and way for the company to diversify their business, this
project is business critical, very visible to senior management and can be a career maker or breaker.
The senior management team is anxious to see the project brought to life, but the company lacks a
strong risk management process. They would like Cynthia to prepare a risk response plan and submit it
prior to the project’s first milestone in 3 weeks. What should Cynthia do?
A Because the company lacks a risk management structure and has handled risk poorly in the past,
Cynthia should first search internally for risk experts. Internal experts would be knowledgeable of risks
that exist within the business as it deals with construction. Then she should identify subject matter
experts external to the organization knowledgeable of risk management as it relates to convenience
stores with a gas station component. Another viable resource would be the historical documents
around risk from previously completed projects, which will also point out other stakeholders and/or
SMEs who can contribute to the risk response planning process. After having the key players in place,
Cynthia can work with them to go through the identification and prioritization process of risk that
leads up to the development of their plan.
Plan Risk Management is the process of defining how to conduct risk management activities for a project. The
key benefit of this process is it ensures that the degree, type, and visibility of risk management are commensurate
with both the risks and the importance of the project to the organization. [3] It is part of the Planning Process Group.
Project charter
Legend
Input
Output Analytical techniques Expert judgment Meetings
Tools & Techniques
Planning Process
The table given below shows the impact on scope, cost, time, and quality.
Identify Risks is the process of determining which risks may affect the project and documenting their characteristics. [4]
It belongs to the Planning Process Group.
Perform Qualitative Risk Analysis is the process of prioritizing risks for further analysis or action by assessing their
probability of occurrence and impact. [5] This process belongs to the Planning Process Group.
PROJECT RISK MANAGEMENT
Organizational process
assets
Legend
Input Risk probability and Risk data quality Probability and impact
Output impact assessment assessment matrix
Tools & Techniques Risk urgency
Risk categorization Expert judgment
Planning Process assessment
Concept based questions on qualitative risk analysis can be expected in the exam.
Exam Tips
17 Copyright 2014, Simplilearn, All rights reserved.
Probability and Impact Matrix—Example
A probability and impact matrix tabulates the probability and impact scales for the opportunities and
threats on the project.
Probability Threats Opportunities
0.9 0.05 0.09 0.18 0.36 0.72 0.72 0.36 0.18 0.09 0.05
High 0.7 0.04 0.07 0.14 0.28 0.56 0.56 0.28 0.14 0.07 0.04
0.5 0.03 0.05 0.10 0.20 0.40 0.40 0.20 0.10 0.05 0.03
Medium
0.3 0.02 0.03 0.06 0.12 0.24 0.24 0.12 0.06 0.03 0.02
Low 0.1 0.01 0.01 0.02 0.04 0.08 0.08 0.04 0.02 0.01 0.01
Impact 0.05 0.10 0.20 0.40 0.80 0.80 0.40 0.20 0.10 0.05
Perform Quantitative Risk Analysis is the process of numerically analyzing the effect of identified risks on overall
project objectives.[6] This is part of the Planning Process Group.
Schedule management
plan
Perform Quantitative Risk
Project document updates
Enterprise environmental Analysis
factors
Organization process
assets
Legend
Input Data gathering and Quantitative risk analysis and
Expert judgment
Output representation techniques modeling techniques
Tools & Techniques
Planning Process
Plan Risk Responses is the process of developing options and actions to enhance opportunities and to reduce threats
to project objectives.[7] It is part of the Planning Process Group.
Project documents
updates
Legend
Input Strategies for negative risks (or threats): Avoid, transfer, mitigate, accept Contingent response strategies
Output
Tools & Techniques
Planning Process Strategies for positive risks (or opportunities): Exploit, share, enhance, accept Expert judgment
Residual risks are those that remain after the risk responses were implemented. Secondary risks arise out
! of implementing risk responses.
20 Copyright 2014, Simplilearn, All rights reserved.
Control Risks
Control Risks is the process of implementing risk response plans, tracking identified risks, monitoring residual risks,
identifying new risks, and evaluating risk process effectiveness throughout the project. [8] It is part of the Monitoring
and Controlling Process Group.
Organizational process
assets updates
Change request
Legend
Input Risk audits Risk re-assessment Meetings
Output
Tools & Techniques Variance and trend Technical performance
Monitoring & Controlling
Reserve analysis
analysis measurement
21 Copyright 2014, Simplilearn, All rights reserved.
Quiz
a. Transfer
b. Mitigation
c. Acceptance
d. Avoidance
a. Transfer
b. Mitigation
c. Acceptance
d. Avoidance
Answer: a.
Explanation: It is an example of transfer as the financial risk is transferred to the insurance
company.
Answer: d.
Explanation: The right project management practice dictates that a work around should be
created as a response to the event.
a. Risk Seeker
b. Risk Averse
c. Risk Neutral
d. Risk Mitigator
a. Risk Seeker
b. Risk Averse
c. Risk Neutral
d. Risk Mitigator
Answer: b.
Explanation: Someone who doesn't want to take risk is called risk averse and the attitude of
the organization seems to be the same.
Answer: a.
Explanation: Decision tree analysis is a quantitative risk analysis technique that involves a
diagram describing different decisions under consideration and the impact on the project of
choosing one over the another.
30 Copyright 2014, Simplilearn, All rights reserved.
QUIZ
How early can a comprehensive risk analysis be done on a project?
5
Answer: b.
Explanation: Only after the entire scope has been defined in the Work Breakdown Structure
(WBS), a comprehensive risk analysis can be done.
•Exercise 19
•Exercise 20
This course is based on PMBOK® Guide – Fifth Edition Copyright 2014, Simplilearn, All rights reserved.
PMP, PMI, PMBOK is a registered mark of PROJECT MANAGEMENT INSTITUTE®
[1] Definition taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body
of Knowledge, (PMBOK® Guide) – Fifth Edition, Project Management Institute, Inc., 2013.
[2] Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Fifth
Edition, Project Management Institute, Inc., 2013, Page 309.
[3] Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Fifth
Edition, Project Management Institute, Inc., 2013, Page 313.
[4] Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Fifth
Edition, Project Management Institute, Inc., 2013, Page 319.
[5] Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Fifth
Edition, Project Management Institute, Inc., 2013, Page 328.
[6] Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Fifth
Edition, Project Management Institute, Inc., 2013, Page 333.
[7] Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Fifth
Edition, Project Management Institute, Inc., 2013, Page 342.
[8] Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Fifth
Edition, Project Management Institute, Inc., 2013, Page 349.
38 Copyright 2014, Simplilearn, All rights reserved.