Lesson 3 - PMP - Prep - Project Management - V3
Lesson 3 - PMP - Prep - Project Management - V3
This course is based on PMBOK® Guide – Fifth Edition Copyright 2014, Simplilearn, All rights reserved.
PMP, PMI, PMBOK is a registered mark of PROJECT MANAGEMENT INSTITUTE®
After completing ● Differentiate between Project Life Cycle and Project Management Process
this lesson, you will
be able to: ● Name the five Project Management Process Groups
Given below are the differences between project lifecycle and project management process:
In the software industry, project lifecycle includes In the develop schedule process, one needs to develop the
understanding requirement in the requirement analysis project schedule, irrespective of the industry or domain you
phase, implementing requirement in the design phase, are working.
writing code and implementing the functionality in the
coding phase, debugging of code in the testing phase,
installation of the software at customer location, and
providing support in the operations and support phase.
The iteration of processes within the phases is dependent on the scale of the projects. Small projects may
! only one iteration, while bigger projects may have multiple iterations before they enter a new phase.
Process Groups have overlapping activities that occur throughout the project life cycle. The output of
one process acts as an input to another process or a deliverable of the project.
Figure—B[2]
5 Copyright 2014, Simplilearn, All rights reserved.
Project Management Process Map
Study the table to identify processes under project management and the knowledge area they belong
to.
Exam Tips
6 Copyright 2014, Simplilearn, All rights reserved.
Initiating Process Group
Initiating Process Group defines a new project or phase. When the project charter is approved, the
project is officially authorized.
Inputs Actions taken
● Project statement of work ● Review the statement of work and business case
● Agreements ● Clarify the assumptions and constraints
● Business case ● Establish the feasibility of the project
● Enterprise environmental factors ● Identify the key stakeholders of the project and
● Organizational process assets their interest in the project
● Procurement documents ● Confirm the organization’s willingness and
capability to work on the project
The inputs and activities of initiating process group are important from the exam perspective.
Exam Tips
Planning Process Group establishes the total scope of effort, objectives, and course of action required
to attain those objectives.
Inputs Actions taken
● Project charter ● Refine requirements and convert it into a scope
● Requirements given by the customer statement and the work breakdown structure
● Stakeholder register ● Get stakeholder approval and buy-in
● Stakeholder management strategy ● Develop the baseline scope, cost, and schedule
● Organizational process assets ● Select project team and determine their roles and
● Enterprise environmental factors responsibilities
● Teaming agreements ● Determine project’s quality standards and plan
● Resource calendars ● Framework for risk management, identification,
analysis, and response planning
● Determine what needs to be purchased
● Determine how to execute and control the project
● Document the project management plan
● Handle updates on the plan arising out of change
requests
8 Copyright 2014, Simplilearn, All rights reserved.
Executing Process Group
Executing Process Group completes the work defined in the project management plan to satisfy the
project specifications.
Inputs Actions taken
● Project management plan ● Manage stakeholder engagements
● Resource calendars ● Deliver the work packages as planned
● Project documents ● Implement quality assurance activities
● Enterprise environmental factors ● Produce project reports
● Seller proposals ● Remove project bottlenecks
● Approved change requests ● Organize team building activities
● Quality control measurements ● Organize training for the team members
● Make-or-buy decisions ● Conduct project progress meetings
● Source selection criteria ● Implement approved changes, corrective actions,
● Work performance report preventive actions, and defect repair
● Work performance information ● Finalize procurement arrangements and contracts
Monitoring and Controlling Process Group tracks, reviews, and regulates the progress and
performance of the project; identifies and initiates the changes to the plan when required.
Inputs Actions taken
● Deliverables ● Measure project performance against the baseline
● Work performance data ● Determine variances and take appropriate action
● Change requests ● Recommend changes, corrective, and preventive
● Organizational process assets action
● Project management plan and documents ● Facilitate conflict resolution
● Selected sellers ● Identify root causes of problems
● Obtain formal acceptance for the deliverables
● Administer contracts with sellers
● Control changes
● Conduct status review meetings, etc.
Closing Process Group finalizes the activities across all Project Management Process Groups to
formally complete the project, phase, or contractual obligations.
Inputs Actions taken
● Project plan and documents ● Confirm that all project requirements are met
● Accepted project deliverables ● Obtain formal signoff from customer
● Procurement documentation ● Make payment to all parties and update cost
● Organizational process assets records
● Enterprise environmental factors ● Complete contract closure
● Update lessons learned database
● Measure customer satisfaction
● Handover project deliverables to operations team
● Release resources from the project
a. Planning
b. Monitoring and Controlling
c. Initiating
d. Closing
a. Planning
b. Monitoring and Controlling
c. Initiating
d. Closing
Answer: b.
Explanation: Monitoring and Controlling (see PMBOK® Guide section 3.6). During project
closure the project manager reviews the acceptance documentation from scope validation
to ensure that all project requirements are completed.
a. Project charter
b. Organizational process assets
c. Enterprise environmental factors
d. Procurement documents
a. Project charter
b. Organizational process assets
c. Enterprise environmental factors
d. Procurement documents
Answer: a.
Explanation: Project charter is the output of the Initiating Process Group. All other options
are inputs to the Initiating Process Group.
a. Project manager
b. Functional manager
c. Team members
d. Stakeholders
a. Project manager
b. Functional manager
c. Team members
d. Stakeholders
Answer: a.
Explanation: The project manager is in control of the project throughout the project life
cycle.
a. Planning
b. Closing
c. Monitoring and Controlling
d. Initiating
a. Planning
b. Closing
c. Monitoring and Controlling
d. Initiating
Answer: d.
Explanation: The high level constraints of schedule and budget are determined during the
Initiating Process Group. The detailed planning is done during the Planning Process Group.
d. Cost and staffing levels are low at the start, peak as the work is carried
out, and drop rapidly as the project draws to a close
d. Cost and staffing levels are low at the start, peak as the work is carried
out, and drop rapidly as the project draws to a close
Answer: b.
Explanation: Stakeholder influences are greatest towards the beginning of the project.
Answer: a.
Explanation: In every project, all five Process Groups must be included but the level of
attention given to each Process Group will be governed by the project manager depending
on the project size and complexity.
• Exercise 1
• Exercise 2
• Exercise 3
This course is based on PMBOK® Guide – Fifth Edition Copyright 2014, Simplilearn, All rights reserved.
PMP, PMI, PMBOK is a registered mark of PROJECT MANAGEMENT INSTITUTE®
[1] Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Fifth
Edition, Project Management Institute, Inc., 2013, Page 50.
[2] Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Fifth
Edition, Project Management Institute, Inc., 2013, Page 51.