0% found this document useful (1 vote)
418 views11 pages

Preventive Maintanance Vacum Circuit Breaker (VCB) : S T A R

The document discusses preventive maintenance of vacuum circuit breakers (VCBs). It describes steps for removing the VCB from its compartment, racking it out, and cleaning its finger contacts with scotch breath and alcohol before lubricating with electrical grease. Key parts of the VCB are inspected, including bolts securing the coil and insulation and resistance values, which are tested by opening and closing the VCB. Once checks are completed, the VCB is reinstalled and tested before being normalized and put back into service.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
0% found this document useful (1 vote)
418 views11 pages

Preventive Maintanance Vacum Circuit Breaker (VCB) : S T A R

The document discusses preventive maintenance of vacuum circuit breakers (VCBs). It describes steps for removing the VCB from its compartment, racking it out, and cleaning its finger contacts with scotch breath and alcohol before lubricating with electrical grease. Key parts of the VCB are inspected, including bolts securing the coil and insulation and resistance values, which are tested by opening and closing the VCB. Once checks are completed, the VCB is reinstalled and tested before being normalized and put back into service.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
You are on page 1/ 11

PREVENTIVE MAINTANANCE VACUM CIRCUIT

BREAKER (VCB)
Disusun oleh : Fakhri Maulana Arsyad

Serve, Trustworthy, Accountable & Reliable


VACUM CIRCUIT BREAKER (VCB)

2 Serve, Trustworthy, Accountable & Reliable


VACUUM CIRCUIT BREAKER (VCB)

A – Open/closed auxiliary contacts


B – Geared motor for loading closing spring
C – Built-in closing spring loading lever
D – Mechanical signaling device for circuit breaker open/closed
E – Mechanical operation counter
F – Contacts for signaling spring loaded/discharged
G – Signaling device for closing springs loaded/discharged
H – Service releases
I – Closing push-button
L – Opening push-button
M – Operating mechanism locking electromagnet
N – Additional shunt opening release
O – Transient contact
P – Lock that prevents racking-in when door is open

3 Serve, Trustworthy, Accountable & Reliable


ALAT DAN BAHAN BAHAN

ALAT BAHAN
1. Insulation tester 1. majun
2. Resistence meter 2. Alkohol
3. Socket set ¼ inci 3. Scotchbreath
4. Obeng (+) dan (-) 4. No’ox (grease electrical)
5. Kunci L tuas VCB
6. Multi meter
7. Breaker analyzer *

4 Serve, Trustworthy, Accountable & Reliable


Preventive Maintenance VCB
• Keluarkan VCB dari kompartemen

1. Pastikan VCB sudah dalam kondisi open


circuit (lihat indicator on dan off pada
panel VCB.
2. Grounding kabel menuju ke utility,lihat
panel untuk mengetahui status grounding
3. Rack out kompartemen VCB, kemudian
cabut socket vcb dari panel
4. Pasang trolly dan Tarik vcb keluar dari
kompartemen

5 Serve, Trustworthy, Accountable & Reliable


Preventive Maintenance VCB
Periksa part part dari
VCB

1. Buka cover body


penutup kompartemen
VCB
2. Periksa baut kecil untuk
pengikat coil di bagian
bawah, pastikan baut
tidak kendor
3. Periksa nilai Insulation
dan resistance dari vcb
(tes open close vcb)

6 Serve, Trustworthy, Accountable & Reliable


Preventive Maintenance VCB

Periksa nilai Insulation dan resistance dari vcb (tes open close vcb)

7 Serve, Trustworthy, Accountable & Reliable


Preventive Maintenance VCB
Periksa nilai Insulation dan resistance VCB

8 Serve, Trustworthy, Accountable & Reliable


Preventive Maintenance VCB
Bersihkan finger contact vcb dengan mengguanak scotch breath, kemudian lap dengan alcohol
sampai kering dan oleskan tipis tipis electrical grease

9 Serve, Trustworthy, Accountable & Reliable


Preventive Maintenance VCB

• Pastikan semua kompartemen telah di cek kembali dan pasang kembali cover body vcb
kompartement, cek panel lv vcb dan pastikan semua baut tidak ada yg kendor.
• Masukan kembali VCB kompartemen dan posisikan dalam test position,test ON dan
OFF VCB sebelum di normalisasi.
• Normalisasi VCB dan buka grounding
• Vcb siap untuk dioperasikan .