0% found this document useful (0 votes)
131 views75 pages

State Highway Development Project: Date:06-08-2021

This document provides details about road improvement projects 293A, 293B, and 294 in Karnataka. It includes information about the name and location of the works, estimated costs, contractors selected, and progress updates. For each package, details are given on culverts constructed, utility shifting, tree cutting, and physical progress achieved to date. The work on all three packages is reported as not yet completed. Nine Tech Infra Solutions Pvt Ltd is named as the Project Management Consultant.

Uploaded by

Mohan Mylarappa
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
131 views75 pages

State Highway Development Project: Date:06-08-2021

This document provides details about road improvement projects 293A, 293B, and 294 in Karnataka. It includes information about the name and location of the works, estimated costs, contractors selected, and progress updates. For each package, details are given on culverts constructed, utility shifting, tree cutting, and physical progress achieved to date. The work on all three packages is reported as not yet completed. Nine Tech Infra Solutions Pvt Ltd is named as the Project Management Consultant.

Uploaded by

Mohan Mylarappa
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
You are on page 1/ 75

GOVT OF KARNATAKA

PUBLIC WORKS DEPARTMENT


 

State Highway Development


Project

Date:06-08-2021

1
Package no : 293
(A)Improvements to Sidlaghatta-Anekal- Road SH-35 from Km 94.18 to Km 102.48 (in selected
reaches) in Anekel Taluk of Bangalore Rural District Via Thamarasanahalli, T.Agrahara,
Bhuvanahalli to join SH-82, Chikkanahalli.
Name of Work (B)Improvements to road as a peripheral road MDR from S.K.F factory (near Hebbagodi police
station to road joining Dhoddathoguru MDR road from 0.00 km to 10.20 km (in selected reaches) in
Anekal Taluk of Bangalore rural District via new town, Sai baba temple, new road junction in
electronic city premises in Anekal.
Estimated Cost
27,12,57,000.00 
(Rs Lakhs)
CER No 51,52/2018-19 
Tender Amount
(Rs In Lakhs) (SR 2018- 22,70 ,47,505.34
19)
V.Prakash Reddy, Near Rama Temple, New Pet, Anekal Town,
Name of Contractor
Bangalore – 562106. 
Agreement No & Date 70/2019-20  Dated:08-08-2019
Date of Start 08-08-2019 
Date of Completion 07-07-2020 
Status of Work Not yet completed
Name of PMC M/s Ninetech Infra Solutions Pvt Ltd.
Progress Details

Length as per DPR Length as per Physical Progress till


Sl No Road
(In Km) Variation (In Km) date (In Km)

 1  A  6.82KM 7.83KM  -
 2  B  9.59KM - 9.39KM 
Variation Details

Variation Variation Revised Contract


Variation Approved % of Variation
Proposed Received Amount ( Rs In Lakhs)

 Yes  Yes -  0.00  0.00

Time Extension Details

Time
Time Extension Time Extension
Extension Time Extension Upto Time Extension in Days
Received Approved
Proposed

 Yes  Yes - -  - 
Shifting of Utilities
Electric Pole Shifting
Amount Agency
Sub Estimate Proposal Status of
Road Approved (Rs In Fixed /Not Remarks
Received Work
Lakhs) Fixed
 A Yes Yes  -  - In Progress   
 B Yes Yes  -   - In Progress   
Water Line Shifting
Amount Agency
Sub Estimate Proposal Status of
Road Approved (Rs In Fixed /Not Remarks
Received Work
Lakhs) Fixed
Fixed by
 A Yes Yes  -  Completed   
Contractor
Fixed by
 B Yes Yes  -  Completed   
Contractor
Tree Cutting
Amount Payement
Road Status of
Proposal Received Approved (Rs In Status Remarks
Work
Lakhs) (Paid/Not Paid )
 A Yes Yes  -  Not Paid  In Progress  
 B Yes Yes  -  Not Paid  In Progress  
Culvert Details

No. of Culverts as per


Sl No Road Executed Culverts Remarks
DPR

Total – 6Nos.
Deck Slab :94.70KM Deck Slab :94.70KM Completed

Deck Slab :96.39KM Deck Slab :96.39KM Completed

Deck Slab :96.56KM Deck Slab :96.56KM Completed


 1 293 A
Deck Slab :97.81KM Deck Slab :97.81KM Completed

Deck Slab :94.96KM Deck Slab :94.96KM Completed

Pipe Culvert:101.00KM Pipe Culvert:101.00KM Completed


Total – 8Nos.

2 293 B Deck Slab – 0.00KM Deck Slab – 0.00KM Completed

Deck Slab – 2.10KM


Deck Slab – 2.10KM Completed
Culvert Details

No. of Culverts as per Physical Progress till


Sl No Road Executed Culverts
DPR date (In Km)

Deck Slab – 4.31KM


Deck Slab – 4.31KM Completed
Deck Slab – 4.40KM
Deck Slab – 4.40KM Completed
Deck Slab – 5.11KM
Deck Slab – 5.11KM Completed
Deck Slab – 9.60KM
Deck Slab – 9.60KM Completed
Deck Slab – 10.20KM
Deck Slab – 10.20KM Completed
Pipe Culvert – 7.54KM
Pipe Culvert – 7.54KM Completed
Package: 293 A

Nine Tech Infra Solutions Pvt


Ltd…,Banglaore
Package: 293 B

Nine Tech Infra Solutions Pvt


Ltd…,Banglaore
Package no : 294
Improvements to Bangalore-Anekal-Bannerghatta Road SH-87 from Km
Name of Work 39.10 to Km 47.31 (in selected reaches) in Anekal Taluk of Bangalore Rural
District Via Connecting Hosur Border 
Estimated Cost
Rs.20,00,00,000.000 
(Rs Lakhs)

CER No 53/2018-19 

Tender Amount
(Rs In Lakhs) (SR 2018- Rs.16,05,44,087.48 
19)
Ganapathi stone crushers, Lakshmi Palace, Magadi main road,
Name of Contractor
Sunkadakatte, Bangalore-560091 

Agreement No & Date 165/2019-20 Dated 03-02-2020 

Date of Start 01-02-2020 

Date of Completion 01-01-2021 

Status of Work Not Yet Completed

Name of PMC M/s. Ninetech Infra Solutions Pvt. Ltd.


Progress Details

Length as per DPR Length as per Physical Progress till


Sl No Road
(In Km) Variation (In Km) date (In Km)

 1 294  8.21KM  - 3.00KM 


Variation Details

Variation Variation Revised Contract


Variation Approved % of Variation
Proposed Recevied Amount ( Rs In Lakhs)

 - -  -  - - 

Time Extension Details

Time
Time Extension Time Extension
Extension Time Extension Upto Time Extension in Days
Recevied Approved
Proposed

Yes Yes  -  -  -
Culvert Details

No. of Culverts as per Executed


Sl No Road Remarks
DPR Culverts

Total – 5nos.
Deck Slab – 41.700Km Deck Slab – 41.700Km Completed

Pipe Culvert – 42.32Km Pipe Culvert – 42.32Km Completed

 1 294 Pipe Culvert – 43.45Km Pipe Culvert – 43.45Km Completed

Pipe Culvert – 43.84Km Pipe Culvert – 43.84Km Completed

Pipe Culvert – 44.73Km Pipe Culvert – 44.73Km Completed


Shifting of Utilities
Electric Pole Shifting
Amount Agency
Sub Estimate Proposal Status of
Road Approved (Rs In Fixed /Not Remarks
Received Work
Lakhs) Fixed
 Work in
 294  Yes  Yes -   Self Execution
Progress
 
Water Line Shifting
Amount Agency
Sub Estimate Proposal Status of
Road Approved (Rs In Fixed /Not Remarks
Received Work
Lakhs) Fixed
294  Yes  Yes  - Self Execution  Completed  
Tree Cutting
Amount Payement
Road Status of
Proposal Received Approved (Rs In Status Remarks
Work
Lakhs) (Paid/Not Paid )
 
294  Yes  Yes  -  Not Fixed Tendered  
Package: 294

Nine Tech Infra Solutions Pvt


Ltd…,Banglaore
Package no :295
 (A) Improvements to Nelamangala - Chikkaballapura road SH-74 from Km 8.60 t o Km
13.00 & Km 31.40 to Km 32.40 & loop Road Km 0.00 to Km 2.90 (in selected reaches) in
Doddaballapura taluk of Bangalore Rural District Via Uddichikkanahalli cross,
Kanasavadi, Doddaballapura Town, Heggadihalli
(B) Improvements to KS road to Balenahalli road MDR from Km 0.00 to Km 7.51 and
Hadonahalli to Melekote MDR road from Km 0.00 to Km 0.50 (in selected reaches) in
Doddaballapura taluk of Bangaluru Rural Dist Via Gaddambachahalli Cross , Tubagere
Name of Work
Cross, Hadonahalli
(C) Improvements to Channapattna - Nelamangala road New SH from km 75.90 to Km
77.90 (in selected reaches) in Nelamangala Taluk of Bangalore Rural District Via
Bramanipura - Kavanapura - SRS Betta - Avverahalli - Kailancha - Nagohalli -
Hunasanahalli - Uragahalli - Bidahi - Ganakallu
(D) Improvements to Begur NH - 04 to join NH- 207 road MDR from Km 0.00 to Km 14.60
(in selected reaches) in Nelamangala Taluk of Bangalore Rural District

Estimated Cost
 Rs 38,20,45,000.00
(Rs Lakhs)

CER No 54,55,56 &57 /2018-19 

Tender Amount
Rs 31,25,90,866.63
(Rs In Lakhs)

Sri.M.Venkataramareddy, RG No 2469/2010-15, P.W.D. Class-I Contractor, No.36,


Name of Contractor
Mestrappa Building, 80 Feet road, Hennur main road, Bangalore-84  

Agreement No & Date 170/2019-20, Dated:02-03-2020 


Date of Start 08-08-2019 
Date of Completion 08-07-2020 
Status of Work Not Yet Completed
Name of PMC M/s Ninetech Infra Solutions Pvt. Ltd.
Progress Details
Length as per DPR Length as per Physical Progress till
Sl No Road
(In Km) Variation (In Km) date (In Km)
 1  A 7.94KM   - - 
 2  B  8.01KM  -  -
 3  C  1.93KM  -  1.93KM (Completed)
4 D 12.40KM - -
Variation Details

Variation Variation Revised Contract


Variation Approved % of Variation
Proposed Received Amount ( Rs In Lakhs)

295 A Yes - - - -
- - - - -
- - - - -
295 D Yes -  -  -  -
Time Extension Details

Time
Time Extension Time Extension
Extension Time Extension Upto Time Extension in Days
Received Approved
Proposed

Yes  - -  -  - 
Culvert Details

No. of Culverts as per


Sl No Road Executed Culverts Remarks
DPR

Total – 4 Nos.
Deck Slab – 1.100Km - Not yet started

Deck Slab – 1.200Km - Not yet started


 1 295 A
Pipe Culvert-10.71KM - Not yet started

Pipe Culvert-31.62KM - Not yet started

Total – 7 Nos.

Pipe Culvert-0.00KM
Pipe Culvert-0.00KM Completed
2 295B
Pipe Culvert-0.70KM Pipe Culvert-0.70KM Completed

Pipe Culvert-1.71KM Pipe Culvert-1.71KM Completed


Culvert Details

No. of Culverts as per


Sl No Road Executed Culverts Remarks
DPR

Pipe Culvert-3.10KM
- Not yet started
Pipe Culvert-4.70KM - Not yet started
295B
Pipe Culvert-6.10KM - Not yet started

Pipe Culvert-7.50KM
- Not yet started

Total – 1Nos.
3 295 C
Not yet started
Pipe Culvert – 76.45KM -

Total – 11Nos.

4 295 D Deck Slab – 2.45Km Not yet started

Deck Slab – 4.74Km


Not yet started
Culvert Details

No. of Culverts as per


Sl No Road Executed Culverts Remarks
DPR

Deck Slab – 4.92Km - Not yet started


Deck Slab –6.06Km - Not yet started

Deck Slab – 6.45Km - Not yet started

Deck Slab –7.10Km - Not yet started

Deck Slab –8.65Km Not yet started


-
4
Pipe Culvert–2.55Km
- Not yet started

Pipe Culvert–8.85Km - Not yet started

Pipe Culvert–9.36Km - Not yet started

Pipe Culvert–9.69Km - Not yet started


-Shifting of Utilities
Electric Pole Shifting
Sub Estimate Proposal Amount Agency Fixed Status of
Road Approved Remarks
Received (Rs In Lakhs) /Not Fixed Work
 A Yes Yes  - Not Fixed   -  
 B Yes Yes  - Not Fixed  -  
 C Yes Yes  - Not Fixed  Completed  
 D Yes Yes  - Not Fixed  -  
Water Line Shifting
Sub Estimate Proposal Amount Agency Fixed Status of
Road Approved Remarks
Received (Rs In Lakhs) /Not Fixed Work
 A Yes Yes  - Fixed  -  
 B Yes Yes  - Fixed  Completed  
 C Yes Yes  - Fixed  Completed  
 D Yes Yes  - Fixed  -  
Tree Cutting
Amount Payement
Road Status of
Proposal Received Approved (Rs In Status Remarks
Work
Lakhs) (Paid/Not Paid )
 A Yes Yes  - Not Fixed -   

 B Yes Yes  - Not Fixed Completed  

 C Yes Yes  - Not Fixed Completed  


 D Yes Yes  - Not Fixed  -  
Package: 295 B

Nine Tech Infra Solutions Pvt


Ltd…,Banglaore
Package: 295 C

Nine Tech Infra Solutions Pvt


Ltd…,Banglaore
Package no :296
A) Improvements to Devanahalli-Kempapura Road SH-96 from Km 0.00 to Km
5.00 (in selected reaches) in Devanahalli taluk of Bangalore Rural District B)
Improvements to Vijayapura - Shidlagatta road MDR from Km 7.60 to Km
Name of Work 12.00 (in selected reaches) in Devanahalli Taluk of Bangalore Rural District C)
Improvements to Chapparakallu - Thimmsandra - Rajanakunte road MDR
from Km 0.00 to Km 14.00 (in selected reaches) in Devanahalli taluk of
Bangalore Rural District
Estimated Cost
Rs.29,15,22,000.00 
(Rs Lakhs)
CER No 58,58,60/2018-19 
Tender Amount
Rs.24,04,30,075.00 
(Rs In Lakhs)
M/S B Munikrishnappa, J C extension, Vijayapura
Name of Contractor
Bangalore Rural District-592135
Agreement No & Date 171/2019-20 Dated: 02-03-2020 
Date of Start 02-03-2020 
Date of Completion  02-02-2021
Status of Work Not Yet Completed
Name of PMC M/s Ninetech Infra Solutions Pvt Ltd
Progress Details
Length as per DPR Length as per Physical Progress till
Sl No Road
(In Km) Variation (In Km) date (In Km)
 1  A 4.70KM  -  DBM 4.05 KM 
Proposed variation for
 2  B  4.35KM DBM 0.8000 KM
1.4 km
 3  C  13.64KM  -  -
Varition Details

Variation Variation Revised Contract


Variation Approved % of Variation
Proposed Received Amount ( Rs In Lakhs)

- - - - -
296B - YES - - - -
296C - YES -   - -  - 
Time Extension Details
Time
Time Extension Time Extension
Extension Time Extension Upto Time Extension in Days
Received Approved
Proposed
Yes -  -  -  - 
Culvert Details

No. of Culverts as per


Sl No Road Executed Culverts Remarks
DPR

Total -6Nos
Deck Slab – 1.760Km Deck Slab – 1.760Km Completed

Pipe Culvert -3.16Km Pipe Culvert -3.16Km Completed

Pipe Culvert -4.29Km Pipe Culvert -4.29Km Completed


 1 296 A
Pipe Culvert -4.63Km Pipe Culvert -4.63Km Completed

Pipe Culvert -0.87Km Pipe Culvert -0.87Km Completed

Pipe Culvert -0.95Km Pipe Culvert -0.95Km Completed

Total – 1 No.
2 296B
Deck Slab – 11.22KM - Not Yet Started
Culvert Details

No. of Culverts as per


Sl No Road Executed Culverts Remarks
DPR

Total – 14 Nos.
Deck Slab -0.00KM Deck Slab -0.00KM Completed

Deck Slab -2.60KM Deck Slab -2.60KM Completed

Deck Slab -2.735KM Deck Slab -2.735KM Completed

Deck Slab -3.29KM Deck Slab -3.29KM Completed


3 296C
Deck Slab -4.03KM Deck Slab -4.03KM Completed

Deck Slab -5.59KM Deck Slab -5.59KM Completed

Deck Slab -7.45KM Deck Slab -7.45KM Completed

Pipe Culvert-0.46Km Completed


Pipe Culvert-0.46Km
Culvert Details

No. of Culverts as per Physical Progress till


Sl No Road Executed Culverts
DPR date (In Km)

Pipe Culvert-1.56Km
Pipe Culvert-1.56Km Completed
Pipe Culvert-4.72Km Pipe Culvert-4.72Km Completed

Pipe Culvert-6.46Km Pipe Culvert-6.46Km Completed

Pipe Culvert-8.54Km Pipe Culvert-8.54Km Completed

Pipe Culvert-11.07Km Pipe Culvert-11.07Km Completed

Pipe Culvert-12.88Km Pipe Culvert-12.88Km Completed


Shifting of Utilities
Electric Pole Shifting
Amount Agency
Sub Estimate Proposal Status of
Road Approved (Rs In Fixed /Not Remarks
Received Work
Lakhs) Fixed
 A Yes Yes  - Self Execution  -  
 B Yes Yes  - Self Execution  -  
 C Yes Yes  - Self Execution  -  
-Water Line Shifting
Amount Agency
Sub Estimate Proposal Status of
Road Approved (Rs In Fixed /Not Remarks
Received Work
Lakhs) Fixed
 A Yes Yes  - Self Execution -   
 B Yes Yes  - Self Execution  -  
 C Yes Yes  - Self Execution  -  
Tree Cutting
Amount Payement
Road Status of
Proposal Received Approved (Rs In Status Remarks
Work
Lakhs) (Paid/Not Paid )
 A Yes Yes  - Not Fixed -   
 B Yes Yes  - Not Fixed  -  
 C Yes Yes  - Not Fixed  -  
Package: 296 A

Nine Tech Infra Solutions Pvt


Ltd…,Banglaore
Package no :297
(A) Improvements to Devanahalli-Kempapura road SH-96 from Km 25.50 to Km 28.98 (in
selected reaches) in Hoskote taluk of Bangalore Rural District Vijayapura Bypass
(B) Improvements to SH 35 Siddalagatta - Hosakote- Kadugodi- Anekal road to join
Name of Work Thoranahallidinne road MDR from Km 6.40 to Km 16.44 (in selected reaches) in
Hoskote Taluk of Bangalore Rural District Via Ammaranahalli, T Agrahara,
Buvanahalli SH 82, Chikkanakanahalli NH 75
Estimated Cost
Rs.16,38,87,000.00 
(Rs Lakhs)
CER No 61,62/2018-19 
Tender Amount
Rs.12,92,85,125.00 
(Rs In Lakhs)
M/s Haigreeva Infra Tech Projects Ltd.
Name of Contractor
No. 101, 4th main, NGEF Layout, Sanjayanagar, Bangalore-560094
Agreement No & Date 118/2019-2020 
Date of Start 24-10-2019 
Date of Completion  23-09-2020
Status of Work Completed
Name of PMC M/s Ninetech Infra Solution Pvt Ltd.
Progress Details

Length as per DPR Length as per Physical Progress till


Sl No Road
(In Km) Variation (In Km) date (In Km)

 1  A 3.48KM   - 3.48KM 
 2  B  10.01KM  -  10.01KM
Varition Details

Variation Variation Revised Contract


Variation Approved % of Variation
Proposed Recevied Amount ( Rs In Lakhs)

- - - - -

 -  -  -  -  -

Time Extension Details

Time
Time Extension Time Extension
Extension Time Extension Upto Time Extension in Days
Received Approved
Proposed

 - -  -  -  - 
Culvert Details

No. of Culverts as per Physical Progress till


Sl No Road Executed Culverts
DPR date (In Km)

Total – 4Nos.
Deck Slab-27.36KM Deck Slab-27.36KM Completed

Pipe Culvert – 26.8KM Pipe Culvert – 26.8KM Completed


 1 297A
Pipe Culvert – 28.30KM Pipe Culvert – 28.30KM Completed

Pipe Culvert – 28.60KM Pipe Culvert – 28.60KM Completed


Culvert Details

No. of Culverts as per


Sl No Road Executed Culverts Remarks
DPR

Total – 4nos.

Slab Culvert – 8.70Km Slab Culvert – 8.70Km Completed

 2 297B Slab Culvert – 10.1Km Slab Culvert – 10.1Km Completed

Slab Culvert -11.87KM Slab Culvert -11.87KM Completed

Slab Culvert – 12.10KM Slab Culvert – 12.10KM Completed


Shifting of Utilities
Electric Pole Shifting
Amount Agency
Sub Estimate Proposal Status of
Road Approved (Rs In Fixed /Not Remarks
Received Work
Lakhs) Fixed
 A NA NA -   Fixed Completed   
 B NA NA  - Fixed  Completed   
Water Line Shifting
Amount Agency
Sub Estimate Proposal Status of
Road Approved (Rs In Fixed /Not Remarks
Received Work
Lakhs) Fixed
 A Yes Yes  - Fixed Completed  
 B Yes Yes  - Fixed Completed  
Tree Cutting
Amount Payement
Road Status of
Proposal Received Approved (Rs In Status Remarks
Work
Lakhs) (Paid/Not Paid )
 A NA NA  - Fixed Completed  
 B NA NA  - Fixed Completed  
Package: 297 A Package: 297 B

Nine Tech Infra Solutions Pvt


Ltd…,Banglaore
GOVERNMENT OF KARNATAKA
STATE HIGHWAY DEVELOPMENT PROJECT
PHASE-04
Division : Nelamangala Circle : Bangalore

Name of Work: Providing Project Management Consultancy for SHDP Phase-IV


Works Under Bangalore District.
(Work Package Nos: 293, 294, 295, 296 & 297)

Checklist for Making Payments


Checklist for Scrutiny of Bill of Project Management Consultant (PMC)

Nine Tech Infra Solutions Pvt


Ltd…,Banglaore
1. Whether the Consultant has participated in preparing
and finalizing work programme prior to the commencement
of work or revisions during the progress of the work
keeping the interest of the Client

Status
Package %
Yes No Partly

293  
 
294   
 
295  0.20%
   
296 
   
297 
   

Nine Tech Infra Solutions Pvt


Ltd…,Banglaore
2. Whether the Consultant thoroughly checked the Detailed
Project Report (DPR) with the actual field conditions and
brought to the notice of the Client with suggestions and
economic alternatives

Status
Package %
Yes No Partly

293 
 
294 
 
295  0.20%
 
296 
 
297 
 

Nine Tech Infra Solutions Pvt


Ltd…,Banglaore
3. Whether the Consultant documented all project related
matters, including minutes of different meetings and
prepared periodical reports relating to time, cost and
quality

Status
Package %
Yes No Partly

293   
 
294   
 
295  0.20%
   
296 
   
297 
   

Nine Tech Infra Solutions Pvt


Ltd…,Banglaore
4. Whether the Consultant inspected and certified the
quality of materials available at the source for usage on the
specified work as per tender conditions/ specifications

Status
Package %
Yes No Partly

293   
 
294   
 
295  0.20%
   
296 
   
297 
   

Nine Tech Infra Solutions Pvt


Ltd…,Banglaore
5. Whether the Consultant assessed the adequacy of the
Men, Materials and the Machineries available at the work
site provided by the construction agency for execution of the
project(s), method of execution and regularly updated
informations regarding the availability of Men, Materials
and Machineries and took necessary action for expediting
the required progress of the work.
Status
Package %
Yes No Partly

293   
 
294   
 
295  0.20%
   
296 
   
297 
   

Nine Tech Infra Solutions Pvt


Ltd…,Banglaore
6. Whether the Consultant inspected, reported and certified
all the installations of the construction agency i.e. Quarry,
Crusher, Hot Mix Plant, Pug Mill Site, Quarters, Site Office,
Permanent Laboratory with full fledged testing
equipment's, Temporary Laboratory, Mobile Laboratory
and Ware Houses

Status
Package %
Yes No Partly

293   
 
294   
 
295  0.20%
   
296 
   
297 
   

Nine Tech Infra Solutions Pvt


Ltd…,Banglaore
7. Whether the Consultant conducted the Original Ground
Level (OGL) survey and setting out along with the
construction agency and the Engineer-in-charge

Status
Package %
Yes No Partly

293  
 
294   
 
295  0.20%
   
296 
   
297 
   

Nine Tech Infra Solutions Pvt


Ltd…,Banglaore
8. Whether the Consultant has verified the suitability of the
construction materials

Status
Package %
Yes No Partly

293   
 
294   
 
295  0.20%
   
296 
   
297 
   

Nine Tech Infra Solutions Pvt


Ltd…,Banglaore
9. Whether the Consultant has participated during
construction agency conduction of 100% Quality Control
tests

Status
Package %
Yes No Partly

293  
 
294   
 
295  1.50%
   
296 
   
297 
   

Nine Tech Infra Solutions Pvt


Ltd…,Banglaore
10. Whether the Consultant has issued non-conformance
letter to the construction agency when the quality of the
construction materials or the workmanship does not
conforms to the requirements

Status
Package %
Yes No Partly

293   
 
294  

295 0.20%
 
296
 
297  

Nine Tech Infra Solutions Pvt


Ltd…,Banglaore
11. Whether the Consultant has verified the obtain the
Design Mix obtained wherever necessary

Status
Package %
Yes No Partly

293   
294     
295     
0.50%

296     
297     

Nine Tech Infra Solutions Pvt


Ltd…,Banglaore
12. Whether the Consultants has conducted additional 10%
Quality Control Tests during construction to check the
requirements and workmanship

Status
Package %
Yes No Partly

293   
294     
295     
1.50%

296     
297     

Nine Tech Infra Solutions Pvt


Ltd…,Banglaore
13. Whether the Consultant established Temporary
Laboratories at each work site with the equipment's
required to conduct the QC tests of the ongoing nature of
works.

Status
Package %
Yes No Partly

293 
294  
295 0.50%

296

297   

Nine Tech Infra Solutions Pvt


Ltd…,Banglaore
14. Whether the Consultant has Mobile
Laboratory/Laboratories

Status
Package %
Yes No Partly

293   
294     
295     
0.40%

296     
297     

Nine Tech Infra Solutions Pvt


Ltd…,Banglaore
15. Whether the Consultant has fixed and report the photo
points

Status
Package %
Yes No Partly

293   
294     
295     
0.20%

296     
297     

Nine Tech Infra Solutions Pvt


Ltd…,Banglaore
16. Whether the Consultant took photographs or video graphs at the
designated photo points before commencement of work, during the progress
of the work at different stages and upon completion of the work and upload
the photographs or video graphs with proper description, documented the
progress or performance of the work, inspection of Various Officers
through Photos, Videos and other written documents in the Project
Monitoring System (PMS)

Status
Package %
Yes No Partly

293   
294   
295 2.00%
  
296
  
297   

Nine Tech Infra Solutions Pvt


Ltd…,Banglaore
17. Whether the Consultant prepared and submitted
Monthly/Quarterly Progress Report

Status
Package %
Yes No Partly

293   
294     
295     
2.00%

296     
297     

Nine Tech Infra Solutions Pvt


Ltd…,Banglaore
18. Whether the Consultant proposed and recommend with
a detailed report to the Client, the changes in the quantities
of the item in the contract agreement or the extra items and
changes in the scope of work if any, including its effect on
the contract amount and the project completion

Status
Package %
Yes No Partly

293   
294   
295   
1.00%

296   
297   

Nine Tech Infra Solutions Pvt


Ltd…,Banglaore
19. Whether the Consultant verified and recommend the
revised work programme if any submitted by the
construction agency

Status
Package %
Yes No Partly

293   
294
  
295 0.20%
  
296
  
297
  

Nine Tech Infra Solutions Pvt


Ltd…,Banglaore
20. Whether the Consultant provided necessary advices and
compliances to the department on construction agency’s
possible claims, etc

Status
Package %
Yes No Partly

293   
294     
295     
0.20%

296     
297     

Nine Tech Infra Solutions Pvt


Ltd…,Banglaore
21. Whether the Consultant informed the Client of any
potential problems that may arise in connection with the
works contract and make recommendations for possible
solutions

Status
Package %
Yes No Partly

293   
294     
295     
0.20%

296     
297     

Nine Tech Infra Solutions Pvt


Ltd…,Banglaore
22. Whether the Consultant deputed Technical personnel at
the Hot mix Plant Site / Pug Mill Site / Concrete Batch Mix
plant Site (If any) so that adequate supervision of work /
quality of material is ensured at all times during the
progress of work

Status
Package %
Yes No Partly

293   
294     
295     
0.80%

296     
297     

Nine Tech Infra Solutions Pvt


Ltd…,Banglaore
23. Whether the Consultant provided assistance to the
representatives of the Client / Construction agency relating
to ground survey control, markings, Quality Control testing
and progress of the project

Status
Package %
Yes No Partly

293   
294     
295     
0.80%

296     
297     

Nine Tech Infra Solutions Pvt


Ltd…,Banglaore
24. Whether the Consultant offered the professional advice
to the Client or shall make arrangements to obtain the
advice from the competent institutes whenever such a
situation warrants

Status
Package %
Yes No Partly

293   
294     
295     
0.20%

296     
297     

Nine Tech Infra Solutions Pvt


Ltd…,Banglaore
25. Whether the Consultant maintained Site Order Book at
the Site to take down the instructions of the Inspecting
Officers

Status
Package %
Yes No Partly

293   
294     
295     
0.20%

296     
297     

Nine Tech Infra Solutions Pvt


Ltd…,Banglaore
26. Whether the The Consultant prepared the draft
Inspection Reports of the officers from the Client
Department in consultation with the Engineer-in-charge
and submitted for approval of the competent authority

Status
Package %
Yes No Partly

293   
294     
295     
0.20%

296     
297     

Nine Tech Infra Solutions Pvt


Ltd…,Banglaore
27. Whether the Consultant prepared the Technical Reports
or make arrangements to obtain the same from the
competent institutions whenever necessary and submit to
the Client for approval

Status
Package %
Yes No Partly

293   
294   
295   
0.20%

296   
297   

Nine Tech Infra Solutions Pvt


Ltd…,Banglaore
28. Whether the Consultant maintained the log book of
construction machinery / man power deployed by the
construction agency indicating its adequacy, the idle period if
any, the condition of the machineries, etc., and adequately
document the same and report to the Client on weekly basis

Status
Package %
Yes No Partly

293   
294     
295     
0.40%

296     
297     

Nine Tech Infra Solutions Pvt


Ltd…,Banglaore
29. Whether the Consultant verify the quantities and items
for which the construction agency has claimed

Status
Package %
Yes No Partly

293   
294     
295     
2.00%

296     
297     

Nine Tech Infra Solutions Pvt


Ltd…,Banglaore
30. Whether the Consultant prepared and recommended for
approval the working Drawing and shall execute the work
as per the approved working Drawing

Status
Package %
Yes No Partly

293

294

295 1.00%

296

297

Nine Tech Infra Solutions Pvt


Ltd…,Banglaore
31. Whether the Consultant prepared as-built drawings for
the works executed by the construction agency and
submitted to the Client for approval

Status
Package %
Yes No Partly

293

294   
295 0.20%
  
296
  
297
 

Nine Tech Infra Solutions Pvt


Ltd…,Banglaore
32. Whether the Consultant ensured that adequate safety
measures are taken to protect lives/property during
execution of works including barricading

Status
Package %
Yes No Partly

293 
 
294 
 
295  0.20%
 
296 
 
297 
 

Nine Tech Infra Solutions Pvt


Ltd…,Banglaore
33. Whether the Consultant carried out necessary inspections,
supervise any remedial works needs to be carried out, prepare a
snag list (Balance Works to be done) if any and assist the Client
in issuing the Completion Certificate of the work

Status
Package %
Yes No Partly

293 
 
294   

295  0.20%
 
296 
 
297 
   

Nine Tech Infra Solutions Pvt


Ltd…,Banglaore
34. Whether the Consultant brought to the notice of the
Client any shortfall in the progress of the work, examine the
reasons for the shortfall, suggest necessary remedial
measures to make good the shortfall within a reasonable
time frame to avoid extension of stipulated construction
period
Status
Package %
Yes No Partly

293 

294 

295 0.20%

296 
 
297 
 

Nine Tech Infra Solutions Pvt


Ltd…,Banglaore
35. Whether the Consultant verified and certified the
Roughness Index measured prior to commencement of work
and after completion of the work

Status
Package %
Yes No Partly

293 
 
294   
 
295  0.20%
   
296 
   
297 
   

Nine Tech Infra Solutions Pvt


Ltd…,Banglaore
36. Whether the Consultant conducted weekly progress
review meeting and identify the activities falling short of
progress, areas of concern and suggest remedial measures to
make up the progress

Status
Package %
Yes No Partly

293 
 
294 
 
295  0.20%
 
296 
 
297 
 

Nine Tech Infra Solutions Pvt


Ltd…,Banglaore
37. Whether the Consultant prepared "as built" drawings of
all the works carried out by the construction agency and to
furnish the same to the Client duly certified both in physical
and digital form.

Status
Package %
Yes No Partly

293 
294 
295  0.50%

296 
297 

Nine Tech Infra Solutions Pvt


Ltd…,Banglaore
37. Whether the Consultant prepared and submitted to the
Client the Revised Estimate as and when each work is
completed by taking into account the actual quantities and
items executed

Status
Package %
Yes No Partly

293 
294 
295 0.50%

296 
297 

Nine Tech Infra Solutions Pvt


Ltd…,Banglaore