Zamzama Phase 2 Development: Preparation of JSA's
Zamzama Phase 2 Development: Preparation of JSA's
Zamzama Phase 2 Development: Preparation of JSA's
Preparation of JSA’s
Preparation of JSA’s
Supervisor believed
Pressure applied by
OK to work on Working at heights
Management (BHPB Work front is behind
unapproved procedure was not
and Descon) to project schedule
scaffolding as work followed
complete job quickly
required was minor
Failure to implement
Planning of Many activities had
actions as required
simultaneous work to occur Area HSEC advice
by local HSEC and
activities in same simultaneously was not followed
Scaffolding
area according to plan
inspector
Failure to follow
Perceived pressure working at height
Only one BHPB Scaffold Inspector protocols in
to commence work
approved scaffold requirements were switchroom
activities due to work
inspector is on site not followed
teams sitting idle
waiting for scaffold
to be inspected
Site supervisors
have not been fully
instilled with ‘Zero
Harm’ as a key
measure of success
(Primaryfactors
(Primary factorshighlighted
highlightedin
inred)
red)
Perceived pressure to commence work Planning to assess potential contingency activities where unforeseen DEL
activities due to work teams sitting idle delays occur in preparatory works (egg scaffolding).
waiting for scaffold to be inspected
Failure to implement actions as Specific ‘Realignment meeting’ to be presented to all field supervisors DEL
required by local HSEC and to reinforce that failure to follow up on advice from Descon field
Scaffolding inspector HSEC team will not be tolerated.
Absent/Failed defences Follow up Action Action By
Working at heights procedure Specific ‘Realignment meeting’ to be presented to all field supervisors DEL
was not followed of mandatory nature of all working at height procedures to be
emphasised.
Area HSEC advice was not Specific ‘Realignment meeting’ to be presented to all field supervisors DEL
followed to reinforce that failure to follow up on advice from Descon field
HSEC team will not be tolerated.
Pre-Start ‘Take Five’ sessions to be conducted for all activities – DEL
involving HSEC member. All issue identified to be addressed prior to
commencing work
Scaffold inspector requirements Specific ‘Realignment meeting’ to be presented to all field supervisors DEL
were not followed to reinforce that disregarding tagging procedures is a dismissible
offence and will not be tolerated.