Ce Laws, Contracts and Specifications
Ce Laws, Contracts and Specifications
Ce Laws, Contracts and Specifications
AND SPECIFICATIONS
TOTAL PROJECT COST: LEGAL,
LAND, ADMINISTRATION, STAFFING
AND FINANCIAL COSTS, AND
CONTINGENCY ALLOWANCE.
Total Project Cost
• Direct cost- (material+labor+equipments)
• Indirect cost- (contractor’s profit+OCM)
• Taxes
-The large company decided that they would need a performance bond
from us to ensure that they got their payment.
Surety Bonds
- A surety bond is simply the agreement between three parties: Principal, Surety
and Obligee. It Is a promise by a surety or guarantor to pay one party (the
obligee) a certain amount if a second party (the principal) fails to meet some
obligation, such as fulfilling the terms of a contract. The surety bond protects the
obligee against losses resulting from the principal's failure to meet the obligation.
Principal
Surety Obligee
Contractor’s All Risk Insurance Bond (CARI)
- Will cover projects from various risks during construction of a building, plant,
warehouse, townhouse, resort, office or store renovation in a mall, house or any
construction/ renovation projects. CARI covers all risk associated with all type of
civil construction risks.
Coverage:
Fire, lightning, flood, inundation, tsunami, windstorm of any kind, earthquake,
subsidence, landslide rockslide burglary, bad workmanship lack of skill, negligence,
malicious acts, and human error. Also includes bodily injury&/or property damage
aggregate limit.
To get covered one must provide the following information:
As the project moves forward from the study and report phase through the final
design phase and finally to construction award, more becomes known about
project details and costs, until at the completion of the project, the final project
cost becomes a known quantity.
To provide for intangible costs, contingencies should routinely be added to the
basic cost estimate. It is common practice to add 20% or more to the estimate
probable total project cost at the completion of the study end report phase,
reducing this to perhaps 10% at the completion of the final design and perhaps to
5% when the construction bids become known. Larger or more complex projects
may require higher contingencies.
The ABC shall be composed of the Direct Cost and the Indirect Cost.
B.2 Contingencies – ranges from 0.5-3% of the EDC. These include expenses for meetings,
coordination with other stakeholders, billboards( excluding project billboards which s pay item
under the General Requirements), stages during ground breaking & inauguration ceremonies, and
other unforeseen events.
B.3 Miscellaneous Expenses - ranges from 0.5-1% of the EDC. These include laboratory tests for
quality control and plan preparation.
B.4 Contractor’s Profit Margin – shall be 8% of the EDC for projects above P5million and 10% for
Projects P10million and below.
B.5 VAT Component – shall be 5% of the sum of the EDC, OCM and profit.
B.6 The following items shall not be subjected to OCM and Profit mark-up:
B.6.1 Mobilization and demobilization
B.6.2 Provision of Service Vehicle
B.7 The following non-civil works items shall not be subjected to OCM mark-up:
B.7.1 Field/Laboratory offices & living quarters (Rental Basis)
B.7.2 Furnishing of furnitures, laboratory equipment, survey Equipment and Consumables
B.7.3 Assistance to the Engineers
B.7.4 Photographs
B.7.5 Health and safety
B.7.6 Traffic Management
B.7.7 Environmental Compliance
B.7.8 Communication Equipment, etc.