Technological University Department of Civil Engineering
Technological University Department of Civil Engineering
Technological University
Department of Civil Engineering
Presented By:
Daw Cho Wai Phyo Kyaw
Demonstrator
Department of Civil Engineering
Chapter-1 (The Concept of Cost Control)
CONTENTS
The concept of cost control
Historical development of cost control process
Need for cost control
2 Main aims of cost control
Role of Quantity Surveyor
Tendering arrangements
Types of contract
Comparison of cost planning and approximate estimating
Course Outcome
3 The Concept of Cost Control
Cost control aims - ensuring that resources are used to
the best advantage
- to operate an effective cost control procedure during the
design stage of a project to keep the total cost of scheme
within the building clients budget
4 Historical development of cost control process
Cost planning, as at present operated , is the logical extension of a
process which has continued since the days of the eighteenth-century
measures, who were employed to measure and value the cost of the
work after it was both designed and executed.
Main contractor system to became fully operative in the early
nineteenth century, implied price competition before construction which
previously rarely occurred.
5 Need for cost control
There is greater urgency for the completion of projects to reduce the amount of
unproductive capital or borrowed money and few building clients have sufficient time for
the redesign of schemes consequent upon the receipt of excessively high tenders.
Building client’s needs are becoming more complicated,more consultants are being
engaged and the estimation of probable costs becomes more difficult.
The move towards reduced waste and greater use of scarce resources creates
the need for more accurate forecasting and improved cost control.
7 Need for cost control
There is an increasing demand for integrated design to secure an efficient combination
of building and services elements in complex developments, such as hospitals.
Rising energy costs necessitate costing alter native heating and thermal insulation
measures.
More attention is being paid to life cycle costing and total cost appraisal.
To keep total expenditure within the amount agreed by the client
Role of Quantity Surveyor
9
Tendering arrangements
All tendering procedures aim at selecting a suitable contractor and
obtaining from him at an appropriate time an acceptable offer, or tender,
upon which a contract can be let.
What is contract?
Contract is an agreement enforceable by law.
A contract is an exchange of promise between two or more parties to do.
Contractors operate under a contract arrangement with the owner.
12 Types of Contract
In this type of contract all the cost that the contractor incurs during the
project are charge back to the client, and thus the contractor is
reimbursed costs.
14
15 Kinds of cost-reimbursable contracts
Cost plus
percentage contract
Cost-reimbursable
contract (or) Cost Cost plus fixed fee
plus contract contract
Cost plus
fluctuating fee
contract
Cost plus percentage contract (CPPC)
Cost plus fixed fee contracts are those in which the sum paid to
the contractor will be the actual cost incurred in the execution of the
work plus a fixed lump sum which has been previously agreed upon
and does not fluctuate with the final cost of the project.
Although it is to his advantage to earn the fixed fee as quickly as
possible and so release his resources for other work
It is superior to the cost plus percentage type of contract.
18 Cost plus fluctuating fee contracts
In this type of contract consultants design the building to a partial stage or scope
design, the competitive tenders are obtained from contractors that develop and
complete the design and then construct the building
Develop and construct requires analysis/creativity of a design team
And then, acceptance/implementation by a construction team which may also be
chosen in competition
Management Contracting
In management contracting the contractor is paid a fee to
manage the construction of a project on behalf of the client and
it is therefore a contract to manage, procure and supervise as
apposed to a contract to build.
Thus the management contractor is a member of the client’s
25 team and works closely with the professional consultants
Comparison of Cost Planning and Approximate Estimating
27
Cost Check
The process of checking the estimated cost of each
section or element of the building as the detailed designs
are developed, against the cost target set against it in the
cost plan.
28
Cost Analysis
29
Approximate Estimating
32
Cost in Use
33
Cost Study
To reveal the distribution of costs between the various parts of the
building.
To relate the cost of any single part or element to its importance as a
necessary part of the whole building.
To compare the costs of the same part or element in different building.
To consider whether costs could have been apportioned to secure a
34
better building.
To obtain and use cost data in planning future buildings and
To ensure a proper balance of quantity and quality within the
appropriate cost limit.
Cost Control
35
36 Cost Management
The synthesizing of traditional quality surveying skills with
structured cost reduction or substitution procedures using a multi-
disciplinary team.
37 Cost Planning
Interpreted as controlling the cost of a project within a
predetermined sum during the design stage, and
normally envisages the preparation of a cost plan and the
carrying out of cost checks.
Course Outcome
38