Content: MPT FTTH Project Operation Team Presentation
Content: MPT FTTH Project Operation Team Presentation
Content
MPT FTTH Team Structure
OM
DyGM
Doc Control Project Engineer(NZA) Project Engineer(ZNW)
Kissflow Team
3U Kyaw Sann Lwin Junior Engineer BE - EC (Thesis) Almost one year in FTTH
4U Toe Shwin Ko Junior Engineer G.T.I (EC) Almost one year in FTTH
5U Aye Chan Lwin Junior Engineer BE-EP Fresher
6U Naing Ye Aung Junior Engineer BE-EC Experience in Micro Wave(BTS)
7U Yin Thein Project Technician Grade (11) Old Service in MPT
8U Aung Kyaw Swar Line Man Third Year (Bot.,) North Dagon
9U Aung Zin Htet Line Man Third Year (Bot.,) Fresher
10U Naing Win Htike Line Man Grade (11) Fresher
11U Ye Wint Kyaw Line Man Grade (11) FTTH in Fortune and South Dagon
12U Tin Tun Aung Line Man B.Sc (Physics) South Dagon
13U Swan Khant Htet Paing Line Man Grade (11) Fresher
14U Hla Aung Line Man Grade (11) Fresher
15U Shine Htet Aung Line Man Grade (11) Fresher
MPT FTTH Skill Requirement
MPT FTTH Team Structure
Proposed to MPT Team(1)
Technician(1)
Engineer
Labour(2)
Team(2)
Technician(1)
Project
Engineer
Engineer
Labour(2)
Team(3)
Technician(1)
Engineer
Labour(2)
MPT FTTH Introduction
Our Capabilities
Our Capacity
1. Day 1 capacity 1 Teams (1xEngineer, 1xTechnician, 2xHard Labour)
2. We can do 4 circuit CID activation per a day by one team.
3. We can maximize up to 12 circuit CIDs activation per a day by three teams.
MPT FTTH Activation
Team Assignment
Phase State and Region Area Number of FAT Number of subscribers Teams
First of all, we have to do cable laying/installation from second splitter to access point of electrical power
at customer’s house.
At the second step, we have to do termination and splicing for drop cable to connect to FAT.
Termination
point
MPT FTTH Technical Implementation
Splicing Set-Up to
point wall
MPT FTTH Technical Implementation
We will use MT9090 µOTDR to measure Optical power level. We have to use 1310nm and 1490nm since this network is
GPON Network.
1310nm 1490nm
MPT FTTH Technical Implementation
6. ONT(Optical Network Terminal) setting-up and Patch Cable connection (ATB to ONT)
In this step, check LED indicator of PON and LOS. If the ‘’LOS” LED indicator is red, check connection of Patch cable(ATB to
ONT),if else check VIP and need to do cleaning connector using cleaning kit(STICKLERS). If the “PON” LED indicator is green in
stable, it is access Internet.
7. ONT Configuration
In this step, we have to do configuration of Wi-Fi SSID name and PASSWORD, set Number of Associated Devices, etc…
User name
Type and
192.168.1.1 Password
MPT FTTH Technical Implementation
Password/
Key SSID
Name
After all
click
“Submit”
MPT FTTH Technical Implementation
8. Network Testing
PING Test :
Open computer and go to “Run” (Press both of window key and R key at the same time).
Type “cmd” in the “Run” box, and will appear C:\Windows\System32\cmd.exe box
PING google.com, youtube.com and dota2.com in the C:\Windows\System32\cmd.exe
Speed Test :
Open internet browser (Mozilla Firefox or Google Chrome, ie, etc…)
Go to Web address bar and type “speedtest.net”
Select “MPT” Sever and Click “GO”
MPT FTTH Technical Implementation
Open computer and go to “Run” (Press both of window key and R key at the same time)
Type “cmd” in the “Run” box, and will appear C:\Windows\System32\cmd.exe box
Type “cmd”
MPT FTTH Technical Implementation
PING google.com, youtube.com and dota2.com in the C:\Windows\System32\cmd.exe
Select “MPT”
Click
“GO”
MPT FTTH Technical Implementation
Working Standard
MPT FTTH Technical Implementation
9. Reporting
To Do Improvement
•Weekly project meeting(Every Saturday)
•Sharing information
•Review for every issues
Review for all projects
Thilawa GEPON project Eager Last-Mile transmission
•Project engagement >> Good •Project engagement >> Fair
•Expense >> Good •Expense >> No good
•Scope >> Clear •Scope >> Clear
•Planning and operation >> Good •Planning and operation >> Not Good
•Done successfully •Done successfully
Thank you
Zarni Win