Supplier Standardised Process Guide: - Raw Material Testing - RM Processing - Forging

The document provides guidelines for the forging process from raw material to final product. It discusses controlling raw material testing and processing, including forging, heat treatment and inspections. Key steps include testing raw materials, separating materials by type and heat, metallurgical testing, and maintaining quality controls through each stage of cutting, forging and heat treating operations. The overall goal is to standardize processing and implement controls to ensure product quality and consistency.

Uploaded by

Bhavna Acharya
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
276 views22 pages

Supplier Standardised Process Guide: - Raw Material Testing - RM Processing - Forging

The document provides guidelines for the forging process from raw material to final product. It discusses controlling raw material testing and processing, including forging, heat treatment and inspections. Key steps include testing raw materials, separating materials by type and heat, metallurgical testing, and maintaining quality controls through each stage of cutting, forging and heat treating operations. The overall goal is to standardize processing and implement controls to ensure product quality and consistency.

Uploaded by

Bhavna Acharya
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
You are on page 1/ 22

Supplier standardised process guide

- Raw material testing


- RM Processing
- Forging

Unique Forgings(India)Pvt .Ltd 1


Forging process control summery as per below

Raw
Material
Yard
Control
Ultrasonic Cutting
Inspection operation
Control control
Forging
Process
Control
MPI Forging Process
Inspection Control
Control
Heat
Treatmen
t Process
Control

Unique Forgings(India)Pvt .Ltd 1


2
Guideline summery as per below

Under stand
the
Drawing for
Proper Material
Sepcifcatio Purchasing
Tagging to all
ns of
Inspected
Raw
recieved
material
Lot Raw
Material Initial
Metallurgical Guideline Inspection of
Inspection material before
as per control unloading
plan Seperate
for received lot Unloading
of all received
material in material
yard.

Unique Forgings(India)Pvt .Ltd 2


Steel Mill TC

Understand the Drawing


for material
Specifications before
purchasing

Steel Steel Process Cleanliness Insp. Metallurgical Crack & Fracture


requirements details detials Inspections Testings

A.Steel Grade & Gas A.Steel A. Microstructure A.Surface


DWM A.Inclusion
Rej level req. Manufacturing Rating B. Grain size condition
CC / B.Approved Steel Mill Route B. Macro & C. Decarb level B. MPI
PPM List B. Rolling Upset Test D. Hardness Testing
C. Required Bar Input size C. Step
C. Rolling- Reduction E. Jominy req. C.Ultrasonic
For Forging down
Problems D.Spark & spectral Ratio C. Mechanical testing
test
Bank / Theme testing Properties D. Blue
fracture
test
Needs to understand the all metallurgical inspections as per customer
requirements as given above(Steel Mill TC attached for reference.

Unique Forgings(India)Pvt .Ltd 3


Unique Forgings(India)Pvt .Ltd 4
Unique Forgings(India)Pvt .Ltd 5
Raw Material Yard Contol
Do’s :
7. 100% Spark & spectral
test for RM bars to detect
mix up of grade.

Unique Forgings(India)Pvt .Ltd 6


Raw Material Yard Contol
Do’s :
1. Unload RM in different
areas with
-Heat no.
-Steel grade
-Dia of bar.
2. Tag material as WIP/ OK
after testing.
3. Use ‘FIFO’ Tag/sticker.
4. Paint both end of bar as
per colour code Chart.
5. Paint along length of RM
bar as per chart.
6. Move NOT OK RM to
scrap yard.
Unique Forgings(India)Pvt .Ltd 7
Raw Material Yard Contol
Don’ts :
1. Don’t unload or mix
condition, unbundled
RM.
2. Don’t store Different
grade and
similar/close dia
material.
3. Donot mix different
heat of same
grade/steel mill/ dia
together.
4. Donot store
rejected
‘RM’ with ‘OK’ RM
Unique Forgings(India)Pvt .Ltd 8
Metallurgical Testing of RM
1. Steel grade ( Third party inspection.
2. Jominy test( Third party inspection.
3. Inclusion rating( Third party inspection.
4. Microstructure Inspection
5.Grain Size
6.Hardness
7. Macro
sample
inspectio
n
8. Upset
test
9. 100% or
End piece
of bar
Unique Forgings(India)Pvt .Ltd 9
Metallurgical Testing of RM

Unique Forgings(India)Pvt .Ltd 10


Unique Forgings(India)Pvt .Ltd 11
Unique Forgings(India)Pvt .Ltd 12
Manufacturing facility with adequate controls

Unique Forgings(India)Pvt .Ltd 13


Cutting Operation
Do
Control
1-Full bar
colour coding
before cutting

2.Check
diameter of
loaded bar
as a 100%
frequency as
per control
plan
Mahindra
Unique CIE Automotive Ltd.
Forgings(India)Pvt .Ltd 15
Cutting Operation DONTs
Control :

1-Bar not coloured fully

2- Checking frequency of diameter of


bar not check as per control plan

Unique Forgings(India)Pvt .Ltd 15


Cutting Operation Control-End piece Segregation
DOs:
1-100% segregation of end piece not
mix in regular cutting bar
2.Scrap the end piece not keep in shop
flower to make conflict

Unique Forgings(India)Pvt .Ltd 16


Cutting Operation Control-End piece
Segrigation DONTs:
1-No poka-yoke system to separate
removal of end piece
2.End piece mix in regular cut bar
pallet.
3.End piece kept on flower

Unique Forgings(India)Pvt .Ltd 17


Cut bar Ready for forging
DOs:
Proper tagging of cut bar pallet
1. RM grade
2. Heat code
3. Bar Size
4. Qty
5. Date, shift & operator codes

Unique Forgings(India)Pvt .Ltd 18


Cut bar Ready for forging
DONTs:
No tag
Cut pallet
Overflow
ing pallet
Similar size bar adjacent to the
pallet.

Unique Forgings(India)Pvt .Ltd 19


Forging Process Control- Pyrometer
DOs:
Pyrometer should be in
Working condition during
forging process

Verify Normal Working of


overheat & Underheat
poka-yoke

Unique Forgings(India)Pvt .Ltd 20


Forging Process Control- Pyrometer
DONTs:
Working of forging press or
hammer, without working of
temperature pyrometer.

Abnormal or non-working of
overheat & Underheat
poka- yoke

Unique Forgings(India)Pvt .Ltd 21