Pressure Test System To Demonstrate Integrity: by Anil Kumar Saxena
Pressure Test System To Demonstrate Integrity: by Anil Kumar Saxena
Pressure Test System To Demonstrate Integrity: by Anil Kumar Saxena
By
Anil Kumar Saxena
Pressure testing is required by most piping codes to verify that a
new, modified or repaired piping system is capable of safely
withstanding its rated pressure and is leak tight.
Compliance to piping codes may be mandated by regulatory and
enforcement agencies , insurance carriers ,or the terms of the
contract for the construction of the system. Pressure testing
whether or not legally required serves the useful purpose of
protecting workers and the public.
Pressure testing may also be used to establish a pressure rating
for a component or special system for which it is not possible to
establish a safe rating by calculation. A prototype of the
component or system is subjected to a gradually increasing
pressure until measurable yielding first occurs or alternatively ,to
the point of rupture. then by using derating factors specified in the
code or the standard appropriate to the component or system. it
is possible to establish a design pressure rating from the
experimental data
Leak Testing Methods
Pt = 1.5 PST / S
.
8). Open ends of piping where blanks cannot
be used e.g. pumps, compressors, etc. shall
be blinded off by using standard blind flanges
of same rating as the piping system being
tested.
9) Indicating pressure gauges mounted locally
may be tested with the line, provided the test
pressure is not in excess of their scale
ratings.
22 mm(7/8 inch) & thicker -Top third of tank 230 mm (9in. )/hr.
- Middle third of tank 300 mm (12 in.) / hr
--Bottom third of tank 460 (18 in. ) / hr.
Filling may continue which elevation measurements are
being made as long as the change in water elevation for
a set of readings does not exceed 300 mm(12in.)
Unless waived on the data sheet, the manufacturer shall
make shell elevation measurements in accordance with
the following.
1). Shell elevation measurements shall be made at
equally-spaced intervals around the tank circumference
not exceeding 0.8 m(32 ft)The minimum number of shell
measurement points shall be eight.
2). Observed elevations shall be referred to a
permanent bench mark. The level instrument shall be
set up at least 1.5 times tank diameter away from the
tank when tank elevation readings are taken. six sets of
settlement readings are required.
a. Before start of the hydro test
b. With tank filled to ¼ test height (+/- 600mm[12ft])
c. With tank filled to ½ test height (+/- 600 mm[12 ft])
d. With tank filled to ¾ test height (+/- 600 mm[12 ft])
e. At least 24 hours after the tank has been filled to the
maximum test height. This 24 hrs period may be
increased to duration specified on the data sheet if the
purchaser so requires for condition such as;
1) The tank is he first one in the area.
2) The tank has a larger capacity then any other existing
tank in the area.
3) The tank has a higher unit bearing load than any other
existing tank in the area.
4) There is a question regarding the rate or magnitude of
settlement that will take place.
f. After tank has been emptied of test water.